Rainy River Site Visit September 15, 2015 Cautionary statements - - PowerPoint PPT Presentation

rainy river site visit
SMART_READER_LITE
LIVE PREVIEW

Rainy River Site Visit September 15, 2015 Cautionary statements - - PowerPoint PPT Presentation

Rainy River Site Visit September 15, 2015 Cautionary statements ALL AMOUNTS IN U.S. DOLLARS UNLESS OTHERWISE STATED CAUTIONARY NOTE REGARDING FORWARD-LOOKING STATEMENTS Certain information contained in this presentation, including any


slide-1
SLIDE 1

Rainy River Site Visit

September 15, 2015

slide-2
SLIDE 2

Cautionary statements

ALL AMOUNTS IN U.S. DOLLARS UNLESS OTHERWISE STATED 2

CAUTIONARY NOTE REGARDING FORWARD-LOOKING STATEMENTS Certain information contained in this presentation, including any information relating to New Gold’s future financial or operating performance are “forward looking”. All statements in this presentation,

  • ther than statements of historical fact, which address events, results, outcomes or developments that New Gold expects to occur are “forward-looking statements”. Forward-looking statements are

statements that are not historical facts and are generally, but not always, identified by the use of forward-looking terminology such as “plans”, “expects”, “is expected”, “budget”, “scheduled”, “targeted”, “estimates”, “forecasts”, “intends”, “anticipates”, “projects”, “potential”, “believes” or variations of such words and phrases or statements that certain actions, events or results “may”, “could”, “would”, “should”, “might” or “will be taken”, “occur” or “be achieved” or the negative connotation of such terms. Forward-looking statements in this presentation include, among others, statements with respect to: anticipated total cash costs and all-in sustaining costs, and the factors contributing to those expected results, as well as expected capital expenditures; mine life; mineral reserve and resource estimates; grades expected to be mined; the expected production, costs, economics, revenues and operating parameters and permitting requirements of the Rainy River project; planned activities for 2015 and beyond at the Rainy River Project, as well as planned exploration activities and expenses; anticipated progress of construction and targeted timing for commissioning and full production (and other activities) related to Rainy River; statements with respect to the ability of the parties to satisfy the conditions of and complete the sale of New Gold’s interest in the El Morro property to Goldcorp Inc.(“El Morro sale”); and the ability of Teck Resources Limited and Goldcorp Inc. to satisfy the conditions of and complete the El Morro – Relincho joint venture (“Project Corridor”); and statements with respect to the payment of the remaining $75 million from Royal Gold. All forward-looking statements in this presentation are based on the opinions and estimates of management as of the date such statements are made and are subject to important risk factors and uncertainties, many of which are beyond New Gold’s ability to control or predict. Certain material assumptions regarding such forward-looking statements are discussed in this presentation, New Gold’s annual and quarterly management’s discussion and analysis (“MD&A”), its Annual Information Form and the Technical Reports on the Rainy River Project dated February 14, 2014 filed at www.sedar.com. In addition to, and subject to, such assumptions discussed in more detail elsewhere, the forward-looking statements in this presentation are also subject to the following assumptions: (1) there being no significant disruptions affecting New Gold’s operations; (2) political and legal developments in jurisdictions where New Gold operates, or may in the future operate, being consistent with New Gold’s current expectations; (3) the accuracy of New Gold’s current mineral reserve and resource estimates; (4) the exchange rate between the Canadian dollar, and U.S. dollar being approximately consistent with current levels; (5) prices for diesel, natural gas, fuel oil, electricity and other key supplies being approximately consistent with current levels; (6) equipment, labour and materials costs increasing on a basis consistent with New Gold’s current expectations; (7) arrangements with First Nations and other Aboriginal groups in respect of Rainy River being consistent with New Gold’s current expectations; (8) all required permits, licenses and authorizations being obtained from the relevant governments and other relevant stakeholders within the expected timelines; (9) the results of the feasibility study for the Rainy Project being realized; (10) conditions of the El Morro sale; and the conditions to closing of Project Corridor being satisfied in a timely manner; and (ii) conditions to the payment of the remaining $75 million from Royal Gold being satisfied in mid-2016. Forward-looking statements are necessarily based on estimates and assumptions that are inherently subject to known and unknown risks, uncertainties and other factors that may cause actual results, level of activity, performance or achievements to be materially different from those expressed or implied by such forward-looking statements. Such factors include, without limitation: significant capital requirements and the availability and management of capital resources; additional funding requirements; price volatility in the spot and forward markets for metals and other commodities; fluctuations in the international currency markets and in the rates of exchange of the currencies of Canada and the United States; discrepancies between actual and estimated production, between actual and estimated reserves and resources and between actual and estimated metallurgical recoveries; changes in national and local government legislation in Canada, and the United States, or any other country in which New Gold currently or may in the future carry on business; taxation; controls, regulations and political or economic developments in the countries in which New Gold does or may carry on business; the speculative nature of mineral exploration and development, including the risks of obtaining and maintaining the validity and enforceability of the necessary licenses and permits and complying with the permitting requirements of each jurisdiction in which New Gold operates, including, but not limited to: in Canada, obtaining the necessary permits for the Rainy River Project; delay or failure to receive regulatory approvals or the failure to satisfy other closing conditions to the El Morro sale or Project Corridor; the lack of certainty with respect to foreign legal systems, which may not be immune from the influence of political pressure, corruption or other factors that are inconsistent with the rule of law; the uncertainties inherent to current and future legal challenges New Gold is or may become a party to; diminishing quantities or grades of reserves and resources; competition; loss of key employees; rising costs of labour, supplies, fuel and equipment; actual results of current exploration or reclamation activities; uncertainties inherent to mining economic studies including the feasibility study for Rainy River; changes in project parameters as plans continue to be refined; accidents; labour disputes; defective title to mineral claims or property or contests over claims to mineral properties; unexpected delays and costs inherent to consulting and accommodating rights of First Nations and other Aboriginal groups; uncertainties with respect to obtaining all necessary surface and other land use rights or tenure for Rainy River; risks, uncertainties and unanticipated delays associated with obtaining and maintaining necessary licenses, permits and authorizations and complying with permitting requirements; and not realizing the potential benefits of the El Morro sale. In addition, there are risks and hazards associated with the business of mineral exploration, development and mining, including environmental events and hazards, industrial accidents, unusual or unexpected formations, pressures, cave-ins, flooding and gold bullion losses (and the risk of inadequate insurance or inability to

  • btain insurance to cover these risks) as well as “Risk Factors” included in New Gold’s disclosure documents filed on and available at www.sedar.com.

