S2S Cycleway & Footway Interim Works (Bull Road to Causeway - - PowerPoint PPT Presentation

s2s cycleway footway interim
SMART_READER_LITE
LIVE PREVIEW

S2S Cycleway & Footway Interim Works (Bull Road to Causeway - - PowerPoint PPT Presentation

S2S Cycleway & Footway Interim Works (Bull Road to Causeway Road) Presentation to Elected Members 11 th November 2015 S2S Cycleway & Footway Interim Works 1 OVERVIEW OF THE SCHEME Cycleway and Footpaths S2S Flood Interim Defence


slide-1
SLIDE 1

S2S Cycleway & Footway Interim Works (Bull Road to Causeway Road)

Presentation to Elected Members 11th November 2015

S2S Cycleway & Footway Interim Works

1

slide-2
SLIDE 2

Cycleway and Footpaths

Flood Defence

New Watermain

S2S Interim scheme

OVERVIEW OF THE SCHEME

2

Part 8 Planning Approval May 2013

slide-3
SLIDE 3

BENEFITS OF COMBINING SCHEMES

3

Cycleway Required New Sections of Seawall

New watermain laid during excavation Sea Defence Element Added to Seawalls

Results in Greater Efficiency in Planning / Design / Procurement

Less Disruption to the SAC / SPA and Residents Better Value for Money

slide-4
SLIDE 4

Western Carriageway (St. Anne’s Park/Properties side)

  • Kerb realignment and footpath works on the western side.

Eastern Carriageway (Seaward Side)

  • 2km of cycle and pedestrians facilities on the eastern side of the existing

carriageway (4.0m wide two-way cycle track and 2m wide concrete footpath);

  • Improved flood defences along route and two new sections of retaining wall and

works to improve existing seawall;

  • Proposed services include improved drainage system, watermain and upgraded

public lighting.

Overall

  • Streetscape improvement – new road surface, footpaths, traffic signals, cycle track and

upgraded public lighting throughout the scheme;

  • Renovation of Dollymount Tram Shelter;
  • Enlarged and upgraded public car park at St. Anne’s Park;
  • Estimated Program Duration: 16+ months;
  • Projected completion date: Q4 2016.

Overview of Scheme

Missing link in an overall 8km cycle track around North Dublin Bay

4

slide-5
SLIDE 5

Public Consultation Undertaken

Advertised:

  • Dublin City Council

website

  • Irish Times Fri 14th

Dec 2012.

  • 14 Site Notices

Erected Plans and particulars available for public inspection for a 6 week period up to 4th February 2013 at :

  • Dublin City Council, Public

Counter, Planning Department.

  • Raheny Library, Howth Road.

Presented to the North Central Area Committee:

  • 17th September 2012
  • 19th November 2012

5

slide-6
SLIDE 6

Public Consultation Undertaken

Public information Meeting:

  • 15th January 2013 at 7.30 p.m.

in Belgrove Girls School Hall. Hosted by the Clontarf Residents Association and attended by circa 180 people. Engineers present with drawings

  • f scheme to answer questions

from members of the public.

Follow-up meeting:

  • 10th May 2013 in Northside

Civic Centre, Coolock. Engineers present and dealt with any additional or new queries that had not been addressed in the consultation process.

Planning Approval 13th May 2013.

