S2S Cycleway & Footway Interim Works (Bull Road to Causeway Road)
Presentation to Elected Members 11th November 2015
S2S Cycleway & Footway Interim Works
1
S2S Cycleway & Footway Interim Works (Bull Road to Causeway - - PowerPoint PPT Presentation
S2S Cycleway & Footway Interim Works (Bull Road to Causeway Road) Presentation to Elected Members 11 th November 2015 S2S Cycleway & Footway Interim Works 1 OVERVIEW OF THE SCHEME Cycleway and Footpaths S2S Flood Interim Defence
S2S Cycleway & Footway Interim Works
1
2
Part 8 Planning Approval May 2013
3
Cycleway Required New Sections of Seawall
New watermain laid during excavation Sea Defence Element Added to Seawalls
Results in Greater Efficiency in Planning / Design / Procurement
Less Disruption to the SAC / SPA and Residents Better Value for Money
Western Carriageway (St. Anne’s Park/Properties side)
Eastern Carriageway (Seaward Side)
carriageway (4.0m wide two-way cycle track and 2m wide concrete footpath);
works to improve existing seawall;
public lighting.
Overall
upgraded public lighting throughout the scheme;
Missing link in an overall 8km cycle track around North Dublin Bay
4
Advertised:
website
Dec 2012.
Erected Plans and particulars available for public inspection for a 6 week period up to 4th February 2013 at :
Counter, Planning Department.
Presented to the North Central Area Committee:
5
Public information Meeting:
in Belgrove Girls School Hall. Hosted by the Clontarf Residents Association and attended by circa 180 people. Engineers present with drawings
from members of the public.
Follow-up meeting:
Civic Centre, Coolock. Engineers present and dealt with any additional or new queries that had not been addressed in the consultation process.
6
7
8
9
10
11
Improved Access along Shoreline Tourism & Recreation Renovation of Tram Shelter
12
Energy Efficient LED Lighting Reduced Noise Pollution Vulnerable Road Users
13
NEW QUADRANT ENTRANCE DESIGN IMPROVE VIEW AND ACCESS TO TREE OF LIFE SCULPTURE
14
COMPENSATORY PARKING AT WOODEN BRIDGE DUE TO LOSS OF PARKING ON CARRIAGWAY
15
RESTAURANT UP TO DOLLYMOUNT AVENUE
AND PART OF DOLLYMOUNT AVENUE SIDE ROAD
16
17
CURRENTLY UNDER CONSTRUCTION FOOTPATH / CYCLEWAY & ROAD PAVEMENT STILL TO BE CONSTRUCTED
18
19
20
21
22
23
24
– Smooth F4 concrete finish with new coping.
– Ready mixed smooth render finish with new coping.
25
Wall height adjustments are as follows:
inches). First 25m no level change. New average wall height = 540mm (21 inches).
(5 inches) and new wall construction. New average wall height = 580mm (23 inches).
existing wall heights. New average wall height = 690mm (27 inches).
metres to match existing levels, no level adjustment to retained wall. New average wall height = 450mm (18 inches).
new coping to be installed. New average wall height = 700mm (28 inches) with maximum wall height = 975mm (39 inches) – same as existing.
wall height = 800mm (32 inches).
690mm (18-27 inches). New average wall height = 840mm (33 inches) with maximum wall height = 1,138mm (45 inches) including 75mm (3 inch) coping.
up to 975mm (38.4 inches). The max height of our current wall north of this is 1,063mm (42 inches) excluding coping, which would be 1,138mm (45 inches) allowing for a 75mm (3 inch) coping.
26
27
28
29
30
31
32
33
34
35
Distance from Howth Road to Baldoyle Road is 2.1km (1.3 miles) – almost identical in length to this scheme. Old sea wall is 0.7m (27.6 inches) to 1m (39.4 inches) high along the 2.1km length. Depending on the relative road level the wall does restrict views of the foreshore at times although Howth is clearly visible. This length of road is much straighter and does not have a bend or camber on the road like there near the pond at St. Anne’s Park that would restrict views for car drivers even further.
36
37
16% 26% 34% 8%
IN ROAD SURFACE LOWER RELATIVE TO FOOTPATH / WALL (Max = 0.5m).
38
1996 – 2011: 163 accidents 50% of Serious and Fatal Accidents involved Pedestrians
39
Reduced Carriageway Width (2 x 3m)
Upgraded Junctions along route
Improved Driver Behaviour Reduced speed limit at north end 60km/h → 50km/h Reduced speeds - 85%ile currently 57.3km/h
Removal of Driver/Cyclist Conflict
40
visibility and safety for pedestrians crossing junctions.
impaired people to cross the junction, as well as people will child buggies.
to corners thereby blocking visibility for pedestrians and other drivers.
41
42
43
20 40 60 80 100 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 MSL in mm ODM
Dublin Annual Mean Sea Level 2000 – 2013
(Provisional)
Observed Annual … 44
Flood Zone A Dark Green; no wave action modelled. Flood Zone B Lighter Green; no wave action modelled.
45