SLIDE 1 QUALITY PLAN POWER TRANSFORMERS MANUFACTURING
CUSTOMER: SIDOR C.A. PROJECT: POWER TRANSFORMERS FOR R5 SUBSTATION ENLARGEMENT
SLIDE 2
Job Quality Assurance Plan
ABB Transformers Pereira
SLIDE 3 C U S T O M E R S
MARKETING & SALES ENGINEERING DISTRIBUTION TRANSFORMERS POWER TRANSFORMERS
LOGISTIC
SUPPORT PROCESSES*
SUPPLY MNGMNT. HUMAN MNGMNT. INFORMATION SYSTEMS INTEGRAL QUALITY MNGMNT. FINANCIAL CONTROL MAINTENANCE & GENERAL SERVICES
SUPPLIERS
C U S T O M E R S
SERVICE * Mutual Interaction COMMUNITY
STRATEGIC MANAGEMENT
TRANSFORMER TESTS & OIL ANALYSIS
SLIDE 4 Code: F01- MGIPTG001 PROCESS LEADER OBJECTIVE SUPPLIER INPUT SUB PARTICULAR ACTIVITIES DOCUMENT RESPONSIBLE OUTPUTS Customer To define and to update the scope of the System of Management To define and to update the Processes of the System of Management, its sequence and interaction To lead the definition of the Programs and Indicators of the System of Management To give support in the update of Aspects and Environmental Impacts and Dangers and Risks To define and to communicate practices for the Operational Environmental Control and of OHS for the processes, suppliers and contractors To identify and access to Legal Requisites and other acquired requisites To lead the planning of changes that affect the System of Management To identify and to plan the response to potential situations of accidents and emergencies, and to prepare and to mitigate the possible illnesses that are associated To carry out activities of verification of the operational controls defined at the environmental level and OHS To carry out the external management of the residues To take care of the minor injuries To support technically the Processes of Manufacture To carry out periodic tests to the procedures of preparation and response before emergencies To prepare and to execute Programs of calibration / verification (including software when necessary) To update and to communicate the Legal Requisites applicable to the activities, products and services carried out and given by the Organization To evaluate periodically the fulfillment of the Legal Requisites and others applicable, and to keep records of this evaluation To manage the Legal Fulfillment with the interested Parties To keep the program: School of the Quality To coordinate the activities of Continuous Improvement and QIT
Requisites of Mgt. System Contract with Certifier entity Reports of previous Audits Indicators of management Audits To plan and to carry out the Audits of the Mgt. System NEZCP026 NTC ISO 9001:2000 NTC ISO 14001:2004 NTC OHSAS 18001:2000 QIT Manager of PTQ Internal auditors Audited Persons Plans of Actions of Improvement Records Managerial report of Audits Certificates of Mgt. System General manager Certifier Entity Processes of Mgt. System Interested Parties QIT Coordinators of Evacuation NEZCP046 Manager of PTQ Assistants of PTQ Competent and Careful Personnel Minutes of the QIT Plans of Action Records of Continuous Improvement Quality School BA PTPR 1LAA000022 Updated Matrix of Legal Requisites Supports of Legal Fulfillment Records PT Division Interested parties Certifier Entity Customers CIDET PT Division PT Division Interested parties Auditors Certifier Entity Manager of PTQ Manager of PTH Records of Operational Control Quality records Record of Evaluation of Simulations Equipments and devices of measurement and monitoring calibrated / verified Records Equipped Classrooms Internal auditors Process of Improvement
Computing Equipments QIT/Managing Boards PTQ Manager (Representative of the Direction for Mgt. System) Equipped offices HUMAN RESOURCES
Brigade of Security Room of Metrology MANAGEMENT OF RESOURCES To plan and to implement the tools of the System of Integral Management of the PT Division, so that both the operation and the control of the Processes of the Mgt. System are effective.
Interested parties PT Division Interested parties Planning of the Mgt. System Activities of the Processes Operational Controls Practices of response before Emergencies Residues of the Processes Information of Security of Chemical Products Equipments of following up and measurement (It includes software when necessary)
Customers Operational control and Response before Emergencies Legal conformity Integral Quality Management Integral Quality Manager Scope of the Mgt. System Process map Program of Management Graphic of Central Control Matrix of Environmental Aspects Matrix of Dangers and Risks Matrix of Legal Requisites Matrix of Administration of Changes COABB PT Division Interested parties MGIPTG001 NTC ISO 9001:2000 NTC ISO 14001:2004 NTC OHSAS 18001:2000 NEZCP061 NEZCP045 NEZCP046 NEZCP060 Manager of PTQ QIT ITPTQ001 - 002 PAPTQ006 - 007 - 008 - 009 - 010 PAPTH002 - 003 PAZCC022 PAZCH015 - 016 NEZCP063 - 064 - 065 ITPTQ040 - 041 - 042 PAPTQ003 PAPTQ004 PAPTQ005 PAPTQ013 PAPTQ027 PAPTQ028 ITPTQ006 - 008 ITPTQ010 ITPTQ015 ITPTQ035 ITPTQ037 - 039 Manager of PTQ Assistants of PTQ Process managers Technician Laboratory of Oils Operators Suppliers Contractors Visitants Engineer Room of Tests Users of equipments / devices Users of Mgt. System Agenda QIT Activities of the Organization Changes to the New Processes
- r Modifications of the Requisites
Results of verifications of Operational Control Previous evaluations Communications of Interested Parties Information Technology Resources (Intranet, internet, databases: SSA, CCRP, Borwin, CRS) RESOURCES OF INFRASTRUCTURE Assistants of Integral Quality OHS committee Brigade Location Nursing station Room of conferences with audio-visual aids (video beam, VHS, TV and projector) Matrix SGI Wasted Chemical Prod. Chemical Prod. Management Tools Critical Com. Legal Reg. Measurement and Monitoring Enviromental Aspects Dangers and Risks Management Prog.
SLIDE 5 Code: F01- MGIPTG001 PROCESS LEADER OBJECTIVE SUPPLIER INPUT SUBP ACTIVITY DOCUMENTS RESPONSIBLE OUTPUT CLIENT To prepare a program of Engineering To study Technical Specifications To review or to perform Check List To do Order Clearing To prepare a Pre-design To do a Technical Offer To draw up electrical design To do a Structure in BaaN To carry out Cards of Manufacture To prepare information for tests To carry out a design of Active Part To carry out a design of assemble, connections y cubing. To carry out a design of isolations (only TrafoStar) To carry out Plans for approval (if it is needed by the client) To carry out external design To do a Structure in BaaN To review, to verify and to validate the Electrical and/or Mechanical Design To control changes of Electrical and/or Mechanical design Electrical Design Engineer Requests of Changes of Design MANAGEMENT OF RESOURCES Mechanical Design Engineer Computing Equipment (computers, printer and plotter) Information technology resources (Intranet, Internet, software of design, database BA) PTO ITPTE001 PAPTE001 PAPTE003 PTE PTM PTS BA PTM PTE BA PTPR Technical specifications of the Client Technical and Commercial offer Technical norms Technical instructions of BA ITPTE002 - ITPTE009 Design for Offers ITPTE001 ITPTE010 ITPTE011 Technical specifications of the Client Technical and Commercial offer Technical norms Technical instructions of BA Electrical Design Technical norms Technical specifications of the Client Price Database Technical instructions of BA Manager of Engineering Equipped offices HUMANS INFRASTRUCTURE PTM PTE BA PTPR Electrical Design Electrical Designers Electrical design for production PTO, PTQ PTD PTP Electrical and Mechanical Designers Engineering Manager of Engineering To define and to plan the activities that allow to obtain designs that meet the requisites agreed in the contract and to achieve their ratification and the later satisfaction of the clients, at the same time the costs of engineering and materials foreseen in the selling are met, and also the technical requisites of the product are met. Program of Engineering Records of Order Clearing PTO Manager of Engineering Electrical and Mechanical Designers Planning Record Meeting SUM Plan of Invoicing Technical specifications Mechanical design for production Plans of Manufacture Technical Support PTD PTP PTO Review and Control
PAPTE004 PAPTE002 Manager of Engineering Electrical and Mechanical Designers ITPTE002 - ITPTE009 Designers of Offers New Designs Cards of Manufacture Plans Electrical design Structure of Materials Data for Tests Technical Support PTD PTP PTO Mechanical Design Room for Tests Technical Offer PTM PTP PTD Mechanical Designers Matrix SGI Remainders Remainders Chemical Prod. Management Tools Critical Com. Legal Reg. Measurement and Monitoring Measurement and Monitoring Enviromental Asp. Dangers and Risks Management Prog.
SLIDE 6 Code: F01- MGIPTG001 PROCESS LEADER OBJECTIVE SUPPLIER INPUT
SUBP
PARTICULAR ACTIVITIES DOCUMENTS RESPONSIBLE OUTPUT CUSTOMER PTP BA PTPR PTQ PTE PTO Product in Process Criteria of Acceptance Sigma Cards Cards of Program of Manufacture Plans / designs General Schedule Macro planning Process control To inspect and to test the product in process PAPTP001, PAPTQ001, ITPTP016, Supervisor Control of Processes of PTP Quality records (Sigma Cards) Sub process of Room of Tests To prepare isolations To paper conductors To wind To dry and to press Windings To dry and to press Windings To separate plates by groups To prepare table for stacking To stack, press and put vertically the cores To strain or to apply Asecond To mount Windings in core To close top yoke To connect Active Part To prepare cubing To dry Active Part To tight again and to cube To mount accessories To prove preliminarily the Airtightness To try and to analyze the Dielectric Oil To do vacuum and to fill with oil To rest and To impregnate To place control wiring To Carry out electrical Tests To test control wiring To prepare protocols of tests To test airtightness, to dismantle external accessories, to do identification and marking, to coordinate their packaging To register consumptions in BaaN and to do entry to Warehouse Technician of Laboratory of Oils Operator of Cores and Active Part Chief of Room of Tests Operator Laboratory PTP Wiring Operator Operator of Connections Operator of Shipments Operator of Cubing and Final Assembly Assistant of Assembling Assistant of Materials Assembling Leader Operator of Oils Planner of Production Supervisor of Production INFRASTRUCTURE Manager of Production Plant of manufacture of Power transformers Equipped offices Sub process of Room of Tests PTS PTE Transformer ready for shipping Registration in BaaN PTO Readying and Operative Shipping ITPTP038 ITPTP045 Leader and Operators of Assembling and Shipping Released Transformer for Shipment Packaging Packing List Warehouse Standard and customized materials, approved, and minor raw materials Winding manufacture ITPTP004, ITPTP005, ITPTP006, ITPTP024, ITPTP025, ITPTP026, ITPTP036, ITPTP039, ITPTP043, ITPTP046 Power Transformers Production Manager To plan and to carry out the production of the Power transformers, under controlled conditions that allow the fulfillment of the requisites of the Product and the Organization Leader and Operators of Windings Block of Windings Sub process of Assembling and Connections PTS Sub processes of Cores, Windings and Warehouse Windings Core Clamps Switch Plans/Designs Active Part Assembly ITPTP026 ITPTP009 ITPTP044 Leader and Operators of Assembling Active part assembled and connected Sub process of cubing Core Manufacture ITPTP003 ITPTP008 Leader and Operators of Assembling Verticalized Core Sub process of Assembling and Connections Sub processes of Assemble and Connections and Warehouse Active connected part Tank Accessories Processed and proved oil Plans/Designs Tanking and Final Assembly ITPTP015, ITPTQ029, ITPTP037, ITPTP038, ITPTP040, ITPTP042 Leader and Operators of Assembling Transformer finished and ready for tests Sub process of Room of Tests PTP PTE Transformer for tests General information of Tests Final Test PAPTQ002, ITPTQ011, ITPTQ012, ITPTQ014, ITPTQ016 - ITPTQ022 ITPTQ032 Engineer of Room of Tests Transformer released by Room of Tests, Protocols of Tests, Minutes of Controlling, Reports of Feedback to the Design PTP, PTO, PTE Financial resources Operator Assembly Windings Paper Operator Teams of safety and personal protection Equipment for the handling of heavy loads Operator Windings Assistant Assembly Windings MANAGEMENT OF RESOURCES Leader of Windings Equipment of inspection, such as micrometers, gauges and others, related to the technical instructions Machinery and equipment of plant to manufacture the product in accordance with the provisions of the instructions of BA and the Production Manuals of LDT and TrafoStar Operator of Insulations Assistant of Windings Computing equipment Information technology resources (Intranet, Internet, databases, BaaN System)Recursos informáticos (Intranet, Internet, Bases de Datos, Sistema BaaN) Room of Tests for transformers of Potency and Laboratory of Oils HUMANS Matrix SGI Waste Chemical Prod. Managment Tools Critical Com. Critical Com. Legal Reg. Mesasurement and Monitoring Enviromental Asp. Dangers and Risks Managment Prog.
SLIDE 7 ABB
Internal Auditors
QHSE - BASC
QIT
Managers´ Team
Quality
Carlos Ossa
H & S
Samuel Zuluága
Test Processes
JCV – JM - HV
Environmental
Paula Mesa
SPT TR DTR TR Oil Analysis Safety Brigade Evacuation Coordinators OHS Advisor
Integral Quality Organization Chart
General Management
BASC
Quality School Instructors
QHSE Management
SLIDE 8 A little of history (Integral Quality milestones)
- 1990: ABB Group arrives to Pereira´s factory through a global acquisition of
Westinghouse T&D segment
- 1996: Quality Management System is certified with ISO 9001 by BVQi
- 1999: Environmental Management System is certified with ISO 14001 by BVQi
- 2002: Philip Crosby´s Quality Improvement Process is implemented
QIT: Quality Improvement Team is established with the local Top
Management
QS: Quality School program is launched to give all people trainin in
Quality issues, technical competence and to encourage their Quality Awareness
- 2003: Six Sigma tool is implemented for TrafoStar power transformers
- 2005: Occupational Health and Safety Management System is certified with
OHSAS 18001 and the 3 Management Systems are integrated in QHSE
- 2006: BASC Managemen System is certified by the WBO (Business Alliance
for Secure Commerce)
SLIDE 9 Last 10 years improvement profile and our VISION
2002
QIP
1
2005
ISO 9001 ISO 14001
1996 1999
OHSAS 18001 + SGI QHSE
2009
2 3 4 5 6 σ
σ τ τ
2006
BASC
World Class Manufacturer
SLIDE 10 We have a great VISION
In 2009 ABB Pereira will be a World Class
Manufacturing plant
Happy people doing well their work
General view of windings shop in Chonqing All employees celebration
SLIDE 11 Zero Failures Zero Impacts Zero Accidents TPT & TTPT reduction On Time Delivery Customer Satisfied More orders Best prices Greater EBIT Stability & Safe labol COPQ’s reduction Cash Flow A good present for Everybody!
The Integral Quality way
SLIDE 12
Our Integral Policy show us the way
SLIDE 13 QHSE and BASC Policy (Translation) Do well our work since first time to get Customer's Satisfaction by means of Quality Products and Quality Services delivered on time, producing the budgeted profitability.
To get this, our commitment is:
Promote people's Competence and Awareness as our greatest asset To rise the life's quality of our employees by means of the continuous
improvement in H&S issues
Reduce waste generation and natural resources consumption in our
processes
Improve continuously our Processes efficacy Prevent illegal practices in our processes (terrorism, illegal trade,
drugs traffic, etc.)
Fulfill all the legal requirements in our processes
SLIDE 14 ABB
Our Zero Defects Objectives
ZD does not mean that we will not have failures, it means that we will not be happy with any failure! Quality ISO 9001
100% OTD Zero Test Failures 100% Customer Satisfaction
H U A C A L T A N Q U E CONSERVADOR PROTECCION AISLADORES H U A C A L R A D I A D O R E S
OHSAS 18001
Zero Lost Day Incidents
Zero Oil Spilling
QHSE Objectives Zero COPQ
Zero Electrical Energy Waste
BASC
Zero contamination
Quality ISO 9001
100% OTD Zero Test Failures 100% Customer Satisfaction
H U A C A L T A N Q U E CONSERVADOR PROTECCION AISLADORES H U A C A L R A D I A D O R E S
Quality ISO 9001
100% OTD Zero Test Failures 100% Customer Satisfaction
H U A C A L T A N Q U E CONSERVADOR PROTECCION AISLADORES H U A C A L R A D I A D O R E S H U A C A L T A N Q U E CONSERVADOR PROTECCION AISLADORES H U A C A L R A D I A D O R E S
OHSAS 18001
Zero Lost Day Incidents
Zero Oil Spilling
QHSE Objectives Zero COPQ
Zero Electrical Energy Waste
BASC
Zero contamination
SLIDE 15 The Quality Strategy
- 1. Philip Crosby´s – QIT – Quality
Improvement Process:
Quality School Quality Improment Team Zero defects philosophy
- 2. Integration QHSE + BASC
Philip Crosby
SLIDE 16 Quality Improvement Process launching
since 2002
SLIDE 17 Quality School´s principle: “The Competence and Consciousness of our employees are our greatest assets”.
BA PPTR Mnger.
since 2002
Quality Improvement Process launching
SLIDE 18 since 2002
Quality School launching
Quality Class Room
SLIDE 19 QS: Every body talking same languaje: QS: Every body talking same languaje: Quality! Quality!
Quality Throughout Work Team (QTWT) Each Improvement Project 1000 USD Savings
Course for Blue collars Course for Blue collars (15 Hours in 6 weeks) (15 Hours in 6 weeks)
Each Improvement Project 1000 USD Savings
Quality Education
Quality Education System (QES) System (QES) Course for White collars Course for White collars (25 Hours in 10 weeks) (25 Hours in 10 weeks) Course for Managers Course for Managers – QIT QIT (12 Hours in one weekend) (12 Hours in one weekend) Course to get internal Quality Instructors Course to get internal Quality Instructors
since 2002
Quality School strucutre
SLIDE 20 EMC: General Manager Quality Manager Controller Logistic Manager Human Resource Manager Engineering Manager Production Manager Marketing Manager Supply Manager Order Handling Manager
Quality Improvement Team
since 2002
The QIT in 2002. Today it has 10 members and they meet each two weeks with the following agenda…
SLIDE 21 Basic Cyclic Agenda Quality Improvement Team
NCR Distribution Transformers Audit Reports Six Sigma & dpmo’s 5S and Housekeeping NCR Power Transformers Environmental Managment System – Follow up to QHSE Objectives Metalshop supplies Follow up OHSAS 18001 Training Program & Quality School Quality Action Plans on going Managment Systems´ Integration CCRP and Customer Satisfaction Balance Score Card Quality Performance Index Improvement Projects
4th Meeting 3th Meeting 2nd Meeting 1st Meeting
In each session at least three of this topics are reviewed
SLIDE 22 1. People develope a holisitic processes´ approach 2. One integral Policy easier to implement and follow 3. Less number of internal and external audits, we pass from 12 to 4 per year 4. One integral Manager´s review 5. Integral operational control for Environmental and OHS systems 6. One integral induction program for new employees 7. More efficient use of IS resources and leaner documentation 8. Less number of registers 9. Prevention of lawful nonconformity
- 10. One integral Manual book (it is an interactive document)
Advantages we have from the QHSE integration QHSE + BASC Integration
SLIDE 23 QHSE + BASC Certifications
ISO 9001 since 1996 ISO 14001 since 1999 OHSAS 18001 since 2005 BASC since 2006
SLIDE 24 BELI EFS
SYSTEM
ISO 9001, ISO 14001, OHSAS 18001, BASC, etc
PROCEDURES
MP, TI, Manuals, etc.
BEHAVI ORS VALUES
Traditional Focus World Class Focus
Certifies are not enough to be World Class
STRUCTURE
Resources
SLIDE 25 By Abraham Maslow (1908 – 1970)
QHSE Management evolution
SLIDE 26
The Integral Employee knows, wants and has will power!
SLIDE 27 June /08 Test Rooms accreditation acc. to ISO – IEC 17025 December /09 Iberoamerican Quality Management Award December /08 Columbian Quality Management Award December /08 Integrate QHSE + BASC + SR December /08 Implement Social Responsibility Management System
DATE DESCRIPTION
Next steps
SLIDE 28