P OTOMAC Y ARD M ETRORAIL S TATION P ROJECT Potomac Yard Metrorail Implementation Work Group March 18, 2019 A GENDA Ongoing Activities PYC/Contractor Update Overview Southwest Entrance Pricing Process Southwest Entrance Matrix


slide-1
SLIDE 1

POTOMAC YARD METRORAIL STATION PROJECT

Potomac Yard Metrorail Implementation Work Group March 18, 2019

slide-2
SLIDE 2

PYMIG| March 18, 2019

AGENDA

  • Ongoing Activities
  • PYC/Contractor Update
  • Overview Southwest Entrance Pricing Process
  • Southwest Entrance Matrix
  • PYMIG Discussion
  • Public Discussion
  • Upcoming Meetings

2

slide-3
SLIDE 3

PYMIG| March 18, 2019

ONGOING ACTIVITIES

  • Submitted Joint Permit Application (JPA)

– Corps & DEQ reviewing application – City responding to questions and information requests – Corps & DEQ public comment periods will be posted – DEQ will post their public hearing date

  • Southwest entrance pricing process

3

slide-4
SLIDE 4

PYMIG| March 18, 2019

PYC / CONTRACTOR UPDATE

4

slide-5
SLIDE 5

PYMIG| March 18, 2019

Milestone Description 9/25/2018 Status NTP 9/25/2018 Completed 1 DSUP Submission 10/25/18 Completed 2 DSUP Approval 4/13/19 Completed 3 Construction Access and Trailers 8/21/19 4 Approvals and Permits 4/22/20 5 Complete Comm/IT Rooms and Systems Facilities 9/29/21 6 WMATA Complete IT Room 10/29/21 7 Complete Preparation for X-Over Installation and Track Cut-OverStation Structure and Track Work 11/28/21 8 Readiness for Installation of Fare Equipment 2/26/22 9 Final Station Completion 3/28/22

Milestone Schedule

CONTRACT MILESTONE SCHEDULE

5

slide-6
SLIDE 6

PYMIG| March 18, 2019

SUMMARY LOOK AHEAD SCHEDULE

MAR APR MAY JUN JUL AUG SEP OCT ACTIVITY SECURE AND SETUP PARKING/STAGING AREAS/TRAILERS DOCUMENTATION OF EXISTING CONDITIONS CONSTRUCTION OF WORK BRIDGE OVER WMATA TRACKS CONSTRUCTION OF AC SWITCHGEAR BUILDING INSTALL ELECTRIC/STORM DRAIN/WATER ETC. UNDER WMATA TRACKS PLACE FILL FOR STATION 2019 PERMITS DESIGN SURVEY STATION DESIGN RELOCATE TOT LOT AND ADJUST TRAFFIC CIRCLE

6

slide-7
SLIDE 7

PYMIG| March 18, 2019

CLOSEST STRUCTURE TO PILE DRIVING

7

slide-8
SLIDE 8

PYMIG| March 18, 2019

PILE DRIVING IMPACTS ON ADJACENT STRUCTURES

8

slide-9
SLIDE 9

PYMIG| March 18, 2019

DOCUMENTATION OF EXISTING CONDITIONS

9

slide-10
SLIDE 10

PYMIG| March 18, 2019

DOCUMENTATION OF EXISTING CONDITIONS

10

slide-11
SLIDE 11

PYMIG| March 18, 2019

STAGING AREA

11

slide-12
SLIDE 12

PYMIG| March 18, 2019

CONTINUED: STAGING AREA

12

slide-13
SLIDE 13

PYMIG| March 18, 2019

CONTINUED: STAGING AREA

13

slide-14
SLIDE 14

PYMIG| March 18, 2019

SOUTHWEST ENTRANCE PRICING PROCESS

14

slide-15
SLIDE 15

PYMIG| March 18, 2019

SOUTHWEST ENTRANCE PRICING PROCESS

  • TASK 1

– Advance engineering sufficiently to allow the performance of independent cost estimates and schedule impact analyses for each of the 3 ideas – Approximately two months to complete (Early April)

  • TASK 2

– WMATA and PYC will both perform the cost estimates and schedule analyses – The cost and schedule analysis results will be included in the Matrix – Approximately one month to complete (Early May)

15

slide-16
SLIDE 16

PYMIG| March 18, 2019

WMATA PROCESS

  • Using PYC for analysis activates the contract

procurement process for a contract change

  • Requires additional level of documentation and

adherence to process, so as not to compromise ability to use PYC to perform

  • Once Task 2 is completed WMATA will present

publicly the analysis of the options

16

slide-17
SLIDE 17

PYMIG| March 18, 2019

SOUTHWEST ENTRANCE DESIGN IDEA #1

SOUTHWEST ENTRANCE PAVILION W/ BRIDGE

17

slide-18
SLIDE 18

PYMIG| March 18, 2019

SOUTHWEST ENTRANCE DESIGN IDEA #2

  • E. GLEBE RAMP W/ MOVING WALKWAY

18

slide-19
SLIDE 19

PYMIG| March 18, 2019

SOUTHWEST ENTRANCE DESIGN IDEA #3

SOUTHWEST ENTRANCE PAVILION W/ SMALL MEZZANINE

19

slide-20
SLIDE 20

PYMIG| March 18, 2019

SOUTHWEST ENTRANCE MATRIX

20

slide-21
SLIDE 21

PYMIG| March 18, 2019

SOUTHWEST ENTRANCE MATRIX

  • Did we get the criteria right?
  • Did we get the criteria definitions right?
  • Is there something missing?
  • Matrix Development Process

– Initial discussion – Based on input received tonight, refine matrix criteria and bring back to PYMIG for verification

21

slide-22
SLIDE 22

PYMIG| March 18, 2019

MATRIX – SOUTHWEST ENTRANCE

22

slide-23
SLIDE 23

PYMIG| March 18, 2019

23

slide-24
SLIDE 24

PYMIG| March 18, 2019

Discussion

24

slide-25
SLIDE 25

PYMIG| March 18, 2019

UPCOMING PYMIG MEETINGS

  • Monday, April 22nd:

– Contractor update – Matrix discussion

  • Tuesday, May 21st:

– Contractor update – Southwest entrance alternatives update

25