Report from the SURF Integration and Installation Workshop
Marco Verzocchi - Fermilab Cold Electronics Consortium Meeting 5 November 2019
Report from the SURF Integration and Installation Workshop Marco - - PowerPoint PPT Presentation
Report from the SURF Integration and Installation Workshop Marco Verzocchi - Fermilab Cold Electronics Consortium Meeting 5 November 2019 Workshop(s) at SURF Mon 29 to Wed 31 Oct - DUNE Installation and Integration Thu 1 and Fri 2 Nov -
Marco Verzocchi - Fermilab Cold Electronics Consortium Meeting 5 November 2019
5 Nov 2018
Cold Electronics and Photon Detector) on the surface at the Integration and Test Facility or in the clean room outside the cryostat at SURF ? YES
with two stacked APAs
3rd detector to be installed)
mine ? The installation of the cryogenic lines from the surface to the DUNE cavern is foreseen for later in the project
5 Nov 2018
readout
5 Nov 2018
connectivity test for the photon detectors
Electronics cables including their routing through the APA frames
patch panel inside the cold box
5 Nov 2018
bridge crane ~12T monorails ~20T cable trays to CUC detector mezzanine
5 Nov 2018
5 Nov 2018
with as much details as possible
internally, mirror cryostat design, understand how we get the LN2 for the cold boxes)
iron structure of the cryostat is complete (advance procurement in the schedule)
5 Nov 2018
and the detector is not yet fully understood
working, need to understand and accommodate also our needs (we may not ship containers, we may ship a lot of small boxes too)
and logistic, need to have full view of database requirements throughout entire life of experiment, well understood list of requirements, before choosing database structure
5 Nov 2018
inside the cryostat (and its activity)
manholes
we can use them to seal the cryostat
around the area that is open
5 Nov 2018
cavern that meets our requirements
assembly tower location interferes with opening / closing the cold boxes
the top of the bridge)
and install the detector on the timescale of 8-9 months
5 Nov 2018
5 Nov 2018
October 30, 2018
Top View with roof framing Materials SAS Personnel SAS Clean Room Materials SAS
5 Nov 2018
access is via one permanent stairway. A second temporary one can be located on the east end of Cavern #1
cleanroom and stairs next to the bridge in the “dirty” area
roof
personnel SAS, a second emergency man- door exit could be at the bottom of the stairs
Materials Handling SAS
Materials Handling SAS Man-door into Personnel SAS
5 Nov 2018
and #3 are shown in Red
shown in Blue ALL materials are moved by SURF from the headframe area to detector halls or a location to be determined Delivery schedule is controlled and managed by SURF, carefully logistics management is required during ALL phases of DUNE A ~1 week DUNE materials buffer underground will help
5 Nov 2018
middle and the top access to the other side is via scissor lift
cleanroom
If needed this could be a separate corridor to keep APA area cleaner
5 Nov 2018
CPA pairs per week at the full rate we have 2 APA assembly towers and 1 CPA assembly tower
assembly tower using the cavern bridge crane
into cleanroom
APA pairs-Repair spot for failed APAs coming out of cold box
components in place
5 Nov 2018
While the Cold Box has not been designed yet one of the key features is that they can move to the area between the cryogenic pumps
In this layout the egress stairs are now part of the personnel SAS
Personnel SAS
5 Nov 2018
installation plan
station to the APA assembly tower 3.5m the Toaster Area is very congested.
same rate but there is so little work space you may have to do CPA and APA work more linear. It is not clear there is room for 20 FTE/shift. Best guess would be ~25% slower See talk on Detector #3 installation
the entire week
the Friday/Saturday/Sunday shifts (that’s when the testing in the cold boxes takes place)
training (1 week) for underground guides
more testing (repairs ?) of APAs in place
5 Nov 2018
until 2024 (?)
the APA production facilities
perform cold testing on a sample of APAs (15-20% feasible) there
5 Nov 2018
design reviews
cable connections, cable trays, cryostat penetrations)
in May/June
Indico page
5 Nov 2018
than just slides (and possibly designs)
are not going to be the first group to be reviewed)
EDMS for drawing / documentation
EDMS into DocDB (not viceversa) when appropriate
designs under discussion
5 Nov 2018