REFERENCE BUILDINGS FOR COST-OPTIMAL ANALYSIS
Bruxelles, March 8, 2012
S.P. Corgnati*, E. Fabrizio§, M. Filippi*
* Politecnico di Torino
§ University of Torino
REFERENCE BUILDINGS FOR COST-OPTIMAL ANALYSIS Bruxelles, March 8, - - PowerPoint PPT Presentation
REFERENCE BUILDINGS FOR COST-OPTIMAL ANALYSIS Bruxelles, March 8, 2012 S.P. Corgnati * , E. Fabrizio , M. Filippi * University of Torino * Politecnico di Torino WHY REFERENCE (BENCHMARK) BUILDING MODELS ? COST OPTIMAL POLICY of the EPBD
§ University of Torino
[EPBD recast-Guidelines]
Energy Performance of Buildings Directive Recast (EPBD recast, 2010/ 31/ EU) BUILDING CATEGORIES:
consumable items cyclical regulatory cost utilities (except energy cost)
global cost
initial investment cost annual cost disposal cost
running cost
professional fees (e.g. project design) construction of assets taxes (if applicable)
contingencies)
energy cost
maintenance cost
periodic substitute investment
result of energy performance calculation energy tariffs
replacement cost
adjustments inspections cleaning repair insurance taxes (if applicable)
consumable items cyclical regulatory cost utilities (except energy cost)
global cost
initial investment cost annual cost disposal cost
running cost
professional fees (e.g. project design) construction of assets taxes (if applicable)
contingencies)
energy cost
maintenance cost
periodic substitute investment
result of energy performance calculation energy tariffs
replacement cost
adjustments inspections cleaning repair insurance taxes (if applicable)
Methodology (EPBD guidelines)
Climate Building envelope Building equipment Operation & Maintenance Occupant behavior Indoor environmental conditions
Principles and Application fields of TABULA project Collected national representative single-family houses by ASIEPI project
Typical floor plan, Multi-family building.
BUILDING
Geometry
External dimensions 12,60 x 37,50 m Gross Floor Area 472,50 m2 Total Gross Area 1336 m2 Room height 3,10 m N-E Façade Exterior wall area 170,10 m2 S-E Façade Exterior wall area 383,70 m2 Window area 122,58 m2 S-O Façade Exterior wall area 170,10 m2 N-O Façade Exterior wall area 326,30 m2 Window area 94,06 m2
Envelope Components
Opaque elements Exterior Wall 0,52 W/ m2K Flat ceiling under the roof 2,02 W/ m2K Slab towards non conditioned basement 1,35 W/ m2K Transparent Elements Window 3,51 W/ m2K
SYSTEM
Heating system
Gas boiler with radiators. The setpoint temperatures are 20°C from 7 a.m. until 8 p.m., and 18°C during the remaining hours.
Ventilation
The infiltration rate is 0,5 ACH and is constant during all days.
OPERATION
Internal Gains
People 0,04 person/ m2 Appliance (incl. Lighting) 4 W/ m2
BUILDING Geometry
External dimensions 16x30 m Gross Floor Area 480 m2 Total Gross Area 2400 m2 Height 2,9 m Northern Façade Exterior wall area 278 m2 Window area 157,50 m2 Southern Façade Exterior wall area 278 m2 Window area 157,50 m2 Western Façade Exterior wall area 232 m2 Window area 140 m2 Eastern Façade Exterior wall area 232 m2 Window area 140 m2
Envelope Components
Opaque elements Exterior Wall 0,761 W/ m2 K Roof 0,828 W/ m2 K Underground slab 0,516 W/ m2 K Transparent Elements Window 3,19 W/ m2 K
SYSTEM HVAC
4 pipes fancoils with outside air
Heating system
Gas boiler (80°C)
Heating setpoint
21,5°C from 5 a.m. until 6 p.m., and 15°C in remaining hours, during week days.
Cooling system
Water-cooled chiller
Cooling setpoint
26°C from 5 a.m. until 6 p.m. during week day; Turn off during the remaining hours.
Ventilation
11 l/ s per person, Air flow is assumed to be constant from 5 a.m. until 6 p.m during week days.
OPERATION Internal Gains
People The occupancy rate for offices id 0,06 person/ m2. Lighting 13 W/ m2 during working days. A 0,5 percentage is assumed during weekends and night time for security systems. Equipm ent 10 W/ m2 during working days.
Axonometric View, Medium office building. Typical floor plan, Medium office building.
Axonometric View, Large office building. Thermal zones, Large office building.
BUILDING
Geometry
External dimensions 48x73 m Gross Floor Area 3563 m2 Total Gross Area 46’320 m2 Floor to Floor Height 2,74 m Northern Façade Exterior wall area 2090 m2 Window area 1391 m2 Southern Façade Exterior wall area 2090 m2 Window area 1391 m2 Western Façade Exterior wall area 1389 m2 Window area 927 m2 Eastern Façade Exterior wall area 1389 m2 Window area 927 m2
Envelope Components
Opaque elements Exterior Wall 0,309 W/ m2 K Roof 0,248 W/ m2 K Underground slab 0,638 W/ m2 K Transparent Elements Window 1,1 W/ m2 K
SYSTEM
HVAC
Multi-zone VAV with fancoils
Heating system Gas boiler (80°C) Heating setpoint
21°C from 5a.m. until 7p.m., and 15,6°C in remaining hours, during weekdays.
Cooling system 2 Water cooled chillers Cooling setpoint 24°C from 5 a.m. until 6 p.m. during weekdays; 30 °C during the remaining
hours.
Ventilation
0,10 ACH. Air flow is assumed to be constant from 6 a.m. until 10 p.m during weekdays.
OPERATION
Internal Gains
People The occupancy rate for offices id 0,06 person/ m2. Lighting 15 W/ m2 during weekdays. Equipment 10 W/ m2 during weekdays.
10 PACKAGES OF MEASURES concerning the building envelope NON-HOMOGENEOUS PACKAGES: measures regarding only to a few building elements. HOMOGENEOUS PACKAGES: measures applied similarly to all building elements.
Thermal zones Input data
20,000 40,000 60,000 80,000 100,000 120,000 140,000 160,000 180,000 1 2 3 4 5 6 7 8 9 10
kWh Package of Measures
Heating demand Envelope losses Ventilation losses
300 350 400 450 500 550 600 25 50 75 100 125 150
Primary energy [kWh/m2]
RB 1 2 3 4 5 6 7 8 9 10 300 350 400 450 500 550 600 25 50 75 100 125 150 175
Global Cost [€/m2]
Primary energy [kWh/m2]