pre bid conference for gmp 3 bid package 2 main lab and
play

Pre-Bid Conference for GMP #3 Bid Package #2 Main Lab and - PowerPoint PPT Presentation

D i a g n o s t i c s V a c c i n e s C o u n t e r m e a s u r e s Pre-Bid Conference for GMP #3 Bid Package #2 Main Lab and Outbuildings August 21 and 22, 2013 D e f e n d i n g A m e r i c a A g a i n s t F o r e i g n A n i


  1. D i a g n o s t i c s • V a c c i n e s • C o u n t e r m e a s u r e s Pre-Bid Conference for GMP #3 Bid Package #2 Main Lab and Outbuildings August 21 and 22, 2013 D e f e n d i n g A m e r i c a A g a i n s t F o r e i g n A n i m a l D i s e a s e s

  2. ������������������� • Location of Fire Exits • Please Silence all cell phones • This presentation will be posted to the McMjv.com website • There will be time at the end for Questions – All technical questions to be per PDC (RFI) process • Please use time after the session for Networking • Jobsite Walkthrough at 1:30 following this afternoon

  3. ������ • Overview of Team • Project Overview • Schedule • GMP #3 Scope • Additional Subcontractor Conditions • Request for Information • FOUO Requirements • Bid Day

  4. ����������� ����� McCarthy / Mortenson (McM) Personnel Jon Jacobsmeyer – Project Executive Mark Heit – Procurement Director Mark Duda – Preconstruction Director Rick Licari – Concrete Ray Elking – Structural Steel and Exteriors Walter Beckman – Interiors & General Works Walter Eads – Mechanical Trevor Turnipseed – Electrical Dan Oneal – Sitework and Water Treatment

  5. ����������� ����� NBAF Design Partnership (NDP) Personnel Perkins & Will – BSL Laboratory Architect Flad & Associates – Large Animal Architect / Structural Engineer Haynes-Whaley – Structural Engineer Travis Pruitt – Civil Engineer Terracon Consultants, Inc. – Environmental & Geotech Consultant Merrick & Company – Large Animal MEP Engineer Associated Engineers, Inc. – BSL Laboratory MEP Engineer ccrd Partners – BSL-4 MEP Engineer

  6. ����������� ����� DHS Key Personnel – NBAF Project Team Danny Hager – Chief, Bio-Containment Procurement Branch Jason Gerloff – Contracting Officer Robert Driggers – Contracting Officer Tim Barr – Site Manager Eugene Cole – Contracting Officer’s Technical Representative Tom Wilkinson – Contracting Officer’s Technical Representative

  7. ���������������� NBAF Mission Drivers • Construction of a BSL-4 large animal facility is critical to protecting the nations food supply, agriculture and public safety. • U.S. currently has no such capacity for large livestock research and is dependent upon the limited use of facilities in Canada and Australia. • The National Academies of Science has unequivocally stated in two recent reports that it is “imperative” that the U.S. have BSL-4 capability. • Current facility, Plum Island Animal Disease Center (PIADC) is 58 years old and at the end of its life cycle. – Limited research capability and no BSL-4 capability – Recapitalization would exceed $620M and still not provide BSL-4 capability

  8. ���������������� ���������

  9. ����������������

  10. ����������������

  11. ����������������

  12. ����������������

  13. ���������������� Main Laboratory Building

  14. ����������������

  15. ����������������

  16. ����������������

  17. ���������������� Transshipping Building

  18. ���������������� Visitor Center

  19. ���������������� Visitor Center

  20. ���������������� Entry Control Point – West Entry Control Point – North

  21. ���������������� Water Treatment

  22. ���������� ����� Overall Project Milestones • March 07, 2013 Start of Construction GMP #2 – Central Utility Plant • July 16 & 23, 2013 Small Business Outreach Sessions • August 13, 2013 GMP #3 – Main Lab and Outbuildings Bid Package Released • August 21, 22, 2013 Pre-Bid Conferences • September 13, 2013 GMP #3 Main Lab and Outbuildings Early Proposals Due • October 04, 2013 GMP #3 Main Lab and Outbuildings Remaining Proposals Due 4 th Quarter 2013 • Post-Bid Interviews

  23. !"��#$�% "��������� Overall Project Milestones 2 nd Quarter 2014 • Award of and Start of GMP #3 Construction 4 th Quarter 2015 • GMP #2 (CUP) Construction Complete 4 th Quarter 2019 • GMP #3 – Main Lab and Outbuildings Substantial Completion 2 nd Quarter 2020 • Commissioning Complete 3 rd Quarter 2020 • Owner Move-In, Operational Facility

  24. !"��#$��������������� Main Lab and Outbuildings Work Categories • WC 100 APR Doors & Windows • WC 101 Sterilizers • WC 102 Incinerators • WC 103 Tissue Autoclaves • WC 104 Liquid Decontamination System • WC 105 Earthwork • WC 106 Site Utilities • WC 107 Foundations/Structural Concrete (McM Self Perform) —WC 107-A Structural Excavation —WC 107-B Drilled Piers —WC 107-C Waterproofing —WC 107-D Reinforcing Steel —WC 107-E Not Used —WC 107-F Ready Mix Concrete – Furnish Only —WC 107-G Flatwork (Place and Finish) —WC 107-H Underslab Drainage

  25. !"��#$��������������� Main Lab and Outbuildings Work Categories • WC 108 Structural Steel • WC 109 Structural Steel Grillage & Impact Wall • WC 110 Masonry • WC 111 Furniture – Bid in Future Package • WC 112 Site Logistics (McM Self-Perform) • WC 113 Metal Studs, Drywall & Plaster • WC 114 General Works • WC 115 Metal Panels and Sheet Metal • WC 116 Roofing • WC 117 Fireproofing • WC 118 Missile and Tornado Resistive Doors • WC 119 Glass and Glazing • WC 120 Interior Glazing • WC 121 Acoustical Finishes • WC 122 High Containment Coatings • WC 123 Laboratory and Containable Coatings

  26. !"��#$��������������� Main Lab and Outbuildings Work Categories • WC 124 Interior and Exterior Painting • WC 125 Wood, Carpet, Resilient Base, and Linoleum • WC 126 Not Used • WC 127 Resinous Matrix Terrazzo, Interior Stone and Tile • WC 128 Penning and Gating • WC 129 Controlled Environment Rooms & Hoist System • WC 130 Light Tower • WC 131 Elevators • WC 132 Mechanical • WC 133 Electrical • WC 134 Building Automation Controls – Previously Awarded • WC 135 Fire Protection • WC 136 Asphalt Paving • WC 137 Landscaping & Irrigation

  27. !"��#$��������������� Main Lab and Outbuildings Work Categories • WC 138 Laboratory Casework and Fume Hoods • WC 139 Laboratory Equipment & Accessories • WC 140 Custom Stainless Steel • WC 141 Test & Balance • WC 142 Fencing • WC 143 Waste Treatment System • WC 144 Air Tight Door Assemblies • WC 145 Not Used • WC 146 Signage • WC 147 Not Used • WC 148 HEPA Filters • WC 149 Not Used • WC 150 Audio Visual & Tele/Data • WC 151 Not Used

  28. !"��#$��������������� Main Lab and Outbuildings Work Categories • WC 152 Food Service Equipment • WC 153 Not Used • WC 154 Building Enclosure Consultant • WC 155 Site Concrete • WC 156 Cleanroom Cleaning – Bid In Future Package

  29. !"��#$��������������� Main Lab and Outbuildings Work Categories Specific Items – Mark Duda • WC-100 – APR Doors and Windows • WC-101 – Sterilizers • WC-102 – Incinerators • WC-103 – Tissue Autoclaves • WC-104 – Liquid Decontamination System For the above Work Categories bidders are reminded: - These are Furnish and Install - Vendors need to Partner with Installers - Refer to Additional Subcontractor Conditions and Specifications - MEP No-Gaps Matrix (Exhibit J) will be issued in September - Exhibit GG (Misc Metals Matrix) defines embeds to be furnished and installed by concrete contractor

  30. !"��#$��������������� Main Lab and Outbuildings Work Categories Specific Items – Dan O’Neal • WC-105 – Mass Excavation – Does not include structural excavation which is part of 107. Can propose on both. • WC-106 – Site Utilities – Refer to P series drawings for some site drains and natural gas piping – Site piping between WWTP components as identified in exhibit PP

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend