Project Presentation Project Overview: Key Figures Location : - - PDF document

project presentation project overview key figures
SMART_READER_LITE
LIVE PREVIEW

Project Presentation Project Overview: Key Figures Location : - - PDF document

May 2010 Project Presentation Project Overview: Key Figures Location : Akhaltsikhe, Southern Georgia Mtkvari HPP project envisages a River : Mtkvari construction of a 46.4 MW hydro power plant in Akhaltsikhe, South Georgia Head : 100.0 m Water


slide-1
SLIDE 1

Project Presentation

May 2010

slide-2
SLIDE 2

Project Overview: Key Figures

Location: Akhaltsikhe, Southern Georgia River: Mtkvari Head: 100.0 m Water discharge: 55.0 m3/sec Number and type of units: 2; Francis Construction time: 3.5 years Potential installed capacity: 46.4 MW Annual power output: 253.0 GW/h Capacity load factor: 63.0 % Estimated construction costs: US$ 70.0-80.0 mln Estimated tariff range (kWh): US¢ 6.1 - 7.4 Estimated payback period: 6-7 years Expected life-span of the plant: 50 years

Mtkvari HPP project envisages a construction of a 46.4 MW hydro power plant in Akhaltsikhe, South Georgia The actual construction of Mtkvari HPP was launched in November 2009 The construction works are expected to last 3.5 years

2

slide-3
SLIDE 3

Project location

Mtkvari HPP is located in Southern Georgia… ….28 km away from the Turkish border

3

slide-4
SLIDE 4

Project location: site description

The headworks of the plant is located in the vicinity of the village Rustavi, Aspindza district, where Mtkvari river will be dammed and diverted into a 9.6 km long headrace tunnel to the powerhouse in village Sakuneti, Akhaltsikhe district, which will be housing two 23.2 MW power generating units PowerHouse area Headworks area Headrace tunnel (9.6 km)

4

slide-5
SLIDE 5

Project success elements

Sector

  • Georgia has the largest underutilized

hydro power generating potential in Europe, with only 30% of the total capacity exploited, situated next to Turkey with the 2nd largest electricity demand growth rate in the world at 8% p.a. for the past 20-25 years

  • There is a huge government support

for the development of the Georgian energy sector, visible through reforms and a consequent near-full liberalisation of tariffs as well as government-led large scale investments in the sector and related infrastructure, including the construction

  • f

a 500 kV transmission grid, connecting Georgia to Turkey, funded by the Georgian government along with KfW and EBRD

  • The new grid will allow Georgian

electricity exports not only to the neighbouring Turkey, but also to the rest of the continental Europe, after Turkey joins the European Network

  • f Transmission System Operators

for Electricity, due July 2010

Location

  • Mtkvari HPP probably has the best

location for the construction of HPP with ample water supply and the already-existent, well developed infrastructure

  • It is environmentally and socially

friendly project, requiring no relocation of people and imposing minimal damage to the landscape

  • The HPP is located close to the

Turkish border, the major potential customer for the produced electricity

  • The new 500 kV transmission grid,

which is currently under construction, passes 2 km away from the HPP site. The new line will export 1,050 MW electricity from Georgia to Turkey, and will be used by Mtkvari HPP, among others, as the main grid for electricity exports

  • It is notable that newly built HPPs in

Georgia are to have the right to export electricity firsthand, over all the other electricity sources

Team

  • The management team comprises

some

  • f

the most qualified professionals both in the energy and finance fields, with extensive experience in Georgian and Turkish energy sectors as well as in the financial hubs such as the city of London

  • The

engineers employed

  • n the

Mtkvari HPP project are the most experienced in Georgia, having worked

  • n

planning, design, construction and rehabilitation of some

  • f

the largest HPPs in Georgia, including the largest Enguri HPP (1,300 MW)

  • Companies employed on the project

are the leading engineering and project development companies in Georgia and Europe

5

slide-6
SLIDE 6

Project timeline

Several leading project development and engineering companies hired to conduct the preliminary studies and research works on Mtkvari HPP Georgian company GeoEngineering Ltd completed the topography of the surface map for Mtkvari HPP and proceeded with the Geological survey completing it in Q2 2009 Ukrainian company UkrHydroProject completed the technical project design of Mtkvari HPP Icelandic company Verkis completed a feasibility study on the project Turkish company ENCON completed the Environmental and Social Impact Assessment Ministry

  • f

Environment Protection and Natural Resources approved the Environmental and Social Impact Assessment President of Georgia M. Saakashvili and the Minister of Energy A. Khetaguri ceremonially unveiled the commencement

  • f

Mtkvari HPP construction The acquisition of lands, used as a power plant construction site, water intake and flooding zones, was completed Infrastructural works fully underway with most of the basic infrastructure already in place Tunnel drilling machine, DOSCO roadheader delivered and assembled on the site Headrace tunnel drilling works commence

Q3-Q4, 2008 Q1-Q2, 2009 Q4, 2009 Q3, 2009 Q3, 2009 Q4, 2009 Q4, 2009 Q4, 2009 Q1, 2010 Q2, 2010 Q2, 2010 Q4, 2009

Local authorities

  • f

Akhaltsikhe and Aspindza districts granted the construction license

6

slide-7
SLIDE 7

Studies conducted on the site

Topography Geology Hydrology Seismology

  • The site comprises in general a mountain range extending between the proposed upper and lower sections of the project
  • It is assumed that the stability of the slopes adjoining the proposed project structures is adequate
  • The upper project section where the headrace works, dams and power intake with appurtenances will be located seems

to favour the construction of a rockfill dam with a central impervious core

  • The detailed study and research was performed on the site, with several wells drilled down the surfaces where the

tunnel and powerhouse constructions will take place

  • Sample materials from the site were taken into the laboratory for the detailed analysis
  • There was a detailed geological and hydrological research performed on the 9.6 km headrace tunnel area with 7 wells

drilled into the surface, with the total length of 973 m

  • It was determined that the geology of the area in general is considered favourable for the construction of the structures

relevant to the hydropower project

  • A tunnel drilling machine, roadheader, was chosen as an optimal method of excavating the tunnel
  • Georgia´s climate is affected by subtropical influences from the west and Mediterranean influences from the east
  • The midwinter average temperature is 5 °C and the midsummer average is 22 °C
  • The average discharge rate of Mtkvari river is 55 m3/s
  • A storage reservoir upstream of the project in the main river or some of its tributary rivers would be very valuable and

increase the energy production during the high discharge season of river Mtkvari

  • The project is located in the central part of South Georgia. It comprises seismically active zones of the central part of

the Ajara-Trialeti infolded-faulted mountain belt, which has a high seismic potential, and the western part of the seismically very active Javakheti Upland

  • It is assumed that the European Earthquake Standard, Eurocode 8 (FS ENV 1998:1994) can be applied as guidance for

the definition of a design spectrum for the project

7

slide-8
SLIDE 8

Project conceptual design

The intake pond will be formed by a dam across the river course It will be some 3 km long with the maximum width of about 0.6 km The usable water volume will be 900 000 m3 The pond can only be used for limited regulation during a day Mtkvari river is diverted to execute the headworks (main dam, power intake) in dry Diversion will be achieved by excavating a diversion canal The diversion canal will be about 80 m long and 12 m wide The canal will be permanently closed at the end of construction The main dam will be about 300 m long with a maximum height of 32 m Dam will be located slightly downstream of the tunnel intake It will have an earth-rockfill structure with an impervious core Cofferdam will be constructed from rockfill and may apply other readily available fill Loose overburden will be set aside to be used in cofferdam Gravel fill & finer grained fill will be placed on the upstream slope to reduce leakage Lastly cofferdam will be raised up to the designed level Spillway will be a 120 m long ogee formed concrete structure It will be extending between the diversion canal and the main dam The water head at the spillway will normally be limited 8

Intake pond Diversion canal Main dam Cofferdam Spillway

Headworks

slide-9
SLIDE 9

Project conceptual design

9

Headrace tunnel Electromechanical equipment

Electromechanical equipment will include 2 Francis type Turbines, 23.2 MW each The turbine manufacturer will also provide for governor and shut-off valves, cooling system, sump pump system, generators and excitation systems, generator terminal equipment, power transformers, high voltage substation equipment, station power supply systems Electromechanical equipment will also include the control-and protection systems, which will be installed in the powerhouse

  • A 9.6 km headrace tunnel will be excavated with a DOSCO roadheader
  • The Mtkvari river will be dammed upstream village Rustavi and diverted into a headrace tunnel
  • At the downstream end of the headrace tunnel, water will enter into the powerhouse
  • The powerhouse will be equipped with two 23.2 MW power generating units
slide-10
SLIDE 10

Construction works - roads

The inner roads on the site, as well as around it have been put in place

10

slide-11
SLIDE 11

Construction works – workers’ lodgings

11

The company has completed the construction of workers’ dwellings and a canteen

slide-12
SLIDE 12

Construction works – administrative building

12

The administrative building for the project engineers has been set up

slide-13
SLIDE 13

Construction works - warehouses

13

One warehouse has already been constructed and another one is currently being built to serve as a storage area for Mtkvari HPP construction materials

slide-14
SLIDE 14

Construction works – water wells

14

Water wells have been drilled in 3 different places on the site, which will supply the water for workers' lodgings, the canteen, the tunnel drilling machine (DOSCO roadheader) and the concrete factory

slide-15
SLIDE 15

Construction works – transmission line

15

A 10 kV transmission line has been built, connecting the site directly to the grid

slide-16
SLIDE 16

Construction works – concrete factory

16

A concrete factory has been set up on the construction site to provide concrete for the headrace tunnel, the bridge and other building works

slide-17
SLIDE 17

Construction works – spillway drain

17

The spillway drain has been put in place near the headrace tunnel

slide-18
SLIDE 18

Construction works – DOSCO roadheader

18

The tunnel drilling machine, DOSCO roadheader, is fully assembled and ready to start the drilling works

slide-19
SLIDE 19

Construction works – tunnel portal

19

The portal of a 9.6 km headrace tunnel construction has been built and the concrete platform has been laid in front of the tunnel portal

slide-20
SLIDE 20

Construction works – bridge

20

The construction of a bridge on the Mtkvari river in underway, which will allow an easy access to the site from the main highway

slide-21
SLIDE 21

Appendix: Caucasus Energy & Infrastructure

Caucasus Energy & Infrastructure is a joint stock company set up in November 2007 under the Georgian legislation The company completed a database of technical and economic parameters of potential greenfield HPP projects in Georgia and shortlisted 26 most attractive projects for future potential construction, with the total required investment of approximately 500 mln Euros Of these projects, Mtkvari HPP presented the most attractive

  • pportunity

and CEI proceeded with its development, obtaining the license for the construction and gaining the required initial funding After the competitive bidding process CEI obtained a license for the construction, building and operation of a 46.4 MW Mtkvari hydro power plant in Southern Georgia In January 2009, CEI set up a special purpose vehicle Mtkvari HPP LLC and allocated capital equivalent of US$ 15 million for the implementation of Mtkvari HPP project The construction of Mtkvari hydro power plant began in November 2009 and is expected to last 3.5 years The HPP construction works are going according to the timetable and it is expected that the Mtkvari HPP will become fully operational by 2014 CEI is currently working on signing the Power Purchase Agreements with several Georgian and Turkish electricity

  • companies. At the same time the company is working with

several IFIs and strategic partners on raising debt and possibly additional equity financing in order to obtain full funding for Mtkvari HPP

Mtkvari HPP project is fully owned and developed by JSC Caucasus Energy & Infrastructure

21

slide-22
SLIDE 22

Appendix: CEI shareholder structure

22 CEI’s shares are traded on the Georgian stock exchange since 2008, under the ticker NRGY The free float is approximately 84% CEI launched a GDR program with BNY Mellon in March 2008, with one GDR representing 10 ordinary shares The company represents a sole investable vehicle

  • ffering

investors a broad exposure to the energy and infrastructure segments

  • f

the economy in Transcaucasia

slide-23
SLIDE 23

Appendix: CEI management

Archil Mamatelashvili (Chief Executive Officer)

Archil Mamatelashvili joined the Company in the capacity of Chief Executive Officer in October 2007. Prior to joining CEI, Mr. Mamatelashvili served as the Country Manager for Energo Pro S.A. in Istanbul, Turkey (April 2007 – October 2007) and as a Deputy Minister of Energy of Georgia (March 2005 – April 2007). Mr. Mamatelashvili holds an Undergraduate degree in Economics from Tbilisi State university, and a joint international MBA degree from Weatherhead School of Management of Case Western Reserve University.

Irakli Bezhuashvili (Chief Financial Officer)

Irakli Bezhuashvili joined CEI in the capacity of Chief Financial Officer in April 2008. Prior to joining CEI, Mr. Bezhuashvili served as a Senior Consultant at PricewaterhouseCoopers as well as an Audit Manager at UBC International Ltd. He has also

  • ccupied the post of Director at Georgian Branch of Eilamed Raj BV. Irakli Bezhuashvili obtained his Bachelor’s degree in

Municipal Engineering and Economy from Technical University of Georgia. Mr. Bezhuashvili is an accredited member of the Association of Certified Chartered Accountants (ACCA).

Bidzina Bejuashvili (Executive Chairman)

Bidzina Bejuashvili served first as a Chairman of the Supervisory Board of CEI and consequently as an Executive Chairman of CEI since November 2007. Mr. Bejuashvili also serves as the Chief Executive Officer of Abbey Asset Management. Prior to joining CEI and Abbey Asset Management, Mr. Bejuashvili served as a Vice-President at the leading global investment banking firm JPMorgan Chase, London, and was responsible for equity research coverage of the oil & gas sector in Russia, CEE, Middle East and Latin America. Prior to joining JPMorgan Chase in October 2005, Mr. Bejuashvili served in similar capacities at Italian Unicredit (2003-2005) and RZB Austria, London (2000-2003). Mr. Bejuashvili has twelve years of professional experience in investment banking, and holds a dual British and Georgian citizenship. Mr. Bejuashvili holds an Undergraduate degree from Moscow State University, Dept. of Applied Mathematics and Cybernetics and a Masters degree in Economics from Boston University.

23

slide-24
SLIDE 24

Appendix: Mtkvari HPP team

Simon Bakhturidze – Head Engineer

Simon Bakhturidze serves as a head engineer at the Mtkvari HPP LLC. Prior to joining Mtkvari HPP Mr. Bakhturidze served as a head of hydro-technical department at the Georgian Energy Generation, where he was responsible for investigation, monitoring and planning of reconstruction and maintenance works of Georgian HPPs. Mr. Bakhturidze has extensive experience in the Georgian hydro energy field and has worked on such projects as Enguri HPP rehabilitation (the biggest hydro power plant in Georgia), where he was a consultant to the chairman of the board of directors on technical issues (2005-2006). At the same time

  • Mr. Bakhturidze served as an invited expert for the USAID project that envisaged construction of Khudori HPP and

Namakhvani HPP. Mr. Bakhturidze has also served as a chief specialist at the Ministry of Energy of Georgia, on the research of new technologies and implementation of new methods into the Georgian energy sector. Mr Bakhturidze holds diplomas from Georgian State University, from the faculty of Radio-Physics and Georgian Polytechnic University in mechanical engineering.

David Kviriasvili – Technical Engineer

David Kviriashvili serves as a Technical engineer at Mtkvari HPP LLC. Prior to joining Mtkvari HPP Mr.Kviriasvili served as an electrical engineer at Energo Pro Georgia at the commercial department in 2005-2008 and as an engineer at the Kakheti Energy Company in 2002-2005. Mr. Kviriasvili holds a Diploma from the Georgian Agrarian University from the faculty of electrification.

Moveli Chaava – Engineer

Moveli Chaava works at Mtkvari HPP LLC as an engineer since 2009. Prior to joining Mtkvari HPP Mr. Chaava worked as a director at the Enguri underground buildings’ construction department (1980-2009). He has also worked as a chief engineer and afterwards as a deputy head of the Enguri N5 power node (1966-1978). Mr. Chaava is one of the most experienced engineers in the hydro power sector in Georgia and has worked on various HPP sites during their construction, reconstruction and operational periods.

Vasil Japaridze – Engineer

Vasil Japaridze serves as an engineer at the Mtkvari HPP LLC. Prior to joining Mtkvari HPP, Mr. Japaride worked on the Rioni HPP rehabilitation project in 2008-2009. In 2000-2008 Mr. Japaridze worked on planning and construction of Zarmagi HPP in

  • Osetia. In 1986-2000 Mr. Japaridze was employed at Sakenergo where he worked on planning, organization and refurbishment

works of different HPPs in Georgia as well as collection, control and analysis of the hydrological data.

24

slide-25
SLIDE 25

Contacts & important notice

25

This material is for information purposes only and does not constitute an offer to sell, nor a solicitation of an offer to buy shares in Mtkvari HPP LLC or JSC Caucasus Energy & Infrastructure in any jurisdiction to any person to whom it is unlawful to make such an offer or sale. This presentation contains statements that constitute “forward-looking statements”, including, but not limited to, statements relating to the implementation of strategic initiatives and other statements relating to our business development and financial performance. While these forward-looking statements represent our judgments and future expectations concerning the development of our business, a number of risks, uncertainties and other factors could cause actual developments and results to differ materially from our expectations. These factors include, but are not limited to, (1) general market, macroeconomic, governmental, legislative and regulatory trends, (2) movements in local and international currency exchange rates, interest rates and securities markets, (3) competitive pressures, (4) technological developments, (5) management changes and changes to our group structure and (6) other key factors that we have indicated could adversely affect our business and financial performance, which are in our past and future filings and reports, including those filed with the NSCG. We are under no obligation (and expressly disclaim any such obligations) to update or alter our forward-looking statements whether as a result of new information, future events, or otherwise.

For further information please contact: Bidzina Bejuashvili, Executive Chairman bbejuashvili@cei.ge +995 95 227 997 Archil Mamatelashvili, CEO amamatelashvili@cei.ge +995 99 159 573

Disclaimer