6

slide-7
SLIDE 7

7

slide-8
SLIDE 8

TYPICAL CROSS-SECTION OF SCHEME

8

slide-9
SLIDE 9

TYPICAL CROSS-SECTION OF SCHEME

9

slide-10
SLIDE 10

UNUSED SPACE OVERLOOKING DUBLIN BAY

10

slide-11
SLIDE 11

RECLAIMING AND REUSING SPACE

11

slide-12
SLIDE 12

AMENITY IMPROVEMENTS

Improved Access along Shoreline Tourism & Recreation Renovation of Tram Shelter

12

slide-13
SLIDE 13

STREETSCAPE ENVIRONMENT IMPROVEMENTS

Energy Efficient LED Lighting Reduced Noise Pollution Vulnerable Road Users

13

slide-14
SLIDE 14

ST ANNE’S PARK

NEW QUADRANT ENTRANCE DESIGN IMPROVE VIEW AND ACCESS TO TREE OF LIFE SCULPTURE

  • SCULPTURE RECOMMENCING SPRING 2016

14

slide-15
SLIDE 15

PARKING PROVISIONS

COMPENSATORY PARKING AT WOODEN BRIDGE DUE TO LOSS OF PARKING ON CARRIAGWAY

15

slide-16
SLIDE 16

PARKING PROVISIONS

  • INCREASE IN PARKING SPACES FROM BAY

RESTAURANT UP TO DOLLYMOUNT AVENUE

  • REMOVAL OF DOUBLE YELLOW ON CARRIAGEWAY

AND PART OF DOLLYMOUNT AVENUE SIDE ROAD

16

slide-17
SLIDE 17

PARKING PROVISIONS

  • UPGRADE OF ST. ANNES PARK CAR PARK
  • NEW STREET PARKING PROVIDED

17

slide-18
SLIDE 18

CURRENTLY UNDER CONSTRUCTION FOOTPATH / CYCLEWAY & ROAD PAVEMENT STILL TO BE CONSTRUCTED

SEA WALL CONSTRUCTION

18

slide-19
SLIDE 19
  • CURRENTLY UNDER CONSTRUCTION
  • UNFINISHED ARTICLE
  • WALL FINISH OPTIONS UNDER REVIEW

SEA WALL CONSTRUCTION

19

slide-20
SLIDE 20
  • CURRENTLY UNDER CONSTRUCTION
  • UNFINISHED ARTICLE
  • WALL FINISH OPTIONS UNDER REVIEW

SEA WALL CONSTRUCTION

20

slide-21
SLIDE 21
  • CURRENTLY UNDER CONSTRUCTION
  • UNFINISHED ARTICLE
  • WALL FINISH OPTIONS UNDER REVIEW

SEA WALL CONSTRUCTION

21

slide-22
SLIDE 22
  • CURRENTLY UNDER CONSTRUCTION
  • UNFINISHED ARTICLE
  • WALL FINISH OPTIONS UNDER REVIEW

SEA WALL CONSTRUCTION

22

slide-23
SLIDE 23
  • CURRENTLY UNDER CONSTRUCTION
  • UNFINISHED ARTICLE
  • WALL FINISH OPTIONS UNDER REVIEW

SEA WALL CONSTRUCTION

23

slide-24
SLIDE 24
  • CURRENTLY UNDER CONSTRUCTION
  • UNFINISHED ARTICLE
  • WALL FINISH OPTIONS UNDER REVIEW

SEA WALL CONSTRUCTION

24

slide-25
SLIDE 25

Proposed Sea Wall Finishes

Proposed wall finishes are as follows:

  • At sections of poured concrete wall

– Smooth F4 concrete finish with new coping.

  • At all other sections of wall (both where existing wall is rebuilt or raised,

and where new masonry wall is built)

– Ready mixed smooth render finish with new coping.

  • Options currently being looked at to amend design to improve aesthetics
  • f the newly completed wall.

25

slide-26
SLIDE 26

Wall Heights between Junctions along Route

Wall height adjustments are as follows:

  • Bull Island Junction to Seafield Road East Junction: Level adjustment of up to 276mm (11

inches). First 25m no level change. New average wall height = 540mm (21 inches).

  • Seafield Road East Junction to Dollymount Park Junction: Level adjustment up to 120mm

(5 inches) and new wall construction. New average wall height = 580mm (23 inches).

  • Dollymount Park Junction to Doyle’s Lane Junction: New wall construction to match

existing wall heights. New average wall height = 690mm (27 inches).

  • Doyle’s Lane Junction to Dollymount Avenue Junction: New wall construction for 55

metres to match existing levels, no level adjustment to retained wall. New average wall height = 450mm (18 inches).

  • Dollymount Avenue Junction to The Oaks Junction: Wall level relatively unchanged with

new coping to be installed. New average wall height = 700mm (28 inches) with maximum wall height = 975mm (39 inches) – same as existing.

  • The Oaks Junction to Mount Prospect Avenue Junction: No level change. New average

wall height = 800mm (32 inches).

  • Mount Prospect Avenue Junction – Naniken Stream: Level adjustment of 450mm-

690mm (18-27 inches). New average wall height = 840mm (33 inches) with maximum wall height = 1,138mm (45 inches) including 75mm (3 inch) coping.

  • Note: the section of wall just south of Mount Prospect Avenue which is not being adjusted is currently at a height

up to 975mm (38.4 inches). The max height of our current wall north of this is 1,063mm (42 inches) excluding coping, which would be 1,138mm (45 inches) allowing for a 75mm (3 inch) coping.

