rookery south erf clp meeting llrs works update
play

Rookery South ERF CLP Meeting LLRS Works Update 12 th June 2017 - PowerPoint PPT Presentation

Rookery South ERF CLP Meeting LLRS Works Update 12 th June 2017 LLRS Works Low Level Restoration Scheme under the Review of Old Minerals Permission Works commenced 24 April Planned Completion 17 October LLRS Works Low Level


  1. Rookery South ERF CLP Meeting LLRS Works Update 12 th June 2017

  2. LLRS Works – Low Level Restoration Scheme under the Review of Old Minerals Permission • Works commenced 24 April • Planned Completion 17 October

  3. LLRS Works – Low Level Restoration Scheme 20,000m3 cut and fill, 40,000m3 top soil strip 4 excavators, 5 dozers, 21 dump trucks

  4. Rookery South ERF - CLP Meeting • 45 people on site, >7000 hours worked • No lost time or reportable incidents to date • Ecology – newts, lapwings • Fencing/Footpaths Complaints log • 2 issues to date: – Noise – Debris on Green Lane

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend