Global Markets and Cost Comparison for Tall Timber Buildings Andrew Dunn CEO Timber Development Association Contents Australias Tall Timber Buildings and CLT use to date Cost Comparison Tall Timber Buildings How Does


slide-1
SLIDE 1

Global Markets and Cost Comparison for Tall Timber Buildings

Andrew Dunn CEO Timber Development Association

slide-2
SLIDE 2

Contents

 Australia’s Tall Timber Buildings and CLT use to date  Cost Comparison Tall Timber Buildings  How Does Australia’s Tall Timber Buildings Compare Globally?

slide-3
SLIDE 3

Mass Timber Use In Australia

 Commenced with Forte Living  First discussed in April 2009  Built and handed over in late 2012

slide-4
SLIDE 4

Forte Living

slide-5
SLIDE 5

Mass Timber Use In Australia

 Since the first project completed at the end of 2012 there has been: – Completed: 29 projects or 31 building – Under construction: 23 projects or 25 buildings – Total 52 projects – 56 buildings

slide-6
SLIDE 6

Diversity of Projects

slide-7
SLIDE 7

Houses - 19

Swaddling House The Seed Maianbar

slide-8
SLIDE 8

Multi-Residential - 12

Credit: Forte, Aveo, Macarthur Gardens Shellharbour, Kenttown, Sheelharbour

slide-9
SLIDE 9

Office - 6

International House, (Lendlease) Strongbuild Office (Strongbuild) K5, (Lendlease)

slide-10
SLIDE 10

Educational – 4

Incubator, NSW (Strongbuild) Monash University Business School, VIC (XLAM)

slide-11
SLIDE 11

Sales Units - 3

Lendlease

slide-12
SLIDE 12

Student Accommodation – 3

Union Court Australian National University, Canberra UTAS Inveresk Residences

slide-13
SLIDE 13

Hotels - 2

Taronga Retreat, NSW (Strongbuild)

55 Southbank Boulevard Adina Hotel, VIC (Atelier Projects)

slide-14
SLIDE 14

Childcare - 2

Oakleigh South Childcare Centre, VIC (Atelier Projects) Kings Co-op Childcare, QLD (Strongbuild)

slide-15
SLIDE 15

Library - 1

Library at the Docks, Victoria (Lendlease)

slide-16
SLIDE 16

Community Centre - 1

Jordan Springs Community Centre, Sydney (Lendlease)

slide-17
SLIDE 17

School - 1

Our Lady of Assumption Catholic Primary School, Sydney

slide-18
SLIDE 18

Agricultural Building – 1

Jamie’s Barn, NSW (Strongbuild)

slide-19
SLIDE 19

Types of buildings CLT Projects

– Houses – 19 – Multi-residential – 12 – Offices – 6 – Educational – 5 – Sales Units – 3 – Student Accommodation – 3 – Hotel – 2 – Childcare – 2 – Library – 1 – Community centre – 1 – School – 1 – Agricultural building – 1

slide-20
SLIDE 20

Australian CLT Projects

 Where are they occurring?

26 18 2 2 2 1 ACT-1

slide-21
SLIDE 21

CLT SuppliersT Projects

XLAM (New Zealand/Australian) – 17 – Stora Enso (Austrian) – 12 – KLH (Austrian) – 11 – Binderholz (Austrian) – 9 – Cross Lam Aust (Australian) – 1 – Hasslancher (Austrian) – 1 – Xlam Dolimiti (Italian) – 1

slide-22
SLIDE 22

COST PLANS

Are Timber Buildings Really Cost Comparative or Better

slide-23
SLIDE 23

Cost Plans

 There is a growing number of generic cost plans around the world – Australia – UK – Canada

slide-24
SLIDE 24

AUSTRALIA

Aveo, Norwest

slide-25
SLIDE 25

Australia

slide-26
SLIDE 26

Office Building (Super structure only)

Timber Model Concrete Model Columns 450,218 307,224 Floors 4,491,903 4,736,195 Roof 559,956 792,480 Lift, Stair and Air Shaft (includes stairs and cladding) 1,186,793 1,545,465 Suspended Ceiling 997,740 997,740 Additional Engineering (fire) & Termite Protection 35,000 Preliminary Adjustments

  • 517,500

$7,237,259 (-13.6%) $8,379,104

slide-27
SLIDE 27

Apartments (Super structure only)

slide-28
SLIDE 28

UNITED KINGDOM

Ellerslie Road, Yoker, Scotland

slide-29
SLIDE 29

UK

 Two recent completed cost plans – Timber Frame and Masonry by RLB – CLT and Concrete by alinea

slide-30
SLIDE 30

UK - CLT and Concrete

 Height: Six storey  Size: 294 apartment  Location: London  Comparison: CLT and Concrete  Cost Planner: alinea Cost Consultants  Costs based on Q2 2017  Client: TRADA

slide-31
SLIDE 31

UK - CLT and Concrete

 Complete building cost  Fitout costs £25.5 mil  No concrete costs breakdown

0.1 % cheaper

slide-32
SLIDE 32

UK - Timber Frame and Masonry

 Height: Two storey, 4 per block, 8 blocks  Size: 32 apartment  Location: London  Comparison: Timber Frame and Masonry  Cost Planner: Rider Levett Bucknall  Costs based on Q1 2018  Client: Structural Timber Association UK

slide-33
SLIDE 33

UK - Timber Frame and Masonry

slide-34
SLIDE 34

UK - Timber Frame and Masonry

 TF 8 weeks quicker

slide-35
SLIDE 35

UK – Summary

 Cheaper but too small to bother with

slide-36
SLIDE 36

CANADA

Pine and Cypress House, Vancouver Canada

slide-37
SLIDE 37

Canada

 Vancouver City – in 1987 allowed 4 storey Timber Frame construction – In 2009 they were reviewing to allow 6 storey timber frame – Through the Urban Development Institute commissioned the BTY Group

slide-38
SLIDE 38

Canada

 BTY is a Cost Management and Project Management consulting firm  They compared – Concrete – Lightweight Steel – Lightweight timber

slide-39
SLIDE 39

Canada

 Results from the study (2009) – Concrete construction: CAD$265 ft2 (CAD$2,851 m2) – Light steel frame construction: CAD$264 ft2 (CAD$2,841 m2) – Wood frame construction: CAD$237 ft2 (CAD$2,550 m2)  11% less expensive than six storey residential concrete or light steel frame

slide-40
SLIDE 40

BTY Group Update

 BTY Group JOE REKAB, PARTNER  General yes, costs have stayed competitive  The big pressure right now in Canada in the major centres (Vancouver & Toronto) is labour (or lack of)

slide-41
SLIDE 41

Vancouver Cost Comparison

 ALTUS Group –Construction Cost Guide, 2016

41

Construction cost per m2

$2,153 to $2,691 $2,260 to $2,906 $1,400 to $1,776 $1,238 to $1,668

Wood frame 1/3 cheaper

slide-42
SLIDE 42

Other cost comparison quotes

 Al Poettcker, CEO and president of UBC Properties Trust (UBCPT).  "A six-storey concrete building will typically cost an additional $60 to $70 extra per square foot when compared to an equivalent suite in a wood-frame building – which can add up very quickly,"

42

slide-43
SLIDE 43

Vancouver’s Wood Frame Market share

slide-44
SLIDE 44

Vancouver’s Wood Frame Market Share

 Vancouver wood frame apartment market share – Up to 4 storey – 90% – 5 and 6 storey – 70% commencing at 0% market share in 2009 (300 + projects to date)

44

slide-45
SLIDE 45
slide-46
SLIDE 46

Canada Summary

 Wood Frame is considerably cheaper  Obtaining dominance in Vancouver

slide-47
SLIDE 47

WHERE IS AUSTRALIA IN THE RACE FOR TALL TIMBER BUILDINGS?

slide-48
SLIDE 48
slide-49
SLIDE 49

My Criteria

 In my opinion, to be impressive in the world of tall wood buildings you need to be

  • Built or underway – no proposed buildings
  • 7 or more storeys of timber construction
  • Must be modern (this century please)
  • Timber elements must be predominately used in

loadbearing vertical and horizontal element  Why?

slide-50
SLIDE 50

Why seven storeys or above?

 Canada has hundreds (300+) at 6 storeys already

slide-51
SLIDE 51

Lots of Older Buildings Greater than 6 Storeys

 Perry House, Brisbane circa 1913

slide-52
SLIDE 52

6 Storey has been done for centuries (6 actually)

52

Rennes, Brittany Circa 1400’s

slide-53
SLIDE 53

Load Path in Timber

 Doorman, Rotterdam  16 on 4  Steel framed

slide-54
SLIDE 54

Terminology

 When describing how high a timber building is, you need to indicate how much is timber and how much is concrete  Example: 5 on 3

slide-55
SLIDE 55

Australian Example

 Seven over seven  Seven storeys of concrete over seven storeys of timber

slide-56
SLIDE 56

Australian Example

slide-57
SLIDE 57

Strongest You Say

 Concrete – 30 MPa  Hardwood (Grey Ironbark) – 95 MPa

slide-58
SLIDE 58

CTBUH’s List of Tall Timber Buildings (www.ctbuh.org)

slide-59
SLIDE 59

CTBUH’s List of Tall Timber Buildings (www.ctbuh.org)

slide-60
SLIDE 60

LAST 10 YEARS

Completed Tall Timber Buildings

slide-61
SLIDE 61

2008

Älvsbacka Strand Skellefteå, Sweden 7 Storey Timber Frame

slide-62
SLIDE 62

2009

Murray Grove: London, UK 8 on 1 Storeys - CLT Limnologen: Växjö, Sweden 7 on 1 Storeys Timber frames Portvakten: Växjö, Sweden 7 on 1 Storeys Timber frames

slide-63
SLIDE 63

Murray Grove

slide-64
SLIDE 64

2010

Nothing - I suspect the GFC lag slowed things down

slide-65
SLIDE 65

2011

H 8: Bad Aibling, Germany 8 Storeys - CLT Bridport House: London, UK 8 Storeys - CLT

slide-66
SLIDE 66

2012

Forte Living: Melbourne, Australia, 9 on 1 Storeys - CLT Lifecycle Tower One: Dornbirn, Austria, 8 Storey – CLT and Glulam Strandparken: Stockholm, Sweden 8 Storey - CLT

slide-67
SLIDE 67

2013

Maison de l'Inde: Paris, France 7 on 1 Storeys - CLT Pentagon II Ås, Norway, 8 Storey - CLT Via Cenni: Milan, Italy, 9 on 1 Storey - CLT

slide-68
SLIDE 68

2014

Jules Ferry: St. Die-des-Vosges, France, 7 on 1 Storey - CLT K8: Aalen-Waldhausen, Germany, 7 Storey - CLT

slide-69
SLIDE 69

2015

Puukuokka: JYVÄSKYLÄ, Finland, 8 on 1 Storeys, CLT Treet: Bergen, Norway 14 Storey – CLT and Glualm Banyan Wharf: London, UK 9 on 1 Storeys

  • CLT

Eskolantie: Helsinki, Finland, 7 Storeys -CLT Vallen: Växjö, Sweden, 7 Storeys

slide-70
SLIDE 70

2016

Moholt: Trondheim, Norway 9 Storeys - CLT Hotel Nautilus: Pesaro, Italy 7 Storeys - CLT

slide-71
SLIDE 71

2017

Brock Commons: Vancouver, Canada 17 on 1 Storeys – CLT and Glulam The Garden: Sydney, Australia 5 on 1, 6 on 1 & 7 on 1 Storeys - CLT

slide-72
SLIDE 72

2017

Highpoint Terrace: London, UK 7 storey - CLT Carbon12: Portland, USA 7 on 1 Storeys - CLT

slide-73
SLIDE 73

2017

Orgine Condos: Quebec, Canada , 12 on 1 Storeys - CLT Dalston Lane: London, UK 9 on 1 Storeys - CLT

slide-74
SLIDE 74

2017

Frostaliden: Skövde, Sweden 8 Storeys - CLT Moxy Hotel: Oslo, Norway 7 Storeys - CLT

slide-75
SLIDE 75

2018

Ellerslie Crescent, Yoker, Scotland 7 Storeys - CLT

slide-76
SLIDE 76

Under Construction

Aveo Norwest: Sydney, Australia 9 on 2 Storeys - CLT Wood City: Helsinki, Finland 7 on 1 Storey - LVL

slide-77
SLIDE 77

Under Construction

Arbora: Montreal, Canada 9 Storeys - CLT Building C - Suurstoffi, Switzerland 9 on 1 Storeys – LVL, Glulam and TCC

slide-78
SLIDE 78

Under Construction

Building A - Suurstoffi, Switzerland 14 on 1 Storeys – LVL, Glulam and TCC

slide-79
SLIDE 79

Under Construction

HoHo: Austria, Vienna 22 on 2 Storeys - CLT Mjøstårnet, Norway 18 Storeys – LVL & CLT

slide-80
SLIDE 80

Under Construction

Prospective: Bordeaux, France 7 - CLT Tingstorget: Botkyrka, Sweden Various 7 to 9 - CLT Trummen Strand: : Växjö, Sweden 7 on 1 Storeys Timber frames

slide-81
SLIDE 81

Under Construction

K5: Brisbane, Australia 9 on 1 Storeys - CLT Adina Hotel, Melbourne, Australia 10 on 7 storey - CLT extension

slide-82
SLIDE 82

Under Construction

Press House, Wembley, UK 8 Storeys, CLT

slide-83
SLIDE 83

Under Construction (Groundwork)

Skaio: Heilbronn, Germany 8 on 1 Storeys - CLT Framework: Portland, USA 11 on 1 Storeys - CLT ANU Teaching and Student Accommodation 2 x 10 storey, 1 x 7 storey, CLT

slide-84
SLIDE 84

Summary

 30 projects completed to date  16 under construction  Total - 46 projects but around 50 buildings

slide-85
SLIDE 85

Storey Height - Seven Storeys and Above

17 15 10 2 1 1 2 1 1 1 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22

Storey Height

Frequency

slide-86
SLIDE 86

Building Type

RESIDENTIAL OFFICE

Number of Buildings

88%

12%

slide-87
SLIDE 87

Seven storey and above include under construction by country

2 2 2 2 3 2 4 6 6 1 2 3 4 5 6 7 New Zealand Austria Australia Canada France Finland Germany Italy Norway Sweden UK USA Switzerland

Completed

Completed

slide-88
SLIDE 88

Seven storey and above include under construction by country

1 2 2 2 2 3 2 3 6 6 1 1 3 1 1 1 1 1 2 1 2 3 4 5 6 7 New Zealand Austria Australia Canada France Finland Germany Italy Norway Sweden UK USA Switzerland Completed Under Construction

???

slide-89
SLIDE 89
slide-90
SLIDE 90

WoodSolutions 2018 European Tour 23 to 29 September

Sunday 23 September to 29 September 2018 Salzburg, Austria to Biel, Switzerland Visiting buildings under construction and recently completed, CLT and glulam plants, modular and panelised fabrication Costs – Land content only AUD$5,750.00

slide-91
SLIDE 91

THANK YOU

Questions