pre construction informational meeting
play

Pre Construction Informational Meeting University Avenue (Allen - PowerPoint PPT Presentation

Pre Construction Informational Meeting University Avenue (Allen Boulevard Segoe Road) March 1, 2012 City of Madison City of Middleton Village of Shorewood Hills Dane County Changes Since March 2011 Meeting Dual Right Turn Lane at Allen


  1. Pre ‐ Construction Informational Meeting University Avenue (Allen Boulevard – Segoe Road) March 1, 2012 City of Madison City of Middleton Village of Shorewood Hills Dane County

  2. Changes Since March 2011 Meeting • Dual Right Turn Lane at Allen Boulevard – Changed to Single Right Turn Lane • Cul ‐ de ‐ sac at Laurel Crest (South) – Changed to Right ‐ Out Only • Left ‐ In Right ‐ In Right ‐ Out Access at Craig Avenue – Changed to Full Access Intersection with Traffic Signal • Old Middleton Road & Ramp Improvements – Added Bike Lanes, Sidewalks, Turn Lane • Erdman Property Development – Added New Intersection (University Row) with Traffic Signal

  3. Allen Boulevard Dual Right Turn Lane Changed to Single Right Turn Lane

  4. Laurel Crest (South) U-Turn Location Median Opening for Left-In Access Closed Right-Out Access Only

  5. Craig Avenue Sidewalk Changed to Minimize MG&E Impacts Full-Access, Signalized Intersection

  6. University Row Merge Lane for Westbound Traffic Median Opening Median Opening with University Row Half-Signalized Intersection Left-In Access only for U-Turns • Eastbound Traffic Stopped for Left-In/Left-Out Traffic at Perkins and Pedestrians • Westbound Traffic Stopped for Pedestrians Only New Crosswalk New Bus Pull-Out and Shelter

  7. Old Middleton Road Added Left Turn Sidewalk Added Lane Along Old Middleton Road, Ramps, and Univ EB/WB Bike Avenue between Lanes Added Eau Claire Avenue Along Ramps and and Segoe Road Old Middleton Road

  8. Construction Staging and Traffic Control • Access to businesses/residents maintained at all times • Notify business/property owners in advance of closure or restriction of access • Bi ‐ weekly meetings with business/property owners will be held to discuss the project schedule of operations including vehicular, bicycle and pedestrian access during construction operations • Portable Changeable Message Signs in advance of project to alert traffic • One lane of traffic in each direction throughout project • Temporary turn lanes at intersections • Temporary signals • Temporary crosswalks, sidewalks and bus stops • No work near Allen Boulevard intersection during Good Neighbor Festival Weekend • No work near Spring Harbor Drive intersection during school drop off and pick up times • No work on Badger home football game and UW Graduation days • Six stages of construction • Construction staging and schedule are subject to change • Construction to be completed by October 26, 2012

  9. Stage 1 Construction (Approx. 3/26 ‐ 4/23) Traffic • Remove medians, place temporary • Traffic reduced to one lane in each pavement for Stage 2 traffic direction from Allen Boulevard to Old Utility work Middleton Road and two lanes in each • • Install temporary traffic signals (Allen direction from Old Middleton Road to Boulevard, Capital Avenue, Spring Harbor Segoe Road Drive, and Whitney Way intersections) • Intersections open (sometimes under • Clearing and grubbing on entire project flagging)

  10. Stage 2 Traffic Construction (Approx. 4/23 ‐ 6/25) • Traffic reduced to one lane in each • Construct University Avenue eastbound direction from Allen Boulevard to Old lanes Middleton Road and two lanes in each Construct Spring Harbor pedestrian • direction from Old Middleton Road to underpass under eastbound lanes Segoe Road • Construct Capital Avenue (South), • St. Dunstan Drive intersection closed Norman Way (West), and Whitney Way • All other intersections open (sometimes intersections utilizing staged under flagging) construction • Temporary sidewalk on north ‐ side from • Construct Heim Avenue, Hickory Hollow Capital Avenue to Spring Harbor Drive Drive, Laurel Crest (South) and Craig • University Avenue approaches to Old Avenue intersections using flagging Middleton/railroad overpass to be operations during off ‐ peak hours closed (during night time hours only) for Grade and pave Old Middleton • 2 consecutive nights, Traffic will be Road/railroad overpass approaches detoured via Whitney Way and Old • Install street lights Middleton Road, University Avenue open during day

  11. Stage 3 Construction (Approx. 6/25 ‐ 7/23) Traffic • Construct University Avenue eastbound • Traffic reduced to one lane in each inside lane (for Stage 4 traffic) direction from Allen Boulevard to Old Construct Old Middleton Road Middleton Road and two lanes in each • Eastbound On ‐ Ramp to University direction from Old Middleton Road to Avenue Segoe Road • Install street lights • St. Dunstan Drive intersection closed • All other intersections open (sometimes under flagging) • Old Middleton Road Eastbound On ‐ Ramp to University Avenue closed for a maximum of 14 calendar days (from approx. 7/9 ‐ 7/23)

  12. Stage 4 Construction (Approx. 7/23 ‐ 10/1) Traffic • Construct University Avenue westbound • Traffic reduced to one lane in each direction from Allen Boulevard to Old outside lanes Middleton Road and two lanes in each Construct Spring Harbor pedestrian • direction from Old Middleton Road to underpass under westbound lanes Segoe Road • Construct Allen Boulevard, Capital • St. Dunstan Drive intersection closed Avenue (North), Norman Way (East), • Baker Avenue, Hickory Drive, and Laurel and Spring Harbor Drive intersections Crest ‐ North intersections to be closed utilizing staged construction one at a time • Construct Overlook Pass, Camus Lane, • All other intersections open (sometimes Fritz Avenue, and Tomahawk Trail under flagging) intersections using flagging operations during off ‐ peak hours Construct Baker Avenue, Hickory Drive, • and Laurel Crest (North) intersections • Install street lights

  13. Stage 5 Construction (Approx. 10/1 ‐ 10/26) Traffic • Construct University Avenue westbound • Traffic reduced to one lane in each inside lanes direction from Allen Boulevard to Old Construct Old Middleton Road Middleton Road and two lanes in each • Westbound Off ‐ Ramp from University direction from Old Middleton Road to Avenue Segoe Road • Construct permanent traffic signals • St. Dunstan Drive intersection closed (Allen Boulevard, Capital Avenue, Spring • All other intersections open (sometimes Harbor Drive, University Row, and under flagging) Whitney Way) • Old Middleton Road westbound off ‐ • Install street lights ramp from University Avenue closed for a maximum of 21 calendar days (from approx. 10/1 ‐ 10/22)

  14. Stage 6 Construction (Approx. 10/1 ‐ 10/26) Traffic • Construct final pavement surface during • Temporary lane closures during daytime night ‐ time hours and nighttime hours Place permanent pavement marking All intersections open (sometimes under • • flagging)

  15. Temporary Business Signs • Driveway Signs • Alternate Business Access Sign

  16. Erosion / Storm Water Control • Require Topsoiling & Finishing as Grading Progresses • Work Window for Sensitive Area (Hickory Gulch) • Inlet Protections • Tracking Pads at Grading Egress Locations • Erosion Mat on Slopes • Silt Fence at Embankments • Ditch Checks in Ditches/Swales/Channels • Catch Basins with Sumps • Storm Water Treatment Devices

  17. How to Get Info • Project Website – http://www.cityofmadison.com/engineering/universityAvenue/segoeAllen.cfm – Bi ‐ weekly meetings with contractor • My Madison Account for e ‐ mail updates – https://my.cityofmadison.com/index.cfm

  18. Construction Contacts Bob Endres Kevin Eslick Parisi Construction AECom 848 ‐ 5991 279 ‐ 0399 Bob@parisiconstruction.com KEVIN.ESLICK@aecom.com Glen Yoerger Scott LaCoursiere City of Madison Engineering OTIE 261 ‐ 9177 220 ‐ 2171 gyoerger@cityofmadison.com SLaCoursiere@otie.com

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.