qa qc program overview
play

QA/QC Program Overview November, 2015 Quality Roles on the Project - PowerPoint PPT Presentation

QA/QC Program Overview November, 2015 Quality Roles on the Project Construction Management Oversight (CMO-Turner) functions as the TJPAs eyes and ears. Construction Manager/General Contractor (CM/GC- WOJV) manages and directs the


  1. QA/QC Program Overview November, 2015

  2. Quality Roles on the Project • Construction Management Oversight (CMO-Turner) functions as the TJPA’s eyes and ears. • Construction Manager/General Contractor (CM/GC- WOJV) manages and directs the work. • Design Team sets Quality Standards during the design and specifications development. • Design team verifies standards through the submittal process and field observations. • Quality Control is the role of the CM/GC. • Quality Assurance is the role of the CMO including specialty inspection.

  3. Overview of the CMO Services • “Construction management • Key Activities: services to coordinate, – Quality Assurance including administer, monitor, inspect and daily and code compliance interface with the Transbay inspections and coordination. Transit Center design teams, the – Engineering oversight of RFI CM/GC, the Demolition Contractor and submittal process. and the TJPA…” – Change order and claims • “Administrative tasks…which management. include the documentation of – Pay application review and work progress, progress reports, recommendations. correspondence, record keeping, – Schedule analysis. payment verification and communications…” – Field supervision during all work shifts. • “Rapid emergency response to – Maintain a 24 hour hotline for the TJPA...provide 24-hour on-call neighbor issues. representation for on-site – emergencies.” Design/Assist verifications.

  4. Document Control Other Quality Assurance / Code General Project Oversight / 7% 3% Required Testing and Agency Coordination Inspection 9% 44% Community Outreach 3% Engineering Oversight 15% Field Oversight 19% Construction Management Oversight Breakdown (dollars)

  5. Quality Assurance – Prevent, Detect and Correct • Key Activities: • “Establish a quality assurance / quality control (QA/QC) plan and – Turner developed the QA Plan in implementing procedures…that accordance with Project meets requirements of the Program requirements, FTA requirements and Quality Management System, including compliance with the FTA’s Army Corp QMS best practices. – Quality Assurance and Quality Turner has updated the QA Plan Control Guidelines and the TJPA’s three times as work in the field has approved Quality Management changed during construction. System.” – QA Plan mandates observations, • “QA/QC plan and procedures shall inspections, corrective actions, provide for effective oversight of documentation and data collection. the CM/GC’s quality control plan…” – As part of the QA Plan, Turner has performed quality surveillances of the CM/GC and vital offsite surveillances at manufacturing facilities around the country .

  6. Quality Assurance – Prevent, Detect and Correct • Key Activities: • “Development of appropriate inspection guidelines and – Implemented Autodesk BIM360 checklists, independent assurance (originally called Vela) quality tracking and sampling test guidelines, and inspection request system. formats for daily inspection reports – In the last year, there have been 2,737 and inspection and test Inspection Requests (IRs) from the documentation requirements. Contractors (Nov. 2014 – October 2015). Include procedures for oversight Average of 57 IR’s per week, over 200 and implementation of the non- IR’s per month. All managed by Turner. conformance reporting and corrective action processes.” – To date, through daily observation, the • “Support for Program QA QA/QC team has identified, tracked and assisted in resolving over 1600 Field surveillance and audits of Condition Reports (“FCRs”) and over contractor, supplier and Contractor 140 Non Conformance Reports activities and products.” (“NCRs”). – Currently there are over 10,000 unique Inspection and Test records in the system.

  7. Quality Assurance – Prevent, Detect and Correct • “Provide code and quality • Key Activities : inspections, on a timely basis in – Local and National Building Codes, the conformance with the structural engineer and National Construction Documents…” organizations such as the American Welding Society (AWS) and American Institute of • “Provide specialty inspections Steel Construction (AISC) mandate code and independent testing inspection and test requirements for steel including…steel, concrete, fabrication. The same is true for concrete, soil compaction and other work activities. masonry, fireproofing coverage, – Turner has subcontracted with ISI to provide soil compaction, water code compliance and special testing and intrusion, and inspection. waterproofing…in conformance – In the case of structural steel, ISI provides Certified Welding Inspectors (CWI) onsite for with the Construction field welding and offsite at 15 locations Documents…” throughout the country. ISI has performed more than 2500 tests and inspections at a total of 16 offsite facilities to date.

