Contractors Seminar Asset Protection and Credit Control Stephen - - PowerPoint PPT Presentation

contractor s seminar asset protection and credit control
SMART_READER_LITE
LIVE PREVIEW

Contractors Seminar Asset Protection and Credit Control Stephen - - PowerPoint PPT Presentation

Contractors Seminar Asset Protection and Credit Control Stephen Byrne, Director 15 December 2011 Brisbane | Mackay www.kellylegal.com.au Building Construction Industry Payment Act 2004 (Qld) BCIPA Enables contractors to recover


slide-1
SLIDE 1

Contractor’s Seminar Asset Protection and Credit Control

Stephen Byrne, Director 15 December 2011

www.kellylegal.com.au Brisbane | Mackay

slide-2
SLIDE 2

Building Construction Industry Payment Act 2004 (Qld) “BCIPA”

www.kellylegal.com.au

  • Enables contractors to recover progress

payments

  • Construction work
  • Construction contract
slide-3
SLIDE 3

Construction work…

www.kellylegal.com.au

  • Broadly defined
  • Includes supply of related goods and services
  • Does not include:
  • Drilling for oil/gas
  • Extraction of minerals
slide-4
SLIDE 4

Progress payment becomes payment claim by…

www.kellylegal.com.au

  • Contractor
  • Subcontractor
  • Supplier
  • Hirer
  • Consultant
slide-5
SLIDE 5

Home owners are excluded unless…

www.kellylegal.com.au

  • Owner/builder
  • Not intending to reside
slide-6
SLIDE 6

Payment claim must…

www.kellylegal.com.au

  • Describe the work or goods & services
  • State the amount
  • Be endorsed

“this is a payment claim made under the Building Construction Industry Payment Act 2004 (Qld)”

slide-7
SLIDE 7

Payment claim…

www.kellylegal.com.au

  • Within 12 months
  • One per reference date or
  • Last day of the month
slide-8
SLIDE 8

Respondent to payment claim must, within 10 days…

www.kellylegal.com.au

  • Pay; or
  • Deliver a payment schedule

(reason for not paying)

slide-9
SLIDE 9

Payment schedule must…

www.kellylegal.com.au

  • State amount, if any, to be paid
  • State reasons for not paying full amount
slide-10
SLIDE 10

If no payment schedule within 10 days…

www.kellylegal.com.au

  • Suspension of work
  • Adjudication
  • Court judgment
slide-11
SLIDE 11

If payment schedule and less than full amount offered…

www.kellylegal.com.au

  • Suspension of work
  • Adjudication
slide-12
SLIDE 12

Adjudication…

www.kellylegal.com.au

  • By an independent adjudicator
  • As appointed by authorised nominating

authority

  • Increasing each year
slide-13
SLIDE 13

Adjudication process…

www.kellylegal.com.au

  • Very quick (30 days)
  • Final
  • Equal contribution to cost
slide-14
SLIDE 14

Subcontractors Charges Act…

www.kellylegal.com.au

  • Secures money payable by the principal

to your contractor

  • Three parties:
  • Principal/Developer/Contractor
  • Your contractor
  • You
slide-15
SLIDE 15

Charge can be over...

www.kellylegal.com.au

  • Unpaid money
  • Security

The work is broadly defined, but is not unlimited.

slide-16
SLIDE 16

Work includes…

www.kellylegal.com.au

  • Construction
  • Development of a mine
  • Use of plant or machinery
  • Includes supply of materials
slide-17
SLIDE 17

Work does not include…

www.kellylegal.com.au

  • Mere delivery of goods under a contract for

sale of goods

  • Work under a contract of service
  • Testing/taking measurements
slide-18
SLIDE 18

You…

www.kellylegal.com.au

  • Must be licensed
  • Must claim within 3 months
  • On completion of work
  • Of expiry of maintenance period
  • Of expiry of release period (security)
slide-19
SLIDE 19

Your Notice of Charge…

www.kellylegal.com.au

  • Must be certified
  • Architect/Engineer etc
  • Must be supported by a Statutory Declaration
slide-20
SLIDE 20

If the charge is accepted...

www.kellylegal.com.au

  • Payment by the principal
  • Proportional payment if insufficient money

for all

slide-21
SLIDE 21

If legal proceedings...

www.kellylegal.com.au

  • Money held or paid into court
  • Money paid by court order
slide-22
SLIDE 22

Company winding up…

www.kellylegal.com.au

  • Minimum amount $2,000
  • 21 days to pay
  • Must be for debt
  • Demand served by post or delivery
slide-23
SLIDE 23

Effect of non-compliance…

www.kellylegal.com.au

  • Presumption of insolvency
  • Setting aside demand
  • Within 21 days of service
  • By application to the court
slide-24
SLIDE 24

Grounds for setting aside…

www.kellylegal.com.au

  • Genuine dispute
  • Offsetting claim
  • Defect in notice
  • Some other reason
slide-25
SLIDE 25

Genuine dispute…

www.kellylegal.com.au

  • As to the nature of the debt
  • As to the amount
slide-26
SLIDE 26

Winding up application…

www.kellylegal.com.au

  • Within 3 months
  • Can only be opposed with leave of the Court
  • ATO debts cannot be disputed
slide-27
SLIDE 27

Voidable preferences…

www.kellylegal.com.au

  • Bankruptcy of a person
  • Winding up of a company
slide-28
SLIDE 28

Repay money received from the company…

www.kellylegal.com.au

  • In at least 6 months
  • Before the liquidation
slide-29
SLIDE 29

Why should you benefit at the expense of all other creditors?

www.kellylegal.com.au

The Test …

  • Good faith
  • No reasonable grounds for suspecting

insolvency

  • Reasonable person would not have either
  • Valuable consideration provided
slide-30
SLIDE 30

QCAT (Queensland Civil and Administrative Tribunal)

www.kellylegal.com.au

Debt Recovery…

  • $25,000 maximum
  • Simple
  • Economical
slide-31
SLIDE 31

Procedure…

www.kellylegal.com.au

  • Application
  • Response
  • Mediation
  • Hearing
slide-32
SLIDE 32

Generally…

www.kellylegal.com.au

  • Paper trail
  • Credit control
  • Get advice early
slide-33
SLIDE 33

Questions…

Stephen Byrne, Director 15 December 2011

www.kellylegal.com.au Brisbane | Mackay