Bus Rapid Transit Program Update Sound Transit Board 3/26/20 - - PowerPoint PPT Presentation

bus rapid transit program update
SMART_READER_LITE
LIVE PREVIEW

Bus Rapid Transit Program Update Sound Transit Board 3/26/20 - - PowerPoint PPT Presentation

Bus Rapid Transit Program Update Sound Transit Board 3/26/20 Agenda BRT program overview Project development status Program approach Implementation schedule 2020 look ahead 2 BRT Program overview Connecting the


slide-1
SLIDE 1

Bus Rapid Transit Program Update

Sound Transit Board

3/26/20

slide-2
SLIDE 2

2

Agenda

  • BRT program overview
  • Project development status
  • Program approach
  • Implementation schedule
  • 2020 look ahead
slide-3
SLIDE 3

BRT Program overview

slide-4
SLIDE 4

4

Connecting the region

LINK connections

I-405 BRT Redmond-Seattle-Lynnwood

Lynnwood City Center & Bellevue Downtown

Issaquah-Bellevue-South Kirkland

Bellevue Downtown

Everett-Seattle-West Seattle

Lynnwood City Center

Ballard-Tacoma

Tukwila International Boulevard Station

SR 522 BRT Redmond-Seattle-Lynnwood

Shoreline South/145th

Everett-Seattle-West Seattle

Shoreline South/145th

slide-5
SLIDE 5

5

What is Stride?

Fast, frequent and reliable bus rapid transit service

  • I-405: 10-minute peak,15-minute off-

peak headways

  • SR 522/NE 145th: 10-minute

headways

  • Up to 19 hours of service Monday

through Saturday

  • Up to 17 hours on Sunday
slide-6
SLIDE 6

6

BRT Program overview

  • 45-mile corridor
  • 24 BRT station pairs across 12 cities
  • 6 new/expanded parking facilities
  • One transit center
  • Connections to Link light rail in

Lynnwood, Shoreline, Bellevue and Tukwila

slide-7
SLIDE 7

7

Stride Program Elements

  • Transit speed, reliability and

access improvements

  • BRT stations (branding,

signage, shelter, amenities)

  • BRT fleet
  • Bus operations and

maintenance facility

  • Parking facilities
  • Rider information system
slide-8
SLIDE 8

Project Development

slide-9
SLIDE 9

9

Project Development

Environmental review and 10% design nearly complete,

  • ngoing outreach
  • Consistent with 2019 Board direction
  • Advancing to 30% design
  • Early outreach to potentially affected property owners

Agreements in place and in-progress

  • Define improvements and ensure predictable implementation
  • Establish terms for joint projects

Limited final design and construction underway

  • Bothell BAT lane segment and NE 44th in-line stop in north Renton
slide-10
SLIDE 10

Program Approach

slide-11
SLIDE 11

11

Program Approach

Aggressive project schedule requires overlap of phases:

  • WSDOT contracted for components of I-405 project development
  • Starting development of 30% design
  • Procuring resources:
  • Bus Base North Design-Build Project Management resource
  • General Engineering Consultant for final design and construction

management

Planning revenue service as lines are completed

  • New line of business
  • Defining requirements/standards
slide-12
SLIDE 12

Implementation Schedule

slide-13
SLIDE 13

13

System Expansion Implementation Plan Project timelines

’17 ’18 ’19 ’20 ’21 ’22 ’23 ‘24 ‘25 ‘26

I-405 BRT SR 522/NE 145th BRT

KEY

Planning (hatched lines indicate overlap in Planning and Design) Final Design Construction BRT Begins Operations

slide-14
SLIDE 14

14

Schedule

Bus Base North: 2023

  • Key challenges: Permitting and resolution of complex right of way

acquisition

I-405 South: 2024

  • Requires on-time performance of complex construction and

partnering with multiple cities and KCM

I-405 North: 2025

  • Opportunity for greatly improved travel time and service
  • Dependent on timely delivery of WSDOT Express Toll Lane project

and Brickyard in-line station

SR 522/NE 145th: To be Determined

  • BAT lanes not scheduled for completion until 2025
slide-15
SLIDE 15

2020 Look Ahead

slide-16
SLIDE 16

16

2020 Look ahead

2Q 2020

  • I-405 BRT Consultant contract

amendment for Preliminary Engineering

  • Bus Base North design build project

management contract

  • General Engineering Consultant

contract for BRT Program

  • NE 85th Construction agreement

with WSDOT

  • Partner agreements

3Q 2020

  • SR 522/NE 145th BRT project to

be built

  • I-405 BRT project to be built
  • Bus Base North project to be

built

  • Baseline Bus Base North
  • Advertise for Bus Base North

design-builder

4Q 2020

  • Baseline SR 522/NE 145th and

I-405 Projects

slide-17
SLIDE 17

Thank you.

soundtransit.org

Thank you.