Reference Group AWE Limited Update 23 July 2015 2 Key milestones - - PowerPoint PPT Presentation

reference group
SMART_READER_LITE
LIVE PREVIEW

Reference Group AWE Limited Update 23 July 2015 2 Key milestones - - PowerPoint PPT Presentation

Drover-1 Shire of Coorow Community Reference Group AWE Limited Update 23 July 2015 2 Key milestones of a typical onshore oil and gas project Key agency: DMP, or EPA may formally assess Key agency: DMP (also DAA, DoW, DPaW, DER, EPA) Permit


slide-1
SLIDE 1

Drover-1 Shire of Coorow Community Reference Group

AWE Limited Update

23 July 2015

slide-2
SLIDE 2

Key milestones of a typical onshore oil and gas project

Field development only occurs if exploration activities are successful

2

2

Permit Granted Apply or farm-in Work Program Desktop Exploration Review existing data Modelling Conduct Survey/s Aerial Seismic Scientific (baseline) Rehabilitation Exploratory Drilling Exploration well Appraisal well Production testing Proof of concept well Decommission & Rehabilitation Field Development Development drilling Infrastructure construction (pipeline and plant) Commissioning of equipment Operation Decommission & Rehabilitation Year 1 Year 2 Year 3 Year 4-9 Year 10+

Indicative timeline Key agency: DMP (also DAA, DoW, DPaW, DER, EPA) Key agency: DMP, or EPA may formally assess

Drover-1

slide-3
SLIDE 3

Progress report

  • 2012-2013 Initial consultation
  • Aboriginal Heritage Survey conducted
  • Key regulator briefings (DPaW, DMP, DoW, OEPA, EPA)
  • Council briefings
  • Landowner meetings
  • Community Information Session held in Leeman
  • 2013-2014 Proposed exploration well assessment
  • September - submitted EP to DMP (assessment by DoW, DPaW, OEPA, EPA)
  • September - Self-referred proposal to EPA (extended appeal period)

− Appeal period extended (January-April) − One appeal lodged

  • April - Appeals Convenor conducted further assessment then Minister dismissed

appeal

  • April - EP approved

Initial stakeholder engagement developed and implemented

3

slide-4
SLIDE 4

Progress report

  • Exploration Well - Project milestones
  • 2014

− June/July - exploration well drilled (Phase 1) − August/December - initial exploration results analysed − September - Board offered CRG process and committed to delaying Phase 2 although approvals in place − October 2014 - CRG commenced and meetings held at key project milestones (see Terms of Reference)

  • 2015

− April - DFIT undertaken − May-June DFIT results analysed − June - landowner access agreement extended, permit renewal lodged − July 2015 - Official announcement about next phase

Engagement process evolved in response to changing community feedback

4

slide-5
SLIDE 5

Next steps

AWE and its joint venture partner, Titan Energy, have decided to proceed directly with decommissioning and rehabilitation of the Drover-1 well instead of Phase 2.

  • The decision was based on:
  • Exploration drilling technical review results, and
  • Diagnostic Fracture Injection Test data results, which indicated the gas in target formations could not

be commercially extracted

  • DMP approved the work program variation
  • Enables AWE to focus attention and exploration funding on developing the Senecio-

Waitsia conventional gas field in the northern Perth Basin, near Dongara

5

Although approvals in place, AWE halted activity to allow for further community engagement

slide-6
SLIDE 6

Well decommissioning and rehabilitation

  • Key phases
  • Set cement plugs at prescribed depths
  • Cut off the casing below ground level
  • Seal casing then replace soil
  • Collet soil samples to check soil condition

against baseline levels, and act if required

  • Rehabilitate the surface

− Some infrastructure (eg access roads/water bores) may be left in place for use by landowner Rehabilitation plan being developed with landowner

6

Rig #1 decommissioning a well Rehabilitated well site (Mountain Bridge). Wellhead location highlighted by yellow box

slide-7
SLIDE 7

Next steps

  • Drover-1 groundwater monitoring program ongoing until July 2016
  • Invitation to visit site prior to decommissioning and rehabilitation
  • Feedback from Community Reference Group participants sought depending
  • n level of interest in ongoing information exchange

7

AWE seeking feedback