26

slide-27
SLIDE 27
  • TIMBER BATTENS SET OUT ON SITE
  • BLUE SPRAY MARK = FINISHED FOOTPATH LEVEL
  • TOP OF BATTEN = COMPETED WALL HEIGHT

SEA WALL HEIGHT

27

slide-28
SLIDE 28

SEA WALL HEIGHT

Opposite St. Anne's Park Lodge

28

slide-29
SLIDE 29

SEA WALL HEIGHT

Mount Prospect Ave Junction

29

slide-30
SLIDE 30
  • WALL HEIGHT RELATIVE TO COMPLETED FOOTPATH LEVEL
  • 300m WITH NO RELATIVE INCREASE
  • ILLUSTRATES WALL HIGHER ADJACENT ST. ANNES PARK
  • MAX =1.138M
  • MIN = 0.410M

SEA WALL HEIGHT (RELATIVE TO FOOTPATH)

30

slide-31
SLIDE 31

SEA WALL HEIGHT (RELATIVE TO FOOTPATH)

31

slide-32
SLIDE 32

SEA WALL HEIGHT (RELATIVE TO FOOTPATH)

32

slide-33
SLIDE 33

SEA WALL HEIGHT (RELATIVE TO FOOTPATH)

33

slide-34
SLIDE 34

SEA WALL HEIGHT (RELATIVE TO FOOTPATH)

34

slide-35
SLIDE 35

SEA WALL HEIGHT (RELATIVE TO FOOTPATH)

35

slide-36
SLIDE 36

Howth Road to Baldoyle Road

  • Old Sea Wall Height for Comparison

Distance from Howth Road to Baldoyle Road is 2.1km (1.3 miles) – almost identical in length to this scheme. Old sea wall is 0.7m (27.6 inches) to 1m (39.4 inches) high along the 2.1km length. Depending on the relative road level the wall does restrict views of the foreshore at times although Howth is clearly visible. This length of road is much straighter and does not have a bend or camber on the road like there near the pond at St. Anne’s Park that would restrict views for car drivers even further.

36

slide-37
SLIDE 37

Average Wall Height Chart

37

16% 26% 34% 8%

Average Wall Height 0.4m - 0.6m (16 - 24 inches): 16% Average Wall Height 0.6m - 0.8m (24 – 32 inches): 26% Average Wall Height 0.8m – 1.0m (32 – 40 inches): 34% Average Wall Height 1.0m – 1.138m (40 – 45 inches): 8%

slide-38
SLIDE 38
  • ROAD SURFACE LOWER THAN FOOTPATH LEVELS (AVG. 140mm).
  • 150m SECTION ON BEND AT ST. ANNES PARK SUPERELEVATED RESULTING

IN ROAD SURFACE LOWER RELATIVE TO FOOTPATH / WALL (Max = 0.5m).

  • 460m SECTION OF ROAD WHERE DRIVER EYE HEIGHT LOWER THAN WALL .
  • 33 SECONDS AT 50KPH.

SEA WALL HEIGHT (RELATIVE TO ROAD SURFACE)

38

slide-39
SLIDE 39

SAFETY BENEFITS – COLLISION STATISTICS

1996 – 2011: 163 accidents 50% of Serious and Fatal Accidents involved Pedestrians

39

slide-40
SLIDE 40

SAFETY BENEFITS

SAFETY

Reduced Carriageway Width (2 x 3m)

Upgraded Junctions along route

Improved Driver Behaviour Reduced speed limit at north end 60km/h → 50km/h Reduced speeds - 85%ile currently 57.3km/h

Removal of Driver/Cyclist Conflict

40

slide-41
SLIDE 41

SAFETY BENEFITS

Reasons for Buildouts:

  • Improve

visibility and safety for pedestrians crossing junctions.

  • Improve visibility for drivers entering
  • r exiting side streets.
  • Make it easier for visually and mobility

impaired people to cross the junction, as well as people will child buggies.

  • Prevent drivers from parking too close

to corners thereby blocking visibility for pedestrians and other drivers.

41

slide-42
SLIDE 42

Environmental Measures

  • Appropriate Assessment carried out for the scheme
  • Environmental Clerk of Works appointed by DCC
  • Project Ecologist engaged by Contractor

– Environmental Management Plan – Grassland Management Plan – Method Statements for Works on Lagoon – Ongoing environmental monitoring

  • Liaison with NPWS and BirdWatch Ireland
  • Mitigation Measures Implemented

– Screen erected between Works and Lagoon – No Lagoon Works during winter to facilitate wintering birds

42

slide-43
SLIDE 43

43

slide-44
SLIDE 44

Impacts of Climate Change

  • 60
  • 40
  • 20

20 40 60 80 100 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 MSL in mm ODM

Dublin Annual Mean Sea Level 2000 – 2013

(Provisional)

Observed Annual … 44

slide-45
SLIDE 45

Bull Island

(Extract from Draft Development Plan Strategic Flood Risk Assessment SFRA)

Flood Zone A Dark Green; no wave action modelled. Flood Zone B Lighter Green; no wave action modelled.

45