RM 620 South Improvement Project From SH 71 to Hudson Bend Road - - PowerPoint PPT Presentation

rm 620 south improvement project
SMART_READER_LITE
LIVE PREVIEW

RM 620 South Improvement Project From SH 71 to Hudson Bend Road - - PowerPoint PPT Presentation

RM 620 South Improvement Project From SH 71 to Hudson Bend Road Public Hearing Feb. 20, 2020 RM 620 South Improvement Project Feb. 20, 2020 Public Hearing Purpose Provide an update on RM 620 South project Present Draft Environmental


slide-1
SLIDE 1

RM 620 South Improvement Project

  • Feb. 20, 2020

RM 620 South Improvement Project

  • Feb. 20, 2020

From SH 71 to Hudson Bend Road Public Hearing

slide-2
SLIDE 2

RM 620 South Improvement Project

  • Feb. 20, 2020

Public Hearing Purpose

  • Provide an update on RM 620 South

project

  • Present Draft Environmental

Assessment and the Recommended Alternative

  • Receive public input
2
slide-3
SLIDE 3

RM 620 South Improvement Project

  • Feb. 20, 2020

Public Hearing Agenda

3
  • Introduction
  • Project design presentation
  • Environmental presentation
  • 15-minute recess
  • Public comments
slide-4
SLIDE 4

RM 620 South Improvement Project

  • Feb. 20, 2020

Public Comments

Your comments are important to us!

4
slide-5
SLIDE 5

RM 620 South Improvement Project

  • Feb. 20, 2020

Comment Period Deadline

Submit comments by FRIDAY, MA MARCH 6, 202 020

5
slide-6
SLIDE 6

RM 620 South Improvement Project

  • Feb. 20, 2020

Project Design Presentation

Project des ct design pres resen enta tati tion

Brock Miller, P.E. RTG - consultant project manager

6
slide-7
SLIDE 7

RM 620 South Improvement Project

  • Feb. 20, 2020

Project Location, Need and Purpose

  • Project Limits

– SH 71 to Hudson Bend Road – Project length – 9.2 miles – Funded Section: SH 71 to Oak Grove Boulevard

  • Project Need

– Existing capacity inadequate to meet current/future traffic volumes – Congestion, reduced mobility and safety issues

  • Project Purpose

– Improve safety – Improve mobility – Accommodate existing and future traffic demand

7
slide-8
SLIDE 8

RM 620 South Improvement Project

  • Feb. 20, 2020

Existing Roadway

  • Current Roadway

– Two, 11-foot mainlanes with 10-foot shoulders in each direction – Mainlanes separated by 14-foot continuous center-turn lane – No bike lanes or sidewalks

8
slide-9
SLIDE 9

RM 620 South Improvement Project

  • Feb. 20, 2020

Proposed Roadway

  • Proposed improvements

– Add 11-foot mainlane in each direction – Replace continuous center-turn lane – Add 18-foot raised median – Add 10-foot bicycle/pedestrian paths

9
slide-10
SLIDE 10

RM 620 South Improvement Project

  • Feb. 20, 2020

Utility Adjustments

  • Underground and overhead utilities

–Known existing utilities have been identified and mapped –Conflicting utilities will need to be adjusted or relocated prior to roadway construction

10
slide-11
SLIDE 11

RM 620 South Improvement Project

  • Feb. 20, 2020

Projected Schedule and Cost

  • Anticipated Construction

Start: Late 2022

  • Estimated Total Project

Cost: $75 Million

11
slide-12
SLIDE 12

RM 620 South Improvement Project

  • Feb. 20, 2020

Environmental Presentation

Environme mental p l pres resen enta tati tion Darren Dodson CP&Y - consultant environmental manager

12
slide-13
SLIDE 13

RM 620 South Improvement Project

  • Feb. 20, 2020

Environmental Review/Impacts Addressed

  • Right of way
  • Traffic noise
  • Community/socio-

economic

  • Air quality
  • Visual/aesthetics
  • Archeological resources
  • Historic resources
  • Water quality
  • Wetlands/waters of U.S.
  • Biological resources
  • Hazardous materials
  • Indirect and cumulative

effects

  • Section 4(f) (land from

publicly owned parks, recreation areas)

  • Chapter 26 resources

(protection of public parks and recreational lands)

13
slide-14
SLIDE 14

RM 620 South Improvement Project

  • Feb. 20, 2020

Section 4(f) and Chapter 26

  • City of Bee Cave Central

Park –Section 4(f) and Chapter 26 regulations apply –Use of approximately 0.4 acre of park property to construct turn lanes –Impacts existing 5-foot bicycle/pedestrian path in park –Mitigation incorporated into project design –Section 4(f) de minimis determination

14 City of Bee Cave Central Park Existing Bee Cave Hike and Bike Trail Proposed 10-foot wide shared-use path Proposed 6-foot wide pathway
slide-15
SLIDE 15

RM 620 South Improvement Project

  • Feb. 20, 2020

Threatened/Endangered Species

  • Proposed project would impact habitat

for federally endangered Golden- cheeked Warbler

  • Project May Affect, but is Not Likely to

Adversely Affect the species. Informal consultation is in progress with U.S. Fish and Wildlife Service

15
slide-16
SLIDE 16

RM 620 South Improvement Project

  • Feb. 20, 2020

Traffic Noise

  • Traffic Noise Analysis completed according to

TxDOT and FHWA guidelines

  • 23 noise receivers are expected to be impacted
  • Noise barriers would be feasible/reasonable for

three of the impacted receivers: –Falconhead Apartments –Villas on Travis Residential Apartments (north section) –Villas on Travis Residential Apartments (south section)

16
slide-17
SLIDE 17

RM 620 South Improvement Project

  • Feb. 20, 2020

Water Resources

  • Flood

loodpla lains/Edwards A Aquifer – Portions of project within FEMA 100-year flood hazard areas associated with an unnamed tributary to Little Barton Creek – Project would not violate applicable floodplain regulations or

  • rdinances

– Southern portion of project area lies in Edwards Aquifer Contributing Zone; requires TCEQ Contributing Zone Plan

  • Water

ers o

  • f the

e U.S., i incl ncluding W Wetlands – Tributaries to Little Barton Creek, Honey Creek, and two wetland features were evaluated – Proposed project would permanently fill 0.04 acre of streams; no fill within wetlands or other special aquatic sites – Requires a USACE permit without pre-construction notification; compensatory mitigation not required

17

Conclusion: Studies, analyses, and evaluation of the proposed project indicate no significant impacts.

slide-18
SLIDE 18

RM 620 South Improvement Project

  • Feb. 20, 2020

Next Steps

  • Public comment period ends March 6, 2020
  • Anticipated environmental decision (Spring 2020)
  • Prepare detailed design
  • Acquire right of way
  • Utility construction
  • Roadway construction
18
slide-19
SLIDE 19

RM 620 South Improvement Project

  • Feb. 20, 2020

Proposed Right of Way

  • Approximately 34.3 acres of new ROW
  • No required displacements
  • TxDOT ROW personnel available for questions
  • All ROW acquisition would be completed

according to the Uniform Relocation Assistance and Real Property Acquisition Policies Act of 1970, as amended

19
slide-20
SLIDE 20

RM 620 South Improvement Project

  • Feb. 20, 2020

Public Comments

Your comments are important to us!

20
slide-21
SLIDE 21

RM 620 South Improvement Project

  • Feb. 20, 2020

Recess

RECE CESS SS 15 minutes

21
slide-22
SLIDE 22

RM 620 South Improvement Project

  • Feb. 20, 2020

Public Comments

  • Comm

mment P Perio iod –Please note that we will not attempt to respond to your comments at this time –All comments will be fully considered and responded to in the project record which is available on the TxDOT project website

22
slide-23
SLIDE 23

RM 620 South Improvement Project

  • Feb. 20, 2020

Public Comments

Please limit your comments to three (3) minutes

23

3:00 2:59 2:58 2:57 2:56 2:55 2:54 2:53 2:52 2:51 2:50 2:49 2:48 2:47 2:46 2:45 2:44 2:43 2:42 2:41 2:40 2:39 2:38 2:37 2:36 2:35 2:34 2:33 2:32 2:31 2:30 2:29 2:28 2:27 2:26 2:25 2:24 2:23 2:22 2:21 2:20 2:19 2:18 2:17 2:16 2:15 2:14 2:13 2:12 2:11 2:10 2:09 2:08 2:07 2:06 2:05 2:04 2:03 2:02 2:01 2:00 1:59 1:58 1:57 1:56 1:55 1:54 1:53 1:52 1:51 1:50 1:49 1:48 1:47 1:46 1:45 1:44 1:43 1:42 1:41 1:40 1:39 1:38 1:37 1:36 1:35 1:34 1:33 1:32 1:31 1:30 1:29 1:28 1:27 1:26 1:25 1:24 1:23 1:22 1:21 1:20 1:19 1:18 1:17 1:16 1:15 1:14 1:13 1:12 1:11 1:10 1:09 1:08 1:07 1:06 1:05 1:04 1:03 1:02 1:01 1:00 0:59 0:58 0:57 0:56 0:55 0:54 0:53 0:52 0:51 0:50 0:49 0:48 0:47 0:46 0:45 0:44 0:43 0:42 0:41 0:40 0:39 0:38 0:37 0:36 0:35 0:34 0:33 0:32 0:31 0:30 0:29 0:28 0:27 0:26 0:25 0:24 0:23 0:22 0:21 0:20 0:19 0:18 0:17 0:16 0:15 0:14 0:13 0:12 0:11 0:10 0:09 0:08 0:07 0:06 0:05 0:04 0:03 0:02 0:01 3:00 2:59 2:58 2:57 2:56 2:55 2:54 2:53 2:52 2:51 2:50 2:49 2:48 2:47 2:46 2:45 2:44 2:43 2:42 2:41 2:40 2:39 2:38 2:37 2:36 2:35 2:34 2:33 2:32 2:31 2:30 2:29 2:28 2:27 2:26 2:25 2:24 2:23 2:22 2:21 2:20 2:19 2:18 2:17 2:16 2:15 2:14 2:13 2:12 2:11 2:10 2:09 2:08 2:07 2:06 2:05 2:04 2:03 2:02 2:01 2:00 1:59 1:58 1:57 1:56 1:55 1:54 1:53 1:52 1:51 1:50 1:49 1:48 1:47 1:46 1:45 1:44 1:43 1:42 1:41 1:40 1:39 1:38 1:37 1:36 1:35 1:34 1:33 1:32 1:31 1:30 1:29 1:28 1:27 1:26 1:25 1:24 1:23 1:22 1:21 1:20 1:19 1:18 1:17 1:16 1:15 1:14 1:13 1:12 1:11 1:10 1:09 1:08 1:07 1:06 1:05 1:04 1:03 1:02 1:01 1:00 0:59 0:58 0:57 0:56 0:55 0:54 0:53 0:52 0:51 0:50 0:49 0:48 0:47 0:46 0:45 0:44 0:43 0:42 0:41 0:40 0:39 0:38 0:37 0:36 0:35 0:34 0:33 0:32 0:31 0:30 0:29 0:28 0:27 0:26 0:25 0:24 0:23 0:22 0:21 0:20 0:19 0:18 0:17 0:16 0:15 0:14 0:13 0:12 0:11 0:10 0:09 0:08 0:07 0:06 0:05 0:04 0:03 0:02

slide-24
SLIDE 24

RM 620 South Improvement Project

  • Feb. 20, 2020

Questions/Comments

  • Address questions/comments to:

– Mailing Address: TxDOT Austin District Office Attn: Matthew Cho, P.E. TxDOT Austin District P.O. Box 15426 Austin, Texas 78761-5426 – Email: Matthew.Cho@txdot.gov

  • Project information available at: www.txdot.gov

Search: “Public Hearings and Meetings Schedule”

  • Written comments mu

must be p e postmarked b by Friday, March 6, 2020

  • TxDOT addresses all comments; prepares Final Environmental Assessment
24
slide-25
SLIDE 25

RM 620 South Improvement Project

  • Feb. 20, 2020

Thank you

Thank you for your interest in the RM 620 South Improvement Project

25