Rookery South ERF CLP Meeting LLRS Works Update 12 th June 2017 - - PowerPoint PPT Presentation

rookery south erf clp meeting llrs works update
SMART_READER_LITE
LIVE PREVIEW

Rookery South ERF CLP Meeting LLRS Works Update 12 th June 2017 - - PowerPoint PPT Presentation

Rookery South ERF CLP Meeting LLRS Works Update 12 th June 2017 LLRS Works Low Level Restoration Scheme under the Review of Old Minerals Permission Works commenced 24 April Planned Completion 17 October LLRS Works Low Level


slide-1
SLIDE 1

Rookery South ERF CLP Meeting LLRS Works Update

12th June 2017

slide-2
SLIDE 2

LLRS Works – Low Level Restoration Scheme under the Review of Old Minerals Permission

  • Works commenced 24 April
  • Planned Completion 17 October
slide-3
SLIDE 3

LLRS Works – Low Level Restoration Scheme

20,000m3 cut and fill, 40,000m3 top soil strip 4 excavators, 5 dozers, 21 dump trucks

slide-4
SLIDE 4

Rookery South ERF - CLP Meeting

  • 45 people on site, >7000 hours

worked

  • No lost time or reportable

incidents to date

  • Ecology – newts, lapwings
  • Fencing/Footpaths

Complaints log

  • 2 issues to date:

– Noise – Debris on Green Lane