project status
play

Project Status Time- 35.45% (464/1309) Earned- 48.28% - PowerPoint PPT Presentation

Project Status Time- 35.45% (464/1309) Earned- 48.28% ($27,975,596/$58,086,596) Estimated Completion: January 2016 Phase 1-MOT 82 Avenue Transal Park NW 25 Street Truck Lot N BP Station Traffic shifted to the south side of NW 25 Street and


  1. Project Status Time- 35.45% (464/1309) Earned- 48.28% ($27,975,596/$58,086,596) Estimated Completion: January 2016

  2. Phase 1-MOT 82 Avenue Transal Park NW 25 Street Truck Lot N BP Station Traffic shifted to the south side of NW 25 Street and work zone set up to the north.

  3. Phase 1- Major Operations • Culvert Construction • Drilled Shafts • Pile Driving • Foundation Construction • Miami-Dade Water and Sewer JPA • Intersection Improvements (NW 79,82 and 87 Avenues) • Roadway Widening

  4. Phase 1- Culvert Installation 2393 LF of 2870 LF (83.3%)

  5. Phase 1- Drilled Shafts • All five 96 inch drilled shafts completed • Required full SR 826 ramp closures over weekend (24 hrs/day) • Drilled shafts ranged in depth from 120 feet to 65 feet.

  6. Phase 1- Drilled Shaft

  7. Phase 1- Panel Wall Pile Driving Piles Driven- 259 of 269 (96.2%)

  8. Phase 1- Foundation Pile Driving Piles Driven- 85 out of 204 (41.6%)

  9. Phase 1 Upcoming Work • Culvert crossing NW 79 Avenue ‐ one northbound and one southbound lane in each direction (mid ‐ October 2013 through May 2014) • Bridge girders over 25 Street just east and west of Palmetto will require full weekend closures of NW 25 Street • Reconstruction of north side of NW 87 Avenue ‐ two lanes in each direction and one turn lane. (December 2013 ‐ May 2014) • Phase 2 ‐ May 2014 through March 2015

  10. Phase 2 Transal Park NW 25 Street Truck lot 82 Avenue BP Station N Traffic shifted to the north and work zone set to the south. Major operations include reconstruction of south side roadway, new drainage and installation of water and sewer mains.

  11. Contacts Oscar Gonzalez Nelson Perez Public Information Specialist Project Engineer 8290 NW 27 Street 8290 NW 27 Street Doral, Florida 33122 Doral, Florida 33122 Phone: (305) 463-7701 Phone: (305) 463-7701 Fax: (305) 463-7749 Fax: (305) 463-7749 Mobile: ( 786) 280-0983 Mobile: (305) 216-5112 Email: ogonzalez@mrgmiami.com Email: nperez@apcte.com www.fdotmiamidade.com

  12. www.fdotmiamidade.com QUESTIONS?

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend