ProtoDUNE-DP (NP02) status
Filippo Resnati (CERN)
- n behalf of the NP02 collaboration
DUNE Collaboration Call - 28th of June 2019
ProtoDUNE-DP (NP02) status Filippo Resnati (CERN) on behalf of the - - PowerPoint PPT Presentation
ProtoDUNE-DP (NP02) status Filippo Resnati (CERN) on behalf of the NP02 collaboration DUNE Collaboration Call - 28 th of June 2019 ProtoDUNE-DP Single 6x6x6 m 3 liquid argon active volume. Electrons drift upwards, they are extracted into the
DUNE Collaboration Call - 28th of June 2019
2
Single 6x6x6 m3 liquid argon active volume. Electrons drift upwards, they are extracted into the vapour phase where they are multiplied by the LEMs and readout with the anodes. Main components of the detector:
Filippo Resnati - DUNE Collaboration Call - 28th of June 2019
3
On the 8th of March 2019 TPC was mostly completed Closure of the TCO was the major installation work to be completed
Filippo Resnati - DUNE Collaboration Call - 28th of June 2019
4
Additional ~ two weeks of delay were announced mid of April.
Filippo Resnati - DUNE Collaboration Call - 28th of June 2019
5
End of March / beginning of April Installation of the VHV extender, connection to the field cage and installation of the feedthrough
Filippo Resnati - DUNE Collaboration Call - 28th of June 2019
6
Preparatory work started on the 8th of April:
Filippo Resnati - DUNE Collaboration Call - 28th of June 2019
7
Closure of the warm structure of the TCO on the 6th and 7th of May
Filippo Resnati - DUNE Collaboration Call - 28th of June 2019
8
On the 22nd of May, insulation and the corrugated membrane were completed Helium leak tests and global vacuum test successfully accomplished Dismounting of the dirty room and cleaning of the TCO wall
Filippo Resnati - DUNE Collaboration Call - 28th of June 2019
9
From the 27th of June till the 13th of July installation cabling and testing of:
https://www.youtube.com/watch?v=eHNSXwgfPQg Filippo Resnati - DUNE Collaboration Call - 28th of June 2019
10
np02-slow-control.web.cern.ch Filippo Resnati - DUNE Collaboration Call - 28th of June 2019
11
Wavelength-shifter on 30 PMTs was changed from evaporated TPB to PEN sheets. 6 PMTs were left with TPB. The operation took place in situ. Installation of the ground grid followed (11th and 12th of June). Ground grid composed of 4 3x3 m2 pieces above the PMTs and a frema along the periphery (last thing to be installed) Intense cleaning campaign of the accessible components of the detector and the walls and roof of the cryostat from the end of May till the closure of the man hole
Filippo Resnati - DUNE Collaboration Call - 28th of June 2019
12
13th of June: Removal of the last parts of the false floor, cleaning, removal of the scaffold, and finalisation of the ground grid.
Filippo Resnati - DUNE Collaboration Call - 28th of June 2019
13
Filippo Resnati - DUNE Collaboration Call - 28th of June 2019
13th of June: Removal of the last parts of the false floor, cleaning, removal of the scaffold, and finalisation of the ground grid.
Formal CERN approval to start the cryogenic operation after passing a series of tests:
feedthroughs.
weldings were tested at the completion of the cryostat).
secondary barrier tested during the cryostat construction)
gauges (comparison with the deformation model ongoing)
vibrational measurement (seismic, not needed for approval)
14
Filippo Resnati - DUNE Collaboration Call - 28th of June 2019
15
Pressure test on the night of the 13th of June
200 mbarg 100 mbarg 0 mbarg Filippo Resnati - DUNE Collaboration Call - 28th of June 2019
16
From the 14th of June the cryostat is being purged with pure and warm gas argon. In few days the O2 content was brought down to 2 ppm with the argon piston effect. Since then the argon is purified (oxygen and water) in closed loop. Water content is at the level of 350 ppm (expected to be larger than NP04). Installation of cryogenic moisture traps that are functional since today. If the water contamination is too large there is the risk of ice formation on cold surfaces while cooling down
Filippo Resnati - DUNE Collaboration Call - 28th of June 2019
17
Installation:
Tests:
Filippo Resnati - DUNE Collaboration Call - 28th of June 2019
18
0 uA 10 uA 0 uA 0.5 uA
0kV
In air moisture was driving the current drawn Filippo Resnati - DUNE Collaboration Call - 28th of June 2019
Cooling with sprayers starting from Monday 1st of July (if water content diminishes). First 3 trucks (3x 20 ton) expected on the 3rd, 4th and 5th of July. From the 8th of July 2x 20 ton/day during week days for abut 5 weeks. If no regeneration of the purification cartridge is needed during filling, cryostat will be full at the beginning of August. From NP04 experience: cryogenic instrumentation will be fundamental during filling.
19
Filippo Resnati - DUNE Collaboration Call - 28th of June 2019