Public Information Meeting Vermont Route 100B Bridge 2 Replacement - - PowerPoint PPT Presentation

public information meeting
SMART_READER_LITE
LIVE PREVIEW

Public Information Meeting Vermont Route 100B Bridge 2 Replacement - - PowerPoint PPT Presentation

Public Information Meeting Vermont Route 100B Bridge 2 Replacement Moretown, VT August 5, 2019 Pres esen ented ed B By: Rob Young, PE Project Manager VTrans Fianna Barrows, PE Lead Design Engineer Vtrans Jennifer Zorn,


slide-1
SLIDE 1

Public Information Meeting

Vermont Route 100B Bridge 2 Replacement Moretown, VT

August 5, 2019

slide-2
SLIDE 2

Pres esen ented ed B By:

  • Rob Young, PE

Project Manager – VTrans

  • Fianna Barrows, PE

Lead Design Engineer – Vtrans

  • Jennifer Zorn, AICP

Public Information Consultant– McFarland Johnson

slide-3
SLIDE 3

Agend enda

  • Introductions
  • Existing Bridge Condition
  • Proposed Replacement Structure
  • Remaining Project Schedule
  • Proposed Detour Route
  • Questions and Comments
slide-4
SLIDE 4

Br Bridge Si e Site e – Ex Existing

slide-5
SLIDE 5

Ex Existing B g Bridge

  • Originally constructed in 1928
  • Bridge is structurally deficient
  • Less than desirable roadway width
  • Bridge Rating
  • Bridge Deck: 5 (Fair)
  • Bridge Superstructure: 5 (Fair)
  • Bridge Substructure: 5 (Fair)
  • Overall Sufficiency Rating: 63.6 (out of 100)
slide-6
SLIDE 6

Ex Existing B g Bridge D Deficiencies

Substandard Lane and Shoulder widths Existing: 10’/ 0’ ~ Minimum: 11’/ 4’

Currently 1 lane

slide-7
SLIDE 7

Ex Existing B g Bridge D Deficiencies

Heavy spalling in curbs, fascia's, bridge railing, and T-Beams

slide-8
SLIDE 8

Ex Existing B g Bridge D Deficiencies

Substructure Concrete Cracking, Spalling, and Loosing Connection with Ledge

slide-9
SLIDE 9

Existing Si Site D e Defici cienci cies es

Blocks used to Retain Roadway Approach Fill

Could Wash out in High Water

slide-10
SLIDE 10

Prop

  • posed B

ed Bridge

  • Concrete Deck on Steel Girders
  • Spread Footings on Ledge
  • Longer Span (92’ from 59’)
  • Increase Bridge Width, Lane and Shoulders
  • Safer Alignment
  • Construct Retaining Wall
slide-11
SLIDE 11

Proposed Bridge T e Typical Sec Section

slide-12
SLIDE 12

Prop

  • posed

ed Bridge

Increase Waterway Opening Increase Lane and Shoulder Width New Existing New Existing

slide-13
SLIDE 13

Proposed ed Br Bridge Al Alignmen ent Ch Chan ange

Red = Existing Yellow = Proposed

Increase radius of Approach Curves to Increase Safety

slide-14
SLIDE 14

Proposed Br Bridge e Retaining W Wall

slide-15
SLIDE 15

Method hods of

  • f Con

Construct ction

Combination of Accelerated Bridge Construction and Conventional Construction.

  • Overall Goals:
  • Implement Accelerated and Conventional Components Efficiently
  • Maximum Construction Duration of 60 days to Avoid Bus Detour
  • Accelerated Elements (where feasible)
  • Precast Footings, Deck Panels, and Approach Slab Elements
  • Rapid Setting Concrete
  • Conventional Components (due to site complexity)
  • Cast-in-place subfooting to ensure connection to bedrock
  • Cast-in-place deck over pour for smooth, safe ride
slide-16
SLIDE 16

Accel eler erated ed Com Component

Precast Approach Slabs

Joints filled with

Rapid Set Concrete

slide-17
SLIDE 17

Accel eler erated ed Com Component

Precast Deck Panels

slide-18
SLIDE 18

Accel eler erated ed Com Component

Precast Deck Panel Layout

slide-19
SLIDE 19

Accel eler erated ed/ Conven entional Compo ponen ent

Deck Over Pour

slide-20
SLIDE 20

Conven entional C Compo ponen ent

Cast in Place Subfooting to Bedrock

slide-21
SLIDE 21

Final Br Bridge W e Will L Look

  • ok Si

Similar T To:

  • :

Cast in Place Subfooting to Ledge

3-Rail Black with Curb Concrete Deck Steel Girders

slide-22
SLIDE 22

Projec ect Sc Sched edule

Project Advertised October 2019 Begin Construction Activities

  • April/May, 2020

Bridge Closure

  • Close: June 22, 2020
  • Open: August 21, 2020

Project Completion

  • September

2020 Special Schedule Details:

  • Allowed Bridge Closure

Duration – 60 Days

  • Financial Incentives and

Disincentives included in Contract to encourage early completion

slide-23
SLIDE 23

Detour

  • ur

Summary

A to B current: 7.9 Miles A to B detour: 11.5 Miles Added: 3.6 miles End to End 19.4 miles

A B

VT rt. 2

slide-24
SLIDE 24

Traffic ic C Control P l Plan

slide-25
SLIDE 25

Public O c Out utrea each ch

Public Information Consultant - Jennifer Zorn To Sign up for emails with project updates – send an email to jzorn@mjinc.com Jennifer’s Contact information Direct Phone #: (603) 931-3943 Email: jzorn@mjinc.com

slide-26
SLIDE 26

Ques uestions a and nd Com Comments?