  8. Quality Assurance – Special Inspections and Tests • • Concrete Structural Steel (Non- – Visual Inspection for Destructive Testing) reinforcing steel placement, – Visual Inspection. embedded item placement – Ultrasonic testing. and cast-in item placement. – Magnetic particle testing. – Slump testing. – Torque testing. – Air testing. – Decking and Nelson Stud – Temperature testing. welding inspection. – Shrinkage testing. – Pull testing. – Compression testing. • Soil Testing • Future Testing – Nuclear gauge testing – Fireproofing testing. (compaction). – Masonry / Grout testing. – Gradation testing.

  9. Quality Assurance – A Success Story • Issue: • Result: – During shop fabrication of – The applicable code along with the Inspector’s experience mandated the built-up park level further investigation of the issue. nodes, the ISI Inspector, – The Inspector’s diligence caught during Non Destructive this issue at the shop and resulted Testing (“NDT”), noted the in the rejection of the built-up presence of linear nodes. indications in the welds. – An independent 3 rd party welding consultant was brought in to determine the root cause of the issue and develop a revised procedure. – The built-up nodes were rebuilt using the new procedure, passing visual inspection and NDT.

  10. Quality Assurance – A Success Story • Result: • Issue: – In 2011, Turner, working with the TJPA and – Accurate and auditable other team members, identified the need documentation is a for a modern, easy to use documentation cornerstone of a system that would be accessible to all successful QA/QC project participants. – program. Turner is Vela System (later purchased by Autodesk and renamed BIM 360 Field) was selected charged with creating after significant research and meetings and maintaining this with providers of such systems. documentation. – Turner implemented the system Project wide and is responsible for both training and administration of the system. – BIM 360 Field documents / maintains all inspection requests, field conditions, non- conformance conditions, punchlists, quality checklists and, in the future, equipment and systems commissioning.

  11. • The Transbay Transit Center Construction Quality Control (CQC) Program is a blend of the FTA 15 Essential requirements of the FTA Elements QMS 2012 15 Essential USACOE Elements & the Army QM Corp of Engineers’ System Contractor Quality Management System. • The Program has been in place during the design Transbay Quality and construction process. Program • Updated to address design assist packages.

  12. QA/QC Working Together Design Trades WOJV Turner TJPA SMEs

  13. CQC Organization WOJV Trades Vendors & Consultant

  14. For each major activity in Construction, the CQC & QA teams follow a series of steps to ensure that requirements are set and met. Construction Design/Vision

  15. QA/QC Overview Architects & Engineers provide the design of the Project thus setting the requirements through: • Drawings • Specifications • Architectural Supplemental Instructions (ASI) • Sketches Record Plan Record Plan Check Do Check Do Act Act Quality Efforts in this ‘Plan’ phase are led by: Design Subject Matter Experts (SMEs)

  16. QA/QC Overview Architects & Engineers provide the design of the Project thus setting the requirements through: • Drawings • Specifications • Architectural Supplemental Instructions (ASI) • Sketches 17

  17. QA/QC Overview Architects & Engineers provide the design of the Project thus setting the requirements through: • Drawings • Specifications • Architectural Supplemental Instructions (ASI) • Sketches Record Record Plan Plan The CM/GC and Trades outline in more detail how the requirements will be met during construction through: Check Check Do Do • Submittals • RFIs • QC Plans • Logistic Plans • Schedules • Mockups Act Act • Reverse Scheduling Quality Efforts in this ‘Do’ phase are led by: Construction Manager / General Contractor & Trade Subcontractors

  18. QA/QC Overview Planning & Pre-Execution Activities 19

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend