Public Meeting Public Meeting 2005 Storm Sewer Bond Issue Project - PowerPoint PPT Presentation

Public Meeting Public Meeting 2005 Storm Sewer Bond Issue Project 2005 Storm Sewer Bond Issue Project th & Fair to 28 th & Fair St. 24 th & Fair to 28 th & Fair St. 24 Introductions City of Lincoln : Kent Evans- Project


  1. Public Meeting Public Meeting 2005 Storm Sewer Bond Issue Project 2005 Storm Sewer Bond Issue Project th & Fair to 28 th & Fair St. 24 th & Fair to 28 th & Fair St. 24

  2. Introductions • City of Lincoln : • Kent Evans- Project Manager • John Callen- Associate Engineer • Olsson Associates • Eric Dove- Lead Engineer • Travis Figard- Associate Engineer • Lisa Behrns- Public Involvement Coordinator

  3. Agenda • Storm Drainage System • Identify Flood Prone Areas • Project Schedule • Questions

  4. Storm Drainage System

  5. Design Capacity • Gutter Flow & Pipe Flow • 5 year storm: 1.9” in 1 hour • Street Right of Way Flow • 100 year storm: 3.4” in 1 hour

  6. Low Points (Sumps) • Where will the 100 year storm go? • How deep will it get ? • Typically need higher pipe capacity.

  7. Pipe System & Sump Areas of Interest

  8. Flood Prone Structures

  9. Drainage Area to the Alley

  10. Proposed Improvements

  11. Schedule • Field Survey: Started • 60% Design: May 2006 • 90% Design: June 2006 • Public Meeting: June 2006 • Start of Construction: August 2006 • End of Construction: Spring 2007

  12. Questions & Observations Questions & Observations

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.