RICHLAND COUNTY TRANSPORTATION PENNY PROGRAM Town of Irmo January 10, 2019 Program Funding Categories Bike / Ped./ Administration, Greenway, $32,100,000 $80,888,356 Bus Service, Roadway $300,991,000 Projects, $656,020,644 Summary of
RICHLAND COUNTY TRANSPORTATION PENNY PROGRAM
Town of Irmo
January 10, 2019
Program Funding Categories
Roadway Projects, $656,020,644 Bus Service, $300,991,000 Bike / Ped./ Greenway, $80,888,356 Administration, $32,100,000
Summary of Bike/Ped./Greenway, Administration, and Roadway Projects= $769,009,000
Projects By The Numbers 87 BIKEWAYS 15 GREENWAYS 15 INTERSECTIONS 7
NEIGHBORHOOD IMPROVEMENTS
56 SIDEWALKS 5
SPECIAL PROJECTS
14 WIDENINGS
Financials To Date
$ 320.3 M Sales Tax Collections $ 15.7 M Outside Funding $ 89.9 M Disbursed to Comet $ 12.3 M Mitigation Bank $ 17.2 M Program Expenditures $ 196.3 M Project Expenditures $ 38.3 M Design / Planning & Delivery $ 9.7 M Right-of-Way $ 148.2 M Construction $ 316 M Total Expenditures To Date
CALL 1-844-RC PENNY EMAIL INFO@RICHLANDPENNY.COM
www.richlandpenny.com
CALL 1-844-RC PENNY EMAIL INFO@RICHLANDPENNY.COM
Interactive Map
CALL 1-844-RC PENNY EMAIL INFO@RICHLANDPENNY.COM
Clemson Road Widening
Clemson Road (Chimneyridge Drive to Old Clemson Road)
CALL 1-844-RC PENNY EMAIL INFO@RICHLANDPENNY.COM
Recent Construction
Three Rivers Greenway
CALL 1-844-RC PENNY EMAIL INFO@RICHLANDPENNY.COM
Recent Construction
Shop Road Extension – Phase 1
CALL 1-844-RC PENNY EMAIL INFO@RICHLANDPENNY.COM
Recent Construction
North Main Street Widening
CALL 1-844-RC PENNY EMAIL INFO@RICHLANDPENNY.COM
Recent Construction
Sidewalk Construction
CALL 1-844-RC PENNY EMAIL INFO@RICHLANDPENNY.COM
Recent Construction
Construction Complete
Bluff Road Widening – Phase 1
Construction Complete
Greene St Improvements – Phase 1
Construction Complete
Summit Ridge / Summit Pkwy Kennerly Rd / Coogler Rd
Construction Complete
Broad River Rd / Rushmore Rd North Springs Rd / Risdon Way
Construction Complete
North Springs Rd / Clemson Rd / Rhame Rd Farrow Rd / Pisgah Church Rd
Construction Complete
Lincoln Tunnel Greenway
Construction Complete
Riverbanks Zoo Pedestrian Bridge
Construction Complete
Windover St. Wildwood Ave. Franklin St.
CALL 1-844-RC PENNY EMAIL INFO@RICHLANDPENNY.COM
District 1
Active / Completed Projects
Roadway Widening
- Broad River Rd Widening
Intersections
- Kennerly Rd / Coogler Rd
Sidewalks / Bikeways
- along Broad River Rd
Roadway Resurfacing
- Completed (59)
- Construction Phase (37)
Broad River Corridor Improvements
- Greystone Blvd Intersection
- Bush River Rd Intersection
- St. Andrews Rd Intersection
CALL 1-844-RC PENNY EMAIL INFO@RICHLANDPENNY.COM
District 1
Active / Completed Projects
Completed Projects (6)
- Amenity Ct
- Cabin Cove Rd
- Cedar Grove Ln
- Miller Rd
- Shady Grove Church Rd
- Tiger Paw Ln
In Construction / Procurement (8)
- Amick Dr
- Howard Coogler Rd
- Julian Addy Cir
- Manus Rd
- Ken Webber Rd
- Summer Haven Rd
- Haven Cir
- Mrs Macks Rd
In Design / Rights of Way (5)
- Stone House Dr
- Tall Oaks Dr
- Eastview Dr
- Ollie Dailey Rd
- Thelma Hicks Rd
Dirt Road Paving
Upcoming Projects (11)
Kennerly/Coogler Roundabout
CALL 1-844-RC PENNY EMAIL INFO@RICHLANDPENNY.COM
Broad River Rd Widening
BEGIN PROJECT Royal Tower Rd. END PROJECT Shady Grove Rd. END PROJECT Shady Grove Rd. Koon Rd. Woodrow St. Farming Creek Rd. Dutch Fork Rd.
- Ranked #10 of (14) Roadway Widenings
- Approx. 2.5 miles of improvements
- Approx. 22,500 vehicles per day (current)
- Approx. 34,500 vehicles per day (2043)
- High vehicular accident statistics (rear-end/angle)
- Current Cost Estimate = approx. $40 million
Broad River Rd Widening Project Data
CALL 1-844-RC PENNY EMAIL INFO@RICHLANDPENNY.COM
85 FEET
Broad River Rd Widening Typical Section
Project Development
Activities To-Date
- Traffic Counts / Studies
- Field Surveys
- Utility Surveys (SUE)
- Preliminary Geotechnical Studies
- Jurisdictional Determinations
- Cultural Resource Studies
- Hazardous Material Studies
- Pavement Evaluation & Design
- Public Meeting / Public Coord.
- Preliminary Roadway Design
- Value Engineering
- Alignment Studies / Revisions
- Intersection Studies / Relocations
- Cost Evaluations
- Rights-of-Way Roadway Design
- Utility Coordination
- SCDOT Coordination
Project Development Process
- Data Collections / Project Studies
- Preliminary Design & Plans
- Design Verifications & Value Engineering
- Rights-of-Way Plans & Acquisitions
- Construction Design & Plans
- Project Letting
Project Challenges
- High Peak Traffic Volumes
- Multiple Failing Traffic Movements
- Existing & Current Development
- Rights-of-Way Impacts
- Geometry & Intersection Modifications
- Utility Coordination / Utility Relocations
Project Schedule
Begin Rights-of-Way Acquisitions
3rd quarter 2019
Begin Construction
2021
Construction Duration
- approx. 24 – 30 months