WHITELEYS SHOPPING CENTRE COMMUNITY LIAISON GROUP PRESENTATION 01 4 th FEBRUARY 2018 PRESENTATION TOPICS Site entrance arrangements Works Complete and Upcoming Overview and Look ahead programme Faade retention scheme


slide-1
SLIDE 1

WHITELEYS SHOPPING CENTRE COMMUNITY LIAISON GROUP PRESENTATION 01 4th FEBRUARY 2018

slide-2
SLIDE 2

PRESENTATION TOPICS

  • Site entrance arrangements
  • Works – Complete and Upcoming
  • Overview and Look ahead programme
  • Façade retention scheme
  • Tower cranes
  • Hoarding, parking bay and bus lane

suspensions

  • Soft strip progress
  • Demolition
  • Contact information
slide-3
SLIDE 3

SITE ENTRANCE ARRANGEMENTS

  • Pedestrian entrance for construction staff

is via the rear Redan Place entrance

  • Pedestrian entrance for Whiteleys office staff

and art exhibition is from central Queensway security door

  • Vehicle access in to the basement is via Redan Place
slide-4
SLIDE 4

WORKS OVERVIEW

  • Completed works

‐ Scaffold and hoarding to Redan Place ‐ Phone box removal from Porchester Gardens ‐ Tree removal, Redan Place, Porchester Gardens and Queensway ‐ Queensway bus stop has been closed ‐ Queensway bus lane and footpath have been closed ‐ Minilith removal on Queensway (for reinstatement) ‐ Soft strip works to M&S

slide-5
SLIDE 5

WORKS OVERVIEW

  • Upcoming works

‐ Street light removal along Queensway from Thursday 6th Dec ‐ Road improvement works (humps) from Thursday 6th Dec ‐ Queensway central crossing removal from Thursday 6th Dec ‐ Footpath improvement works from W/C 10th Dec ‐ Scaffolding and hoarding to existing entrances ‐ Soft strip of vacant units ‐ New welfare set up ‐ Temporary service installation ‐ Structural investigations ‐ Ongoing asbestos surveys

slide-6
SLIDE 6

PROGRAMME OVERVIEW

slide-7
SLIDE 7

PROGRAMME LOOK AHEAD

slide-8
SLIDE 8

PROGRAMME LOOK AHEAD

slide-9
SLIDE 9

FAÇADE RETENTION SCHEME

  • Final designs being drawn up now
  • Steel fabrication due to start 17.12.18
  • Footpath substrate improvement works Dec/Jan 19
  • Steel frame erection due to start Mid February 19
  • Frame erection planned completion June 19
slide-10
SLIDE 10

TOWER CRANES

  • Two tower cranes are to be erected
  • TC1 (South) 23/24th February 19
  • TC2 (North) 9/10th March 19
  • TC dismantles Sept/Oct 19
slide-11
SLIDE 11

HOARDING AND ROAD WORKS

  • Hoarding has been erected along Redan Place
  • Hoarding to Queensway and Porchester Gardens to commence in Jan 19
  • Queensway bus stop is closed and the bus lane has been suspended.
  • Road improvement works (hump removal) are to start from Thursday 6th December for
  • approx. 3 weeks
  • Footpath improvement works to Redan Place to start next week
slide-12
SLIDE 12

ASBESTOS AND SOFT STRIP WORKS

  • Asbestos survey/investigations are underway ahead of the soft strip work
  • Currently no asbestos has been found
  • Soft strip works have started in the following vacant units

‐ Marks and Spencer ‐ GAP

  • New welfare preparation works have started on the GF of Queensway elevation
slide-13
SLIDE 13

NOISE DUST AND VIBRATION

  • Real time monitors installed before Christmas
  • Monitoring regime developed with independent specialist
  • Monitoring plan submitted and agreed with WCC
  • Alerts sent if any trigger levels are breached
  • Onsite testing of dust suppression equipment
slide-14
SLIDE 14

DEMOLITION

  • Demolition of the car park is due to start 07.01.19
  • Demolition of the car park to be complete mid April 19
  • Demolition of the car park basement slab March to end May 19
  • Demolition of the main shopping centre May – Nov 19
slide-15
SLIDE 15

COMMUNITY LIAISON

Liaison Group Meetings will be held every Month Newsletters will be sent out on a monthly basis and information notices on a ad-hoc basis Complaints Procedure: The contact telephone number of the Erith Site Manager and Erith Communications Team will be displayed around the site boundary and contained in newsletters and notices. If you have any queries, problems or complaints during the works, please contact the Community Liaison Manager Cherrie O’Kane or Project Manager Paul Millar Paul Millar (Erith Project Manager) Mobile – 07584 233922 Email - paul.millar@erith.com Cherrie O’Kane (Erith Community Liaison/Conduct Manager) Mobile - 07894 259321 Email - cherrie.o'kane@erith.com Erith Tel No: 0370 950 8800 Email - enquiries@erith.com for out of hours enquires

slide-16
SLIDE 16

NEXT LIAISON MEETING

The next liaison meeting will be on 29th January 2019 Location to be confirmed