Project Bank Accounts April 2019 Agenda What are PBAs Tender - - PowerPoint PPT Presentation

project bank accounts
SMART_READER_LITE
LIVE PREVIEW

Project Bank Accounts April 2019 Agenda What are PBAs Tender - - PowerPoint PPT Presentation

Project Bank Accounts April 2019 Agenda What are PBAs Tender process Contract award Payment process Other information Project Bank Accounts An overview A PBA is A project specific bank account set up by the


slide-1
SLIDE 1

Project Bank Accounts

April 2019

slide-2
SLIDE 2

Agenda

  • What are PBAs
  • Tender process
  • Contract award
  • Payment process
  • Other information
slide-3
SLIDE 3

Project Bank Accounts

An overview

slide-4
SLIDE 4

A PBA is…

  • A project specific bank account set up by the

head contractor.

  • An account operated consistent with the trust

agreement.

  • A step in the payment process, not a pre-funded

bank account.

slide-5
SLIDE 5

PBAs can…

  • Speed up the payment process for the next tier

in the supply chain

  • Provide a degree of insolvency protection
  • Increase transparency and accountability in the

payment process.

slide-6
SLIDE 6

PBAs do not…

  • Alter the contractual rights and responsibilities of

contractors to:

− Select subcontractors and manage their performance − Retain retentions from subcontractors (which are held in the trust account) − Withhold payment when obligations are not satisfied − Seek adjudication or commence legal action when in dispute (also applies to subcontractors)

slide-7
SLIDE 7

About PBAs

PBA

General Sub-Account Retention Sub-Account Receives and distributes funds Holds subcontractor retention money as required

slide-8
SLIDE 8

About PBAs

  • One PBA per contract
  • General account must have a zero balance

at close of business

  • Must not have an overdraft facility
  • Fees, charges and accrued interest must

be directed to a non-PBA account.

PBA

General Sub-Account Retention Sub-Account

slide-9
SLIDE 9

BMW Payment Process – step by step

Subcontractor #1 Subcontractor #2 Subcontractor #3 Subcontractor #4 Supplier #1

Head Contractor

Super’s Rep

BMW

BANK (PBA provider)

General Sub-Account Retention Sub-Account

Opt-In Supplier #2

slide-10
SLIDE 10
  • 1. Subcontractors Claim Payment from Head Contractor

Subcontractor #1 Subcontractor #2 Subcontractor #3 Subcontractor #4 Supplier #1

Head Contractor

Super’s Rep

BMW

BANK (PBA provider)

General Sub-Account Retention Sub-Account

Opt-In Supplier #2

slide-11
SLIDE 11
  • 2. Head Contractor Submits the Payment Claim to the

Superintendent’s Representative

Subcontractor #1 Subcontractor #2 Subcontractor #3 Subcontractor #4 Supplier #1

Head Contractor

Super’s Rep

BMW

BANK (PBA provider)

General Sub-Account Retention Sub-Account

Opt-In Supplier #2

slide-12
SLIDE 12
  • 3. Superintendent’s Representative Assesses Claim and Issues

Payment Certificate to Head Contractor and BMW

Subcontractor #1 Subcontractor #2 Subcontractor #3 Subcontractor #4 Supplier #1

Head Contractor

Super’s Rep

BMW

BANK (PBA provider)

General Sub-Account Retention Sub-Account

Opt-In Supplier #2

slide-13
SLIDE 13
  • 4. Head Contractor submits payment instruction,

Statutory Declaration and Payment Report to BMW

Subcontractor #1 Subcontractor #2 Subcontractor #3 Subcontractor #4 Supplier #1

Head Contractor

Super’s Rep

BMW

BANK (PBA provider)

General Sub-Account Retention Sub-Account

Opt-In Supplier #2

slide-14
SLIDE 14
  • 5. BMW Deposits Payment into General Project Bank Account

Subcontractor #1 Subcontractor #2 Subcontractor #3 Subcontractor #4 Supplier #1

Head Contractor

Super’s Rep

BMW

BANK (PBA provider)

General Sub-Account Retention Sub-Account

Opt-In Supplier #2

slide-15
SLIDE 15
  • 6. Bank (simultaneously) Pays Head Contractor, Subcontractors,

and Retention Account as per payment instruction

Subcontractor #1 Subcontractor #2 Subcontractor #3 Subcontractor #4 Supplier #1

Head Contractor

Super’s Rep

BMW

BANK (PBA provider)

General Sub-Account Retention Sub-Account

Opt-In Supplier #2

slide-16
SLIDE 16

Commonwealth Bank of Australia

  • PBA structure should not affect:

− General security agreement − Charge over receivables − Floating charge

  • Structure does not impact security over funds due to

the contractor

  • Speak with your financial institution to discuss

potential impact on management working capital.

slide-17
SLIDE 17

Project Bank Accounts

Tender process

slide-18
SLIDE 18

PBAs apply…

  • Construction contracts where the contract value

exceeds $1.5 million (inc. GST)

  • Principal may elect to apply a PBA to contracts
  • utside this price range
  • Subcontractors are being used on the contract.
slide-19
SLIDE 19

PBA tender documentation

PBA contract

BMW PBA preliminaries PBA contract amendments PBA Pack:

PBA Trust Deed PBA Agreement Deed of Release or Priority Deed

slide-20
SLIDE 20

The PBA Pack

  • PBA Trust Deed

− Establishes the terms of the trust − Describes how the trust will operate

  • PBA Agreement

− Outlines duties and obligations of the bank

slide-21
SLIDE 21

The PBA Pack

  • Deed of Release

− Creditors agree to release the account and all money in the account from any security interests they hold

  • Priority Deed

− Creditors agree that beneficiaries to the PBA trust have priority should an insolvency event occur

slide-22
SLIDE 22

Tender Process – Contractors requirements

  • Tenders must include the costs of administering

PBAs where the submitted price is more than $1.5 million

− If the tendered price is less than $1.5 million, no need to build in these costs

  • Must inform subcontractors that the contract will

use a PBA

slide-23
SLIDE 23

Project Bank Accounts

Contract Award

slide-24
SLIDE 24

How a PBA is set up

slide-25
SLIDE 25

Contract award

  • The contractor will be provided with the following

documents at contract award:

− Electronic copy of the PBA pack − Bank information pack − PBA Guideline for Contractors

slide-26
SLIDE 26

PBA establishment

  • Account creation must start immediately
  • Subcontractor contracts will need to be updated to include

PBAs

  • Completed documents should be provided to authorised

signatories for signing by week 3.

  • BMW will be the last to sign and date all documents
  • Contractor should provide subcontractors with a copy of the

PBA Trust Deed.

slide-27
SLIDE 27

Activating the accounts

  • A $1

test payment must be made to the contractor within 10 business days of the Trust Deed being executed.

  • The test payment:

− Establishes the trust − Tests the payment process

slide-28
SLIDE 28

Test payment process

Bank disburses funds as per the payment instruction Finance makes payment into the account on the date for payment listed on the payment instructions Project manager checks the payment instruction to make sure the details are correct Contractor creates payment instruction in CommBiz for $1

slide-29
SLIDE 29

Project Bank Accounts

Payment Process

slide-30
SLIDE 30

Finance PBA progress payments

Contractor submits payment claim SR issues payment certificate BMW assesses monthly payment docs BMW deposits funds to general sub- account Bank disburses funds to contractor, joined subbies and retention account Payment Instruction Payment Report Statutory Declaration

slide-31
SLIDE 31

Progress Payment Instructions (PPI)

  • Instructs the bank how and when to disburse

funds

  • Total amount to be paid must equal the amount

certified

  • Can submit:

− a single instruction for all payments OR − up to three instructions – one for each payment type

slide-32
SLIDE 32

PBA Payment Report

  • Explains why an amount that was certified to be

paid is not reflected in the payment instruction.

  • Details include:

− Amounts paid outside the monthly payment process − Total paid in retention to date − Disputes − Rights set off − Amounts the subcontractor failed to claim

slide-33
SLIDE 33

PBA Statutory Declaration (subcontractors)

  • Along with the PPI and the payment report, the

contractor must supply a declaration that as at the date of the PPI:

− the PPI is true and accurate − The contractor has no outstanding liabilities − There have been no changes to existing or new security interests − The Payment Report is accurate.

slide-34
SLIDE 34

The monthly payment process - timeframes

DAY 28 DAY 14 DAY 19 DAY 23

Within 14 calendar days SR certifies payment Within 19 calendar days Contractor submits payment documents & advises Subcontractors Within 28 calendar days Finance reviews and pays Payment claim received

DAY 0

slide-35
SLIDE 35

Other payments

  • Payments may occur through the PBA but
  • utside the monthly payment cycle:

− Payment to subcontractors − Payment into the retention sub-account − Release of subcontractor retention

slide-36
SLIDE 36

Payment Instruction

Example

slide-37
SLIDE 37

17

41

slide-38
SLIDE 38

For more information on PBAs, check

  • ut our videos available at

www.finance.wa.gov.au/cms/pbavideos/