Port Lands Flood Protection and Enabling Infrastructure Due - - PowerPoint PPT Presentation

port lands flood protection and enabling infrastructure
SMART_READER_LITE
LIVE PREVIEW

Port Lands Flood Protection and Enabling Infrastructure Due - - PowerPoint PPT Presentation

Port Lands Flood Protection and Enabling Infrastructure Due Diligence Presentation 1/25/2017 Contents 1. 1. The he Por ort L Lands ds 2. 2. Don on R River F Flood ood Prot otection on 3. 3. The P e Pro rojec ect 4. 4. Why


slide-1
SLIDE 1

Port Lands Flood Protection and Enabling Infrastructure Due Diligence Presentation

1/25/2017

slide-2
SLIDE 2

Contents

1. 1. The he Por

  • rt L

Lands ds 2. 2. Don

  • n R

River F Flood

  • od Prot
  • tection
  • n

3. 3. The P e Pro rojec ect 4. 4. Why Undert ertake D e Due D ue Dili ligen ence 5. 5. Du Due Dil Dilig igence F Fin indin ings 6. 6. Pro rojec ect B Ben enef efits 7. 7. Timeli eline e and N Nex ext S Step eps

slide-3
SLIDE 3

The Port Lands

slide-4
SLIDE 4

The Port Lands

slide-5
SLIDE 5

Contents

1. 1. The he Por

  • rt L

Lands ds 2. 2. Don

  • n R

River F Flood

  • od Prot
  • tection
  • n

3. 3. The P e Pro rojec ect 4. 4. Why Undert ertake D e Due D ue Dili ligen ence 5. 5. Du Due Dil Dilig igence F Fin indin ings 6. 6. Pro rojec ect B Ben enef efits 7. 7. Timeli eline e and N Nex ext S Step eps

slide-6
SLIDE 6

Don River Flood Protection

Flood Plain Flood Protected Flood Protection Landform

slide-7
SLIDE 7

Contents

1. 1. The he Por

  • rt L

Lands ds 2. 2. Don

  • n R

River F Flood

  • od Prot
  • tection
  • n

3. 3. The P e Pro rojec ect 4. 4. Why Undert ertake D e Due D ue Dili ligen ence 5. 5. Du Due Dil Dilig igence F Fin indin ings 6. 6. Pro rojec ect B Ben enef efits 7. 7. Timeli eline e and N Nex ext S Step eps

slide-8
SLIDE 8

The Project: The Port Lands Today

slide-9
SLIDE 9

The Project: The Port Lands Flood protection Project Uniqu que e and Unprec eced eden ented ed:

  • River Mouth concept as flood protection
  • No established regulatory approval process

for creating a river in brownfield

After er Flood

  • od Prot
  • tec

ection

  • n:
  • New Don River mouth
  • Don Greenway (north of the Ship Channel)
  • Improved Keating Channel
  • Additional Infrastructure to drive

development

slide-10
SLIDE 10

Project Scope: individual Components

slide-11
SLIDE 11

Contents

1. 1. The he Por

  • rt L

Lands ds 2. 2. Don

  • n R

River F Flood

  • od Prot
  • tection
  • n

3. 3. The P e Pro rojec ect 4. 4. Why Undert ertake D e Due D ue Dili ligen ence 5. 5. Du Due Dil Dilig igence F Fin indin ings 6. 6. Pro rojec ect B Ben enef efits 7. 7. Timeli eline e and N Nex ext S Step eps

slide-12
SLIDE 12

Why Due Diligence?

Und nderstand nd the project’s u unk nkno nowns wns and nd pr prov

  • vide

de as m muc uch assura urance e as pos possibl ble on

  • n cost

sts, s, r risk isks, s, and nd sched edule ule to red reduc uce e un uncert ertainty

  • Develop the design concept for the project – beyond the EA design
  • Define project scope
  • Detailed site-specific information on soils, etc.
  • Environmental and regulatory approval requirements and processes
  • Construction logistics
  • Risk identification, assessment and quantification = contingency setting
  • Implementation strategies and schedule

Achiev eves es an ex excep eption

  • nal lev

evel el of

  • f due

e diligen gence e for for a larg arge pub ubli lic c inf nfrastruct uctur ure proj

  • jec

ect

slide-13
SLIDE 13

Due Diligence: Deliverables