Pulaski County Historic Courthouse BUILDING ASSESSMENT - OCTOBER 2019 Goals Identify architectural and structural stabilization action items Identify building systems in need of modernization Concept design to utilize the historic


slide-1
SLIDE 1

Pulaski County Historic Courthouse

BUILDING ASSESSMENT - OCTOBER 2019

slide-2
SLIDE 2

Goals

❖ Identify architectural and structural stabilization action items ❖ Identify building systems in need of modernization ❖ Concept design to utilize the historic courtroom and office space ❖ Concept design for new courtroom addition to the Justice Center and utilization of the Historic Courthouse for alternative functions ❖ Evaluate budget numbers for both concepts and how they relate to the last proposal ❖ From our last presentation we have introduced ideas from administration and reviewed the budgets with further contractor input.

slide-3
SLIDE 3

Architectural Features and Modifications

❖ Windows and Doors ❖ Louvered Vents in the Tower ❖ Sitework ❖ Security – Access point control

slide-4
SLIDE 4

Architectural Features and Modifications

slide-5
SLIDE 5

Site Plan

slide-6
SLIDE 6

Structural Stabilization

❖ Terne Metal Restoration ❖ Below grade waterproofing ❖ Roof gutter and downspout restoration ❖ Perimeter retaining wall ❖ Masonry tuckpointing and cleaning

slide-7
SLIDE 7

System Modernization

❖ HVAC – 4 pipe hydronic system with dedicated fan coil units in each office suite ❖ Plumbing – Upgrades for existing plumbing areas and additional bathroom locations ❖ Fire Protection – Required for modifications to the Courtroom ❖ Electrical – Replace all lighting and outlet locations to meet ADA requirements ❖ Telecommunications – provide cable raceways for current and future upgrades ❖ Electronic Safety and Security – Surveillance and card access upgrades recommended

slide-8
SLIDE 8

Option 1

Notes: ❖ Public and secure access points established and meet ADA requirements ❖ Renovations and upgrades to all of the office suites ❖ Utilization of corridor space for increased office space ❖ Addition of security checkpoint and security office ❖ Renovations and upgrades to the courtroom space – seating space: 70 ❖ Addition of ADA bathrooms and services for public and administrative use ❖ Renovate IT vault for Clerk’s Office Storage, and utilize alternative storage space for IT equipment ❖ Relocate Microfilm Department to renovated lower level office space – Previous Assessor Office ❖ Minor modifications to Judge’s desk

slide-9
SLIDE 9

Main Level Floor Plan – Option 1

slide-10
SLIDE 10
slide-11
SLIDE 11

Lower Level Floor Plan – Option 1

slide-12
SLIDE 12

Second Level Floor Plan – Option 1

slide-13
SLIDE 13

Detailed Courtroom Plan

slide-14
SLIDE 14

Option 2

Notes: ❖ Option 2 upgrades to the lower level and main level are represented in Option 1 ❖ Second Level courtroom proposed to be converted to commissioners / public meeting room ❖ Judges Office suite renovation proposed to be assignable office space ❖ Courtroom and Judges Office are proposed to move to a new 10,650 square foot addition to the Justice center ❖ Courtroom seating: 76 ❖ Increased Justice Center addition provides space for the courtroom and Clerk’s Office. The Judge’s office will move to the existing Probation and Prosecutor Suites. The Probation and Prosecutor will move to new office suites in the Justice Center Addition.

slide-15
SLIDE 15

Second Level Floor Plan – Option 2

slide-16
SLIDE 16

Justice Center Concept

slide-17
SLIDE 17

Justice Center Concept - 2A

slide-18
SLIDE 18

Justice Center Concept - 2B

slide-19
SLIDE 19

Justice Center addition – Option 2A
 First Level

slide-20
SLIDE 20

Justice Center addition – Option 2A
 Second Level

slide-21
SLIDE 21

Justice Center addition – Option 2B
 First Level

slide-22
SLIDE 22

Stabilization and Systems Modernization

Phase 1 Building stabilization and updates Projected Cost Structural Report

  • Basic repairs (100% tuckpointing & cleaning)

$439,000

  • Repairs to Terne Metal

$230,000

  • Below grade water proofing (entire perimeter)

$300,000

  • Perimeter wall restoration & drainage

$170,000 Mechanical - Electrical - Plumbing Report

  • HVAC upgrades for entire building

$805,000

  • Electrical & Lighting system upgrades

$410,000

  • Replace main plumbing supply and waste water

$59,900

  • Fire Protection

$120,000

  • Telecommunications upgrades

$187,000

  • Electronic Safety and Security video surveilance and card access

$67,000 Architectural Detail Repairs

  • Window Replacement

$525,000

  • Door Replacement

$40,000

  • Tower louvered vent restoration

$72,000

  • Modifications to sitework

$40,000

  • Soft Costs

$346,490 Total $3,811,390

slide-23
SLIDE 23

Option 1: Total Courthouse Renovations Budget

Base Price for Building Stabilization and Updates $3,811,390 Interior Office Renovation Total $862,490 Soft Costs Projected 10% $86,249 Furniture, Finishes & Equipment Allowance @15 / s.f. $120,000 Projected Interior Renovation Total $1,068,739 Total Project Budget to completely renovate the historic structure $4,880,129

slide-24
SLIDE 24

Option 2A: 6,500 S.F . Addition

Courtroom and Judge's Office Addition 6,500 s.f. addition Courtroom and Judge's Office Allowance @350 / s.f. $2,275,000 1,200 s.f. addition @ $350/s.f. secure pathway, and minor office renovation Allowance @60 / s.f. $72,000 Site work for Justice Center addtion Allowance $250,000 Soft Costs Projected 10% $259,700 Furniture, Finishes & Equipment Allowance @15 / s.f. $115,500 Justice Center Addtion Total $2,972,200

slide-25
SLIDE 25

Option 2A: Total Courthouse Renovations and Addition Budget

Base Price for Building Stabilization and Updates $3,811,390 Interior Renovation Total $697,570 Soft Costs Projected 10% $69,757 Furniture, Finishes & Equipment Allowance @15 / s.f. $100,000 Projected Interior Renovation Total $867,327 Judicial Center 2A Addition Cost $2,972,200 Total Project Budget for addtion and complete renovation of the historic structure $7,650,917

slide-26
SLIDE 26

Option 2B: 8,550 S.F . Addition

Courtroom, Judge's, and Clerk's Office Addition 6,500 s.f. office suite and courtroom addition Allowance @350 / s.f. $2,275,000 2,050 s.f. - Clerk's office and Vault additon Allowance @400 / s.f. $820,000 1,200 s.f. addition - secure pathway, and minor office renovation Allowance @60 / s.f. $72,000 Site work for Justice Center addtion Allowance $250,000 Soft Costs Projected 10% $341,700 Furniture, Finishes & Equipment Allowance @15 / s.f. $146,250 Justice Center Addtion Total $3,904,950

slide-27
SLIDE 27

Option 2B: Total Courthouse Renovations and Addition Budget

Base Price for Building Stabilization and Updates $3,811,390 Interior Renovation Total $697,570 Soft Costs Projected 10% $69,757 Furniture, Finishes & Equipment Allowance @15 / s.f. $100,000 Projected Interior Renovation Total $867,327 Judicial Center 2B Addition Cost $3,904,950 Total Project Budget for addtion and complete renovation of the historic structure $8,583,667

slide-28
SLIDE 28

2018 Justice Center Addition Budget

Office Suites Square Footage Breakdown – Revised to allow Probation and Prosecutor to remain in current location Courtroom , Jury , and secure access hall – 4,500 S.F . Judge’s Office – 1,800 S.F . Clerk, Recorder , and Microfilm Offices and Vault – 3,600 S.F . Auditor & T reasurer Offices and Vault – 3,600 S.F . Assessor office – 1,800 S.F . Surveyor office – 1,800 S.F . Commissioner Room – 1,200 S.F .

Proposed 2018 Addition - Revised 18,300 s.f. addition 2 levels Allowance @375 / s.f. $6,862,500 Site work for Justice Center addtion Allowance $250,000 Soft Costs for addition Projected 10% $711,250 Furniture, Finishes & Equipment Allowance @15 / s.f. $229,500 Courthouse Demolition Allowance $500,000 Parking Lot Allowance $117,000 New Memorial Space Allowance $60,000 Soft Costs for demolition / parking / memorial space Projected 5% $8,850 Total Project Budget $8,784,100

slide-29
SLIDE 29

Summary

Keep existing courtroom in renovated courthouse: $4,880,129 - 14,750 asf Option 2B - Renovate courthouse and move courtroom and Judge’s Office to Judicial Center: $7,650,917 - 19,950 asf Option 2B - Renovate courthouse and move courtroom, Clerk’s office and Judge’s Office to Judicial Center: $8,583,667 - 22,240 asf Demolish Historic Courthouse and add 18,300 S.F . to Judicial Center with secure vaults and secure circulation routes $8,784,100 - 14,640 asf