Forward-looking statements are not guarantees of future performance, and actual results and future events could materially differ from those anticipated in such statements. All of the forward- looking statements contained in this presentation are qualified by these cautionary statements. New Gold expressly disclaims any intention or obligation to update or revise any forward-looking statements whether as a result of new information, events or otherwise, except in accordance with applicable securities laws. The footnotes, endnotes and appendices to this presentation contain important information. The endnotes and appendices are found at the end of the presentation.

slide-3
SLIDE 3

Site visit agenda – September 15, 2015

8:00am SAFETY ORIENTATION 8:30am PRESENTATION 10:30am SITE TOUR 12:30pm LUNCH 1:00pm Q&A / CORE DISPLAY 3:00pm DEPART SITE / END OF VISIT

3

slide-4
SLIDE 4

Presentation agenda

INTRODUCTION RANDALL OLIPHANT GEOLOGY AND EXPLORATION MARK PETERSEN DEVELOPMENT PLAN PAUL HOSFORD OPERATIONAL READINESS GRANT GODDARD LIFE-OF-MINE PLAN OVERVIEW RYAN HOEL PROCESSING DAVE HALL CORPORATE SOCIAL RESPONSIBILITY / FIRST NATIONS BOB GALLAGHER SUMMARY RANDALL OLIPHANT

4

slide-5
SLIDE 5

Rainy River overview

  • Low-risk, mining-friendly jurisdiction
  • 100%-owned large land package totalling
  • ver 190 square kilometres
  • High-quality, long-life open pit and

underground mine

  • 17 kilometre tie-in to power and close to

regional infrastructure

  • Supportive local government and community
  • 3.8 million ounce gold reserve(1) with

continued exploration upside

RAINY RIVER PROJECT

Construction commenced in May 2015; start-up targeted mid-2017

RAINY RIVER PROJECT

ONTARIO, CANADA

5

  • 1. For a detailed breakdown of mineral resources and reserves by category and the key assumptions and parameters, refer to Appendix 1. Refer to Endnotes under the heading “Cautionary note to U.S. readers concerning estimates of mineral

reserves and mineral resources” and “Technical Information”.

slide-6
SLIDE 6

Rainy River quick facts

Operations Annual Production(3) Costs(3) Gold Reserve(1) and Mine Life Capital Targeted Start-up

  • 1. For a detailed breakdown of mineral resources and reserves by category and the key assumptions and parameters, refer to Appendix 1. Refer to Endnotes under the heading “Cautionary note to U.S. readers concerning estimates of mineral reserves and

mineral resources” and “Technical Information”.

  • 2. Current plan based on $1.25 C$/US$ foreign exchange rate. As at August 31, 2015.
  • 3. First nine years.
  • 4. Refer to Endnote on total cash costs under the heading “Non-GAAP Measures”.
  • 5. Refer to Endnote on all-in sustaining costs under the heading “Non-GAAP Measures”.

3.8 Moz

Gold reserve

$570per oz

Total cash costs(4)

$670per oz

All-in sustaining costs(5)

Open pit and underground 21,000 tonne per day process plant with conventional crushing, grinding, leaching and carbon-in-pulp technology

$733million

Remaining development capital(2)

Mid-2017 14 year

Base mine life

~$33million

Average sustaining capital per year(3)

~325 Koz

Gold production

~480 Koz

Silver production

3.3 Moz

at 1.5 g/t 6

Direct Processing Material

slide-7
SLIDE 7

Rainy River location and infrastructure

  • Located 65 kilometres

northwest of Fort Frances and approximately 160 kilometres south of Kenora

  • Town of Fort Frances has

a population of over 10,000 people

  • Established infrastructure

with year-round road access and power lines in close proximity

  • Accepted into the

Industrial Electricity Incentive Program ("IEI Stream 3") which enables the project to receive a reduction in electricity costs through the end of 2024

7

slide-8
SLIDE 8

Rainy River development – Management team

Bob Gallagher President & CEO

  • Over 40 years in the mining industry in leadership roles with Placer Dome,

Newmont Mining and Peak Gold

David Schummer EVP & COO

  • Over 25 years in the mining industry
  • Previously with Newmont Mining in multiple senior leadership roles

Mark Petersen VP Exploration

  • Over 30 years in minerals exploration and leadership roles
  • New Gold’s Qualified Person for mineral reserve and resource disclosure

Peter Marshall VP Project Development

  • 30 years of resource development experience
  • Previously with Terrane Metals and Placer Dome

Paul Hosford Project Director

  • 30 years of resource experience
  • Previously with Terrane Metals and Hatch

Grant Goddard General Manager

  • Over 30 years of mineral resource experience
  • Previously COO with TMAC Resources

Chris McGoldrick Construction Director

  • Over 35 years of construction and mining project development experience
  • Previously with Anglo American, Placer Dome and Inco

8

slide-9
SLIDE 9

Rainy River stream highlights

9 INCREASES FINANCIAL FLEXIBILITY PROVIDES ATTRACTIVE COST OF CAPITAL MINIMIZES IMPACT TO CONTINUED PROJECT UPSIDE MAXIMIZES EXPOSURE TO GOLD PRICE UPSIDE Secured 20% of total development capital for less than 6% of estimated future revenues(1)(2)(3) Increases project rate of return to equity holders by approximately 3%(1) Stream percentage reduced by 50% to 3.25% gold and 30% silver after threshold ounces(4) delivered Ongoing cash payments to New Gold at 25% of spot gold and silver prices

  • 1. Second instalment of $75 million is to be paid when 60% of development capital spent and other customary conditions are satisfied.
  • 2. Based on $877 million total development capital.
  • 3. Based on a gold price of $1,200/oz and silver price of $16/oz and first nine years of full production from 2018 through 2026.
  • 4. Threshold ounces defined as 230,000 gold ounces and 3.1 million silver ounces.
  • On July 20, 2015 New Gold announced a $175 million streaming transaction with Royal Gold on

future gold and silver production from Rainy River

IRR TO ROYAL GOLD

Gold Price ($/oz) Silver Price ($/oz) $1,100 $14.00 $1,200 $16.00 $1,300 $18.00 IRR (%) 2.5% 3.7% 4.9%

slide-10
SLIDE 10

$327 $733 $175 $757 $65 $236

Rainy River funding

  • Stream proceeds of $175

million together with cash proceeds from El Morro transaction provide meaningful contribution towards funding Rainy River

  • Amount of free cash flow

generated over next two years to determine if any draw required on credit facility

  • 2014 sustaining free

cash flow(1) was $143 million

Liquidity Rainy River Development

Cash Balance June 30/15 Proceeds from Stream(3) Rainy River Remaining Development Capital(5)

  • 1. Sustaining free cash flow is equal to cash generated from operations less sustaining capital expenditures.
  • 2. El Morro cash proceeds net of tax. Completion of the El Morro transaction is subject to certain conditions.
  • 3. Second instalment of $75 million to be paid when 60% of development capital spent and other customary conditions are satisfied.
  • 4. As at June 30, 2015.
  • 5. As at August 31, 2015.

10

Proceeds from El Morro(2) Available Credit Facility Sustaining Free Cash Flow from Operations(1) Rainy River Remaining Development Capital(4)

slide-11
SLIDE 11

Financial analysis

$0.05 change in exchange rate

AFTER-TAX PROJECT ECONOMICS(1)

Gold Price ($/oz) $1,150 $1,200 $1,300 C$/US$ exchange 1.33 1.30 1.25 5% NPV ($mm) 428 462 604 IRR (%) 11.8 12.4 15.3 Payback (years) 5.9 5.7 4.9 $100 per ounce change in gold price

~$65mm ~1.4% ~$15mm ~$20/oz

After-tax NAV IRR Total Cash Costs(2) Development Capital

~$180mm ~3.9%

After-tax NAV IRR

  • 1. Net present value discounted to July 1, 2015, excludes sunk costs. IRR and payback period inclusive of all project development costs. Stream proceeds included as a net reduction to capital costs with future cash flow reduced by stream payment
  • bligations. Assumes second instalment of stream proceeds paid in 2016. Silver price assumption of $16/oz.
  • 2. Refer to Endnote on total cash costs under the heading “Non-GAAP Measures”.

11

slide-12
SLIDE 12

12

GEOLOGY AND EXPLORATION

Mark Petersen, VP Exploration

slide-13
SLIDE 13

Rainy River history

1967

First Exploration

1967 – 1989

Noranda, HudBay, Inco, Mingold

1988

OGS Map P3140 Gold Grains in Rotosonic Drill Core and Surface Samples (1987-1988)

1990

Nuinsco started exploration

1994

First diamond drill program discovered 17 Zone

1994 – 2004

BP, 433 zones discovered

2005

Rainy River Resources Ltd. purchased property

2006

ODM Zone discovered

2007

Cap Zone discovered

2008

First NI 43-101 Resource Completed

2012

PEA completed; discovery of Intrepid Zone

2013

New Gold acquired Rainy River Resources Ltd. Updated Resource Estimate

2014

Environmental assessment report submitted New Gold completed updated Feasibility Study

2015

Environmental approvals for Rainy River received and construction commenced

13

slide-14
SLIDE 14

Superior province gold districts

From Poulsen et al. (2000)

14 Moz produced 28 Moz total endowment

7+ Moz

QFZ

14

Porcupine

slide-15
SLIDE 15

Property ownership and known gold prospects

RR ODM claim block RR Off Lake claim block Mine Development Area

New Gold exploration prospects

15

slide-16
SLIDE 16

Mine Development Areas

Local geology and gold resources

16

slide-17
SLIDE 17

Mine stratigraphy

Massive to pillowed mafic flows Massive to amygdaloidal Dacite flows

CAP ODM HS 433

17

slide-18
SLIDE 18

Mineral reserves – Looking north

Bayfield Extensions

Rainy River Mineral Reserves Summary(1)

as at December 31, 2014 Proven & Probable Reserves Tonnes 000’s Gold g/t Silver g/t Gold Koz Silver Koz

Open pit 62,705 1.31 2.8 2,642 5,632 Underground 4,187 4.96 10.3 668 1,388 Stockpile 37,384 0.39 2.0 462 2,390 Total P&P 104,276 1.13 2.8 3,772 9,410

Bayfield extensions are not included in current mineral reserves for Rainy River.

18

  • 1. For a detailed breakdown of mineral resources and reserves by category and the key assumptions and parameters, refer to Appendix 1. Refer to Endnotes under the heading “Cautionary note to U.S. readers concerning estimates of mineral

reserves and mineral resources” and “Technical Information”.

$800 per ounce optimized pit shell

slide-19
SLIDE 19

M&I (yellow) and Inferred (pink) >1.0 gpt Au View looking North

Resource upside

Rainy River Mineral Resources Summary(1)

as at December 31, 2014

Measured & Indicated Resources Tonnes 000’s Gold g/t Silver g/t Gold Koz Silver Koz Open pit 40,315 1.31 3.5 1,696 4,483 Underground 5,595 3.99 15.2 718 2,728 Stockpile 35,350 0.42 2.5 482 2,788 Total M&I 81,260 1.11 3.8 2,896 9,999 Inferred Resources 18,088 1.10 4.0 637 2,336

19

  • 1. For a detailed breakdown of mineral resources and reserves by category and the key assumptions and parameters, refer to Appendix 1. Refer to Endnotes under the heading “Cautionary note to U.S. readers concerning estimates of mineral

reserves and mineral resources” and “Technical Information”. Mineral resources are exclusive of reserves.

Reserve pit shell MI&I resource pit shell

slide-20
SLIDE 20

Mineral reserves and resources summary(1)

GOLD SILVER

  • 1. For a detailed breakdown of mineral resources and reserves by category and the key assumptions and parameters, refer to Appendix 1. Refer to Endnotes under the heading “Cautionary note to U.S. readers concerning estimates of mineral

reserves and mineral resources” and “Technical Information”. Mineral resources are exclusive of reserves.

Open Pit Direct Processing 1.3 g/t Open Pit Direct Processing 1.3 g/t Open Pit Direct Processing 2.8 g/t Open Pit Direct Processing 3.5 g/t Underground Direct Processing 5.0 g/t Underground Direct Processing 4.0 g/t Underground Direct Processing 10.3 g/t Underground Direct Processing 15.2 g/t

3.8 Moz 9.4 Moz 2.9 Moz 10.0 Moz 0.6 Moz 2.3 Moz

20

Open Pit Direct Processing Underground Direct Processing Stockpile Stockpile Stockpile Stockpile

Stockpile

slide-21
SLIDE 21
  • Large contiguous land position
  • 190 square kilometres
  • Primary deposits and mineral resources well

defined:

  • Over 2,000 drill holes
  • Over 1,000,000 metres of diamond drilling
  • Over 500,000 assays
  • Average 35 metre drill hole spacing
  • Proven & Probable reserves(1):
  • 3.8 Moz gold
  • 9.4 Moz silver
  • Measured & Indicated resources (exclusive of

reserves)(1):

  • 2.9 Moz gold
  • 10.0 Moz silver
  • Excellent long-term exploration upside
  • Rainy River district is a direct analog to the

prolific Doyon-Bousquet-LaRonde gold-rich VMS camp in the central Abitibi belt

Summary

  • Identify and test potential for new

mineralized horizons with focus on potential higher grade upside

  • 2015 exploration budget
  • $1.8 million mine development

area

  • $4.2 million broader district

holdings

NEAR-TERM FOCUS

  • District scale prospectivity recognized in

multiple areas

  • Rainy River VMS stratigraphy

trend extensions to east and west

  • Off Lake orogenic gold veins

FURTHER POTENTIAL 21

  • 1. For a detailed breakdown of mineral resources and reserves by category and the key assumptions and parameters, refer to Appendix 1. Refer to Endnotes under the heading “Cautionary note to U.S. readers concerning estimates of mineral

reserves and mineral resources” and “Technical Information”. Mineral resources are exclusive of reserves.

slide-22
SLIDE 22

23

DEVELOPMENT PLAN

Paul Hosford, Project Director

slide-23
SLIDE 23

Infrastructure

slide-24
SLIDE 24

Rainy River development – Milestones completed

All major construction permits received. Schedule 2 permit expected H1’2016 All land purchases complete Temporary Accommodations Facility complete and 416 beds available Engineering and procurement complete All mechanical, electrical, instrumentation equipment purchased Execution commenced for Bulk Earthworks, Concrete Supply and Install, Steel Supply/Install, Highway 600 Road Relocation and Water Management Earthworks Construction (3 packages), East Access Road, Temporary Buildings, Steel tanks and Pinewood Water Supply System Contracts tendered for 230kV transmission line, Tailings Management Area (TMA), HV substation and the major mechanical/piping/electrical/instrumentation (MPEI) packages Initial mine fleet assembly commenced Operations team recruitment in progress Developed on-site quarries for aggregate material supply ACHIEVED TO DATE 24

slide-25
SLIDE 25

Rainy River development – 2015 year-end targets

Project construction completion progressed to approximately 25% Award remaining major contracts Complete Highway 600 road realignment and East Access Road Complete plant site earthworks Complete grinding building foundations and erect steel building Primary crusher structure approximately 50% complete Complete water management earthworks diversions and facilities, and starter water management pond Commence open pit pre-stripping and haul road build out Complete manufacture and delivery of Ball and SAG mills PLANNED BY END OF YEAR 25

slide-26
SLIDE 26

Rainy River timeline

2014 2015 2016 2017 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2

Complete Feasibility Study Submit Environmental Assessment Report Order Long Lead Equipment Award EPCM Contract Detailed Engineering & Procurement Provincial Environmental Assessment Approval Federal Environmental Assessment Approval Process Plant Construction Tailings & Water Management Facilities Construction Delivery of Pre-Stripping Mine Equipment Power Line Construction Commence Pre-Strip & Pit Development Commissioning

Targeted milestones

Mid-2017 – Start-up and Commissioning

26

slide-27
SLIDE 27

Description ($mm) Direct Costs Mining 157 On-Site Infrastructure 88 Process Plant 298 Tailings Facility 61 Access Corridor 16 Off-Site Facilities 22 Total Direct Capital Costs 641 Owner's and Indirect Costs Other Indirects 150 Owner's Costs 87 Total Owner's & Indirect Capital Costs 237 Total Project $877

PROJECT DEVELOPMENT CAPITAL COSTS(1)(2)

  • 1. Current plan based on $1.25 C$/US$ foreign exchange rate. Contingency has been distributed across the cost items.
  • 2. Numbers may not add due to rounding.
  • 3. As at August 31, 2015.

Rainy River development capital breakdown

$0.05 change in exchange rate equals

~$15 million change in development capital

REMAINING DEVELOPMENT CAPITAL(3) $733 million SPENT TO DATE(3) $144 million

16%

SPENT TO DATE

27

slide-28
SLIDE 28

Rainy River – Committed to date(1)

28

Description Estimate Total Spent / Committed Direct Costs Mining 157 68 On-Site Infrastructure 88 49 Process Plant 298 187 Tailings Facility 61 20 Access Corridor 16 10 Off-Site Facilities 22 3 Total Direct Capital Costs 641 337 Owner's and Indirect Costs Other Indirects 150 86 Owner's Costs 87 57 Total Owner's & Indirect Capital Costs 237 143 Total Project $877 $480

PROJECT DEVELOPMENT CAPITAL COSTS ($mm)(2)(3)

~55% of total capital

spent/committed to date

  • 1. As at August 31, 2015.
  • 2. Current plan based on $1.25 C$/US$ foreign exchange rate. Contingency has been distributed across the cost items.
  • 3. Numbers may not add due to rounding.

SPENT TO DATE(1)

$144 million

FIXED PRICE AND QUANTITIES

$134 million

FIXED UNIT PRICES, VARIABLE QUANTITIES

$202 million

Detailed engineering 100% complete

slide-29
SLIDE 29

 Finalize detailed control estimate and schedule  Tender, award and execute site clearing  Prepare and award major civil works contracts

  • Complete plant site, infrastructure and water

management earth works

  • Construct Highway 600 realignment and mine

access road

  • Construct mill building foundation
  • Commission first phase of mine fleet
  • Commence prestripping

2015 CAPITAL EXPENDITURE DETAILS 2015 PROGRAM

($mm)

Process plant $84 Mining 52 Indirects 27 On-site infrastructure 27 Owners costs 22 Accommodation facility 21 Tailings facilities 15 Access corridor 13 Off-site facilities 13 Construction management services 5 Contingency/escalation 21 Total $300

Rainy River 2015 capital expenditure and project plan

29

slide-30
SLIDE 30

Site construction images

Grinding Building Primary Crusher Foundation Highway 600 Realignment Primary Crusher Foundation

30

slide-31
SLIDE 31

Site construction images

Ball Mill Foundation West Creek Diversion Treatment Pond Plant site area - 20,000 cubic metres of rock blasted Kitchen at the camp Additional Precast

31

slide-32
SLIDE 32

32

OPERATIONAL READINESS

Grant Goddard, General Manager

slide-33
SLIDE 33

Operational readiness

  • What is the operations “project plan”?
  • Guiding the day-to-day work of the
  • perations
  • Linkages of construction activities and
  • verall project schedule
  • Is not “added work” but “the work”

A thoughtful, planned process of managing the many activities necessary to be executed to assure a successful operational start-up and sustainable mining operation

33

slide-34
SLIDE 34

Operations team

Doug Desaulniers Maintenance Manager Dave Hall Mill Manager Ryan Hoel Mine Manager Ann Wallin HR Manager Velibor Petric Finance Manager Sarah Thompson Materials Manager Peta Risojevic Health & Safety Manager Nigel Fisher Environment Manager Chris Reeves Business Development Manager Stacey Jack Community Affairs Manager Grant Goddard General Manager

OPERATIONS TEAM OPERATIONS SUPPORT TEAM

Key operations team members in place

34

slide-35
SLIDE 35

Key workstreams

Organizational Readiness Health & Safety Environmental Communities Training Human Resources Mining Processing Asset Management Procurement & Contracts Finance & Cost Management Commissioning, Ramp Up and Handover Business & Technical Systems Internal Communications Sales Knowledge Management Continuous Improvement Transition & Closeout

HOW DO WE PLAN FOR WORKSTREAMS?

  • Workshops focusing on what activities we

need to accomplish and when to ensure we are ready for “Go Live”

  • Outputs of the workshops are inputs into the

detailed operations work plan and milestone schedule

  • Integrate the plan and schedule with

construction

  • Development of critical actions register
  • Weekly management of work streams to

ensure effective risk management

  • Use of a “War Room” to keep information

relevant and transparent

  • Periodic re-visit of milestones/activities, as

field/execution/project evolves

35

slide-36
SLIDE 36

36

LIFE-OF-MINE PLAN OVERVIEW

Ryan Hoel, Mine Manager

slide-37
SLIDE 37

37

Site layout

West Mine Rock Stockpile East Mine Rock Stockpile

slide-38
SLIDE 38

Open pit illustration LOOKING SOUTH WEST

38

slide-39
SLIDE 39

Current mining fleet and equipment

Hauling and loading equipment

  • 6 – Komatsu 830E 218t (haul trucks)
  • 2 – Komatsu PC5500 26m3 (hydraulic

shovels)

  • 1 – Komatsu WA1200 18m3 (large wheel

loader)

  • 3 – Komatsu D375/D475 (dozers)

Drills

  • 2 – Sandvik DR580 (blasthole drills)

Next major deliveries – Q4’2015

  • 2 – Cat 16M (graders)
  • 1 – Komatsu 830E 218t (haul truck)

39

slide-40
SLIDE 40

Open pit design

Reserves(1) Ore tonnage Mt 100

Including Stockpile Excluding Stockpile

Au grade g/t 1.0 1.3 Ag grade g/t 2.6 2.8 Au koz 3,104 Ag koz 8,022 Waste tonnage Mt 320 Overburden Mt 72

Open pit mine design based on:

  • Updated block model:

10m x 10m x 10m

  • Truck and Hydraulic Shovel
  • 2 Year pre-production
  • 9 Year mine life plus stockpile

Phase 1 (2015 – 2020) Phase 2 (2018 – 2022) Phase 3 (2021 – 2025) North

40

  • 1. For a detailed breakdown of mineral resources and reserves by category and the key assumptions and parameters, refer to Appendix 1. Refer to Endnotes under the heading “Cautionary note to U.S. readers concerning estimates of mineral

reserves and mineral resources” and “Technical Information”.

slide-41
SLIDE 41
  • Primary mobile equipment fleet will move 68 Mtpy of ore, waste and
  • verburden at peak production rates

Equipment Model Units Required During Development Currently At Site Haul trucks Komatsu 830E 218t 22 8 6 Hydraulic shovels (diesel) Komatsu PC5500 26m3 2 2 2 Hydraulic shovel (electric) Komatsu PC7000 29m3 1 Large wheel loader Komatsu WA1200 18m3 1 1 1 Blasthole drills Sandvik DR580 3 2 2 Dozers Komatsu D375 6 4 3 Graders Cat 16M 3 2

Open pit equipment

41

slide-42
SLIDE 42

Open pit mining and milling schedule

10,000 20,000 30,000 40,000 50,000 60,000 70,000 2017 2018 2019 2020 2021 Ore Waste Overburden MINING SCHEDULE – FIRST FIVE YEARS (KT)

Strip Ratio

3.9 3.3 4.0 4.1 4.8

2,000 4,000 6,000 8,000 10,000 12,000 14,000 2017 2018 2019 2020 2021 Open pit ore to mill Open pit ore to stockpile MILLING SCHEDULE – FIRST FIVE YEARS (KT)

  • Avg. grade to

mill (g/t)

  • Avg. grade to

stockpile (g/t)

0.4 1.5 0.4 1.5 0.4 1.4 0.4 1.4 0.4 1.3 Planned three year ramp up to full mining capacity

(1)

  • 1. Mining of waste/overburden expected to commence early-2016.

42

slide-43
SLIDE 43

Open pit mining cost

BREAKDOWN OF OPEN PIT MINING COST PER TONNE

OTHER (1%) BLASTING (11%) FUEL AND ELECTRICITY (30%) EQUIPMENT OPERATING COST (INCLUDING MAINTENANCE) (32%) LABOUR (26%)

Significant Canadian dollar exposure

~70%

Diesel price assumption

$0.95 per litre

43

C$2.15 /t mined

Current diesel price ~$0.60 per litre

slide-44
SLIDE 44

Underground design

  • 1,500 tpd longhole open stope mine

with backfill

  • 10 year mine life with potential to

expand at depth

Reserves(1) Ore tonnage Mt 4.2 Au grade g/t 5.0 Ag grade g/t 10.3 Au koz 668 Ag koz 1,388 44

  • 1. For a detailed breakdown of mineral resources and reserves by category and the key assumptions and parameters, refer to Appendix 1. Refer to Endnotes under the heading “Cautionary note to U.S. readers concerning estimates of mineral

reserves and mineral resources” and “Technical Information”.

slide-45
SLIDE 45

Underground mine plan ODM West ODM Main Upper ODM Main Lower 433 Zone ODM East 17 East Upper 17 East Lower Intrepid Lower Intrepid Upper

Bayfield Burns Block

(‘under development’)

45

slide-46
SLIDE 46

Underground equipment

  • Underground development scheduled to begin once production from open pit commences
  • Primary equipment fleet will mine 1,500 tpd of ore at full production rates

Equipment Specification Units Required During Underground Development Jumbo drill Sandvik DD421 3 2 Load-Haul-Dump Loader Cat R2900 4 2 Haul Truck Cat AD45 6 4 Mechanized Bolter Sandvik DS411 2 2 Production Long Hole Drill Sandvik DL431 2 Face Charger, Explosives Loader Normet Charmec MF 605 2 2 Production Explosives Loader Bulk Modules 1 Shotecrete Sprayer Normet Spraymec 1050WP 1 1 Transmixer Normet Ultimec LF600 1 1

46

slide-47
SLIDE 47

Underground mining schedule

100 200 300 400 500 600 2019 2020 2021 2022 2023 MINING SCHEDULE – FIRST FIVE YEARS (KT)

  • Underground development scheduled to begin once production from open pit commences
  • 23 months development to first underground ore - $115 million capital costs

31.6 4.5 32.3 4.8 18.3 5.3 7.7 5.4 5.0 5.3

Five year ramp up assumed to full production

Gold grade (g/t) Silver grade (g/t)

47

slide-48
SLIDE 48

Underground cost

BREAKDOWN OF UNDERGROUND COST PER TONNE

OTHER (7%) BLASTING (3%) EQUIPMENT OPERATING COST (INCLUDING MAINTENANCE) (32%) LABOUR (45%) FUEL AND ELECTRICITY (13%)

Significant Canadian dollar exposure

~70%

48

C$90.62 /t mined

slide-49
SLIDE 49

Mill feed schedule

1,000 2,000 3,000 4,000 5,000 6,000 7,000 8,000 2017 2018 2019 2020 2021 Open pit ore to mill Underground ore to mill MILL FEED SCHEDULE – FIRST FIVE YEARS (KT)

Average Mill Head Grade (g/t)

Underground Grade (g/t) Open Pit Grade (g/t)

1.5 1.5 1.5 1.5 1.5

1.5

  • 1.5
  • 1.4

4.5 1.4 4.8 1.3 5.3

49

slide-50
SLIDE 50

Gold production profile

50 100 150 200 250 300 350 2017 2018 2019 2020 2021 Open Pit Underground

~325 Koz

50

GOLD PRODUCTION PROFILE – FIRST FIVE YEARS (Koz)

slide-51
SLIDE 51

51

PROCESSING

Dave Hall, Mill Manager

slide-52
SLIDE 52

RECLAMATION ◊ Buildings are removed ◊ Local Vegetation is planted

  • ver stock piles

◊ Tailings Management Area is turned into a lake ◊ Open Pit fills with water Schematic process flow sheet

52

slide-53
SLIDE 53

Process plant design

PROCESS DESIGN CRITERIA

  • Axb = 24.2
  • Bond work index = 15.0
  • Crusher work index = 25.0
  • 80th percentile BWI & Axb used for mill

design

  • Life-of-mine recovery
  • Gold ~91%
  • Silver ~63%

MAJOR PROCESS EQUIPMENT

  • Crusher: 55” x 83”; 600 kW (800 HP)
  • Coarse ore stockpile – 60,000 tonnes

with 20,000 tonne live storage

  • SAG Mill: 36’ x 20’; 15 MW (20,000 HP)

variable speed

  • Ball Mill: 26’ x 40.5’; 15 MW (20,000 HP)

variable speed

  • P80 = 75 micron target grind
  • Pebble Crusher: 448 kW (600 HP)
  • Leach Tanks: 8 x 18 m Ø, 30-hour leach
  • CIP Tanks: 7 x 330 m3
  • Two Cyanide Destruction tanks: 11.5 Ø,

1.5-hour retention

53

slide-54
SLIDE 54

Mill sizing

  • Over 400 comminution tests were conducted covering a large cross section of the pit and ore types
  • 3.5 tests per million tonnes versus industry standard of one test per million tonnes
  • SAG mill design was based on the 80th percentile A x b values; industry standard is 75th percentile
  • Circuit was designed using three independent sizing methods (Starkey, OMC, and Morrel) with

excellent correlation

  • Mill motor and drive combination will provide the power draw required to process the ore at 84% of

the available power; industry standard is 88% to 90%

  • Design parameters were reviewed and endorsed by an independent third party industry expert
  • Gyratory and pebble crusher both have sufficient horsepower that could be used for additional

throughput and/or finer crush sizes – this would allow additional grinding throughput

  • Ball Mill has sufficient grinding power as the drive was selected to maintain common mill drive spares

54

Appropriate size mills and drives in place, secondary crushing not required to reach nameplate throughput

slide-55
SLIDE 55

Processing plant

55

slide-56
SLIDE 56

Processing cost

56 BREAKDOWN OF PROCESSING COST PER TONNE MILLED

OTHER(1) (14%) LABOUR (18%) PROPANE AND ELECTRICITY (22%) REAGENTS (24%) GRINDING MEDIA AND LINERS (22%)

C$9.01

Significant Canadian dollar exposure

~80%

Current power cost assumption

$0.045/kWh

Further reduction in electricity costs anticipated through 2024 as part of IEI Stream 3

  • 1. Includes: Maintenance, transportation and water treatment.
slide-57
SLIDE 57

57

CORPORATE SOCIAL RESPONSIBILITY / FIRST NATIONS

Bob Gallagher, President and CEO

slide-58
SLIDE 58

Benefits to community

  • 400 construction and 600 operations

phase jobs estimated – Currently employ ~80 people with 50% hired locally – Operations team consists of ~50% local hires and 16% members of Aboriginal groups

  • Annual indirect and induced

employment in Ontario during

  • perations is expected to total

approximately 600 and 575 jobs, respectively

  • When added to direct employment for

the Rainy River project, total direct and indirect employment in Ontario as a result of the operation phase is approximately 2,000 jobs per year

  • Estimated gross annual mine payroll
  • f $45 – $50 million per year

ECONOMIC CONTRIBUTIONS(1)

  • 1. Based on 2015 PriceWaterhouse Cooper Report – “Economic and Social Impact of New Gold Inc.'s Ontario Operations” prepared for New Gold.

DIRECT AND INDIRECT GDP IMPACT OF NEW GOLD IN ONTARIO

Indirect Direct

$31.4 MILLION $401.1 MILLION

58

slide-59
SLIDE 59

First Nations communities

59

slide-60
SLIDE 60

Community engagement

We have been an active and engaged member of the community and have a number of successes and initiatives that show our commitment:

  • Four signed Participation Agreements with

local Aboriginal Groups

  • Productive, ongoing discussions with four

additional First Nations

  • Contributions of nearly $100,000 to the local

district through donations, sponsorships and scholarships

  • Established two local New Gold offices, one in

Emo and a second in Thunder Bay – with

  • pen door policies for questions and feedback
  • Established multiple First Nations joint

ventures with non Aboriginal contractors

  • Initiated a Supplier Request for Information to

source locally wherever possible

  • New Gold continues to have progressive

relationships with each of these communities

60

slide-61
SLIDE 61

SUMMARY

Randall Oliphant, Executive Chairman

61

slide-62
SLIDE 62

Rainy River – Where are we today

  • Permits to enable commencement of major

earthworks construction received in May

  • Detailed engineering complete
  • Construction-related activities progressing
  • n schedule
  • Temporary accommodation facility

complete with 416 beds operational

  • First major earthworks for process plant

site commenced and completed in May; mill building construction commenced

  • First concrete pour for primary crusher

foundation successfully completed in July; mill building foundation installation commenced in August

  • Delivery and assembly of initial mining fleet

commenced in August

  • Delivery of mills on schedule for late 2015

62

slide-63
SLIDE 63

Rainy River summary

  • 1. Based on 2015 Behre Dolbear Report – “2015 Ranking of Countries for Mining Investment”.
  • 2. For a detailed breakdown of mineral resources and reserves by category and the key assumptions and parameters, refer to Appendix 6. Refer to Endnotes under the heading “Cautionary note to U.S. readers concerning estimates of mineral reserves

and mineral resources” and “Technical Information”. Mineral resources are exclusive of reserves.

  • 17km tie-in to power and close to

regional infrastructure

  • Land package over 190 square

kilometres

  • Supportive local government and

community

JURISDICTION RESOURCE SCALE(2)

Ontario, Canada

GOLD RESERVES

3.1Moz at 1.0g/t

OPEN PIT UNDERGROUND

0.7Moz at 5.0g/t

3.8 Moz

#1

GOLD M&I RESOURCES

2.2Moz at 0.9g/t

OPEN PIT UNDERGROUND

0.7Moz at 4.0g/t

2.9 Moz

Construction activities remain on time and on budget

63

slide-64
SLIDE 64

Rainy River summary (cont’d)

  • 1. As at August 31, 2015.
  • 2. Current plan based on $1.25 C$/US$ foreign exchange rate.

START-UP / COMMISSIONING REMAINING DEVELOPMENT CAPITAL ESTIMATE(1)(2) 2015 CAPITAL SPEND ESTIMATE(2)

Mid-2017

  • $144 million spent through

August 31, 2015

$733million

  • ~80% in Canadian dollars

$300million

64

slide-65
SLIDE 65

Rainy River cost profile

  • ~80% in Canadian dollars

65

Description (C$ per tonne milled) ($ per gold ounce produced) Direct Costs Open pit mining 10.26 338 Underground mining 3.65 Processing 9.01 219 General and administrative 1.80 44 Royalties 0.67 20 Refining and transport 0.12 3 Cash costs 25.51 624 Silver by-product sales at $16.00 per ounce silver (0.98) (24) Total cash costs(1) 24.53 600 Sustaining capital 4.12 100 All-in sustaining costs(2) 28.65 700

BREAKDOWN OF OPERATING COSTS(1)

  • 1. Refer to Endnote on total cash costs under the heading “Non-GAAP Measures”. Current plan based on $1.25 C$/US$ foreign exchange rate and $16/oz silver price.
  • 2. Refer to Endnote on all-in sustaining costs under the heading “Non-GAAP Measures”. Current plan based on $1.25 C$/US$ foreign exchange rate and $16/oz silver price.
  • Mining costs are projected to be C$2.15 per tonne of material for the open pit and

C$90.62 per tonne of material for the underground

  • Costs per tonne milled over the life-of-mine are summarized below:
slide-66
SLIDE 66

Strong balance sheet

66

  • 1. Cash and equivalents as at June 30, 2015.
  • 2. $64 million of $300 million facility used for Letters of Credit at June 30, 2015.
  • 3. Second instalment of $75 million to be paid when 60% of development capital spent and other customary conditions are satisfied.
  • 4. El Morro cash proceeds of $90 million less taxes. Completion of the El Morro transaction is subject to certain conditions. Refer to Appendix 5.

$803million

LIQUIDITY POSITION

$236 million

UNDRAWN CREDIT FACILITY(2) CASH AND EQUIVALENTS(1)

$327 million

ONGOING SUSTAINING FREE CASH FLOW GENERATION

$175 million

PROCEEDS FROM STREAMING TRANSACTION(3)

~$65 million

NET CASH PROCEEDS FROM EL MORRO TRANSACTION(4)

slide-67
SLIDE 67

Future opportunities

INTEGRATION OF BAYFIELD MINERAL RESOURCES RESOURCES OPEN AT DEPTH – INCREASED UNDERGROUND MINE POTENTIAL UPSIDE POTENTIAL ON MILL THROUGHPUT REGIONAL RESOURCE PROSPECTIVITY

67

slide-68
SLIDE 68

Rainy River impact

  • 1. For a detailed breakdown of mineral resources and reserves by category and the key assumptions and parameters, refer to Appendix 1. Refer to Endnotes under the heading “Cautionary note to U.S. readers concerning estimates of mineral reserves

and mineral resources” and “Technical Information”.

  • 2. First nine years.
  • 3. Refer to Endnote on total cash costs under the heading “Non-GAAP Measures”. First nine years.
  • 4. Refer to Endnote on all-in sustaining costs under the heading “Non-GAAP Measures”. First nine years.
  • 5. Net present value discounted to July 1, 2015, excludes sunk costs. IRR inclusive of all project development costs. Stream proceeds included as a net reduction to capital costs. At spot prices of: Gold - $1,150/oz, Silver - $16/oz; C$/US$ - $1.33.

68

GOLD RESERVES(1)

3.8Moz

MINE LIFE

14 years

AVERAGE PRODUCTION(2)

~325,000

TOTAL CASH COSTS(3)

~$570/oz

ALL-IN SUSTAINING COSTS(4)

~$670/oz

REMAINING DEVELOPMENT CAPITAL

$733 million

NET PRESENT VALUE(5)

$428 million

IRR(4)

11.8%

JOB CREATION

~600

slide-69
SLIDE 69

THANK YOU

New Gold Team

slide-70
SLIDE 70

Appendix

70

slide-71
SLIDE 71

Mineral reserves

71 Mineral Reserves estimate as at December 31, 2014

Tonnes 000s Gold g/t Silver g/t Copper % Gold Koz Silver Koz Copper Mlbs RAINY RIVER Direct processing material Open Pit Proven 15,839 1.47 2.0

  • 746

1,038

  • Probable

46,866 1.26 3.1

  • 1,896

4,594

  • Open Pit P&P (direct processing)

62,705 1.31 2.8

  • 2,642

5,632

  • Underground

Proven

  • Probable

4,187 4.96 10.3

  • 668

1,388

  • Underground P&P (direct processing)

4,187 4.96 10.3

  • 668

1,388

  • Stockpile material

Open Pit Proven 6,843 0.38 1.5

  • 84

332

  • Probable

30,541 0.39 2.1

  • 378

2,058

  • Open Pit P&P (stockpile)

37,384 0.39 2.0

  • 462

2,390

  • Total P&P

Proven 22,682 1.14 1.9

  • 830

1,370

  • Probable

81,594 1.12 3.1

  • 2,942

8,040

  • Total Rainy River P&P

104,276 1.13 2.8

  • 3,772

9,410

  • Metal grade

Contained metal

slide-72
SLIDE 72

Mineral resources

72 Measured and Indicated Mineral Resource estimate (exclusive of Reserves) as at December 31, 2014

Tonnes 000s Gold g/t Silver g/t Copper % Gold Koz Silver Koz Copper Mlbs RAINY RIVER Direct processing material Open Pit Measured 3,416 1.35 1.8

  • 148

199

  • Indicated

36,899 1.30 3.6

  • 1,548

4,284

  • Open Pit M&I (direct processing)

40,315 1.31 3.5

  • 1,696

4,483

  • Underground

Measured

  • Indicated

5,595 3.99 15.2

  • 718

2,728

  • Underground M&I (direct processing)

5,595 3.99 15.2

  • 718

2,728

  • Stockpile material

Open Pit Measured 1,232 0.35 1.2

  • 14

49

  • Indicated

34,118 0.43 2.5

  • 468

2,739

  • Open Pit M&I (stockpile)

35,350 0.42 2.5

  • 482

2,788

  • Total M&I

Measured 4,648 1.08 1.7

  • 162

248

  • Indicated

76,612 1.11 3.9

  • 2,734

9,751

  • Total Rainy River M&I

81,260 1.11 3.8

  • 2,896

9,999

  • Metal grade

Contained metal

slide-73
SLIDE 73

Mineral resources (cont’d)

73 Inferred Resource estimate as at December 31, 2014

Tonnes 000s Gold g/t Silver g/t Copper % Gold Koz Silver Koz Copper Mlbs RAINY RIVER Direct processing Open Pit 7,785 0.82 2.7

  • 206

665

  • Underground

2,609 4.20 7.6

  • 352

635

  • Total Direct Processing

10,394 1.67 3.9

  • 558

1,300

  • Stockpile

Open Pit 7,694 0.32 4.2

  • 79

1,036

  • Total Rainy River Inferred

18,088 1.10 4.0

  • 637

2,336

  • Metal grade

Contained metal

slide-74
SLIDE 74

1) New Gold’s Mineral Reserves and Mineral Resources have been estimated in accordance with the CIM Standards, which are incorporated by reference in NI 43-101. 2) For year-end 2014 mineral reserves for the Company’s mineral properties have been estimated based on the following metal prices and lower cut-off criteria: Mineral Property Gold (US$/oz) Silver (US$/oz) Copper (US$/lb) Lower Cut-off Rainy River $1,200 $18.00

  • Open Pit Direct Processing: 0.30 – 0.70 g/t AuEq

Open Pit Stockpile: 0.30 g/t AuEq Underground: 3.50 g/t AuEq

Reserves and resources notes

3) New Gold reports its Measured and Indicated Mineral Resources exclusive of Mineral Reserves. Measured and Indicated Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability. Inferred Mineral Resources have a greater amount of uncertainty as to their existence, economic and legal feasibility, do not have demonstrated economic viability, and are likewise exclusive of Mineral Reserves. 4) Year-end 2014 Mineral Resources for the Company’s mineral properties (other than the Mineral Resource estimates for the Rainy River Project and Blackwater Project, which are effective March 10, 2015) have been estimated based on the following metal prices and lower cut-off criteria: 5) Mineral Resources are classified as Measured, Indicated and Inferred and are reported based on technical and economic parameters consistent with the methods most suitable for their potential commercial exploitation. Where different mining and/or processing methods might be applied to different portions of a Mineral Resource, the designators ‘open pit’ and ‘underground’ have been applied to indicate envisioned mining method. Likewise the designators ‘oxide’, ‘non-oxide’ and ‘sulphide’ have been applied to indicate the type of mineralization as it relates to appropriate mineral processing method and expected payable metal recoveries. Mineral Reserves and Mineral Resources may be materially affected by environmental, permitting, legal, title, taxation, sociopolitical, marketing and other risks and relevant issues. Additional details regarding Mineral Reserve and Mineral Resource estimation, classification, reporting parameters, key assumptions and associated risks for each of New Gold’s material properties are provided in the respective NI 43-101 Technical Reports which are available at www.sedar.com. 6) All Mineral Resource and Mineral Reserve estimates for New Gold’s operating properties and El Morro Project are effective December 31, 2014. For the Rainy River and Blackwater Projects, the Mineral Resource estimates are effective March 10, 2015 and the Mineral Reserve estimates are effective December 31, 2014. For the Rainy River Project, the Mineral Resource estimate reflects New Gold’s acquisition of Bayfield, which was effective January 1, 2015. Mineral Property Gold (US$/oz) Silver (US$/oz) Copper (US$/lb) Lower Cut-off Rainy River $1,300 $20.00

  • Open Pit Direct Processing: 0.30 – 0.45 g/t AuEq

Open Pit Stockpile: 0.30 g/t AuEq Underground: 2.50 g/t AuEq

74

slide-75
SLIDE 75

Endnotes

CAUTIONARY NOTE TO U.S. READERS CONCERNING ESTIMATES OF MINERAL RESERVES AND MINERAL RESOURCES Information concerning the properties and operations of New Gold has been prepared in accordance with Canadian standards under applicable Canadian securities laws, and may not be comparable to similar information for United States companies. The terms “Mineral Resource”, “Measured Mineral Resource”, “Indicated Mineral Resource” and “Inferred Mineral Resource” used in this presentation are Canadian mining terms as defined in the Canadian Institute of Mining, Metallurgy and Petroleum (“CIM”) Definition Standards for Mineral Resources and Mineral Reserves adopted by CIM Council on May 10, 2014 and incorporated by reference in National Instrument 43-101 (“NI 43-101”). While the terms “Mineral Resource”, “Measured Mineral Resource”, “Indicated Mineral Resource” and “Inferred Mineral Resource” are recognized and required by Canadian securities regulations, they are not defined terms under standards of the United States Securities and Exchange Commission. As such, certain information contained in this presentation concerning descriptions of mineralization and resources under Canadian standards is not comparable to similar information made public by United States companies subject to the reporting and disclosure requirements of the United States Securities and Exchange Commission. An “Inferred Mineral Resource” has a great amount of uncertainty as to its existence and as to its economic and legal feasibility. Under Canadian rules, estimates of inferred mineral resources may not form the basis of feasibility of pre-feasibility studies. It cannot be assumed that all or any part of an “Inferred Mineral Resource” will ever be upgraded to a higher confidence category. Readers are cautioned not to assume that all or any part of an “Inferred Mineral Resource” exists or is economically or legally mineable. Under United States standards, mineralization may not be classified as a “Reserve” unless the determination has been made that the mineralization could be economically and legally produced or extracted at the time the reserve estimation is made. Readers are cautioned not to assume that all or any part of the measured or indicated mineral resources will ever be converted into mineral reserves. In addition, the definitions of “Proven Mineral Reserves” and “Probable Mineral Reserves” under CIM standards differ in certain respects from the standards of the United States Securities and Exchange Commission. TECHNICAL INFORMATION The scientific and technical information in this presentation has been reviewed and approved by Mark A. Petersen, Vice President, Exploration of New Gold. Mr. Petersen is an AIPG Certified Professional Geologist and a “Qualified Person” under National Instrument 43-101. NON-GAAP MEASURES All cash costs and all-in sustaining cost estimates (excluding historical amounts) in this presentation assume the following commodity prices and exchange rates: Silver - $16.00 per ounce, Copper - $2.75 per pound, and CDN/USD - $1.25, AUD/USD - $1.25, MXN/USD - $15.00, unless otherwise stated. (1) ALL-IN SUSTAINING COSTS Consistent with guidance announced in 2013 by the World Gold Council, an association of various gold mining companies from around the world of which New Gold is a member, New Gold defines “all-in sustaining costs” per ounce as the sum of total cash costs, capital expenditures that are sustaining in nature, corporate general and administrative costs, capitalized and expensed exploration that is sustaining in nature and environmental reclamation costs, all divided by the ounces of gold sold to arrive at a per ounce figure. New Gold believes this non-GAAP financial measure provides further transparency into costs associated with producing gold and will assist analysts, investors and other stakeholders of the company in assessing the company’s operating performance, its ability to generate free cash flow from current operations and its overall value. This data is furnished to provide additional information and is a non-GAAP financial measure. All-in sustaining costs presented do not have a standardized meaning under IFRS and may not be comparable to similar measures presented by other mining companies. It should not be considered in isolation or as a substitute for measures of performance prepared in accordance with IFRS and is not necessarily indicative of cash flow from operations under IFRS or operating costs presented under IFRS. Further details regarding historical all-in sustaining costs and a reconciliation to the nearest IFRS measures are provided in the MD&A accompanying New Gold’s financial statements filed from time to time on www.sedar.com. (2) TOTAL CASH COSTS “Total cash costs” per ounce figures are non-GAAP measures which are calculated in accordance with a standard developed by The Gold Institute, a worldwide association of suppliers of gold and gold products that ceased operations in 2002. Adoption of the standard is voluntary and the cost measures presented may not be comparable to other similarly titled measures of other companies. New Gold reports total cash costs on a sales basis. The company believes that certain investors use this information to evaluate the company’s performance and ability to generate liquidity through operating cash flow to fund future capital expenditures and working capital needs. This measure, along with sales, is considered to be a key indicator of the company’s ability to generate operating earnings and cash flow from its mining operations. Total cash costs include mine site operating costs such as mining, processing and administration costs, royalties, production taxes, and realized gains and losses on fuel contracts, but are exclusive of amortization, reclamation, capital and exploration costs and net of by-product sales. Total cash costs are then divided by ounces of gold sold to arrive at a per ounce figure. Co-product cash costs remove the impact of other metal sales that are produced as a by-product of gold production and apportion the cash costs to each metal produced on a percentage of revenue basis, and subsequently divides the amount by the total ounces of gold or silver or pounds of copper sold, as the case may be, to arrive at per ounce or per pound figures. Unless otherwise indicated, all total cash cost information in this presentation is net of by-product sales. This data is furnished to provide additional information and is a non-GAAP financial measure. Total cash costs and co-product cash costs presented do not have a standardized meaning under IFRS and may not be comparable to similar measures presented by other mining companies. It should not be considered in isolation or as a substitute for measures of performance prepared in accordance with IFRS and is not necessarily indicative of cash flow from operations under IFRS or operating costs presented under GAAP. Further details regarding historical total cash costs and a reconciliation to the nearest IFRS measures are provided in the MD&A accompanying New Gold’s financial statements filed from time to time on www.sedar.com.

75

slide-76
SLIDE 76

Contact information

Investor Relations Hannes Portmann Vice President, Corporate Development 416-324-6014 hannes.portmann@newgold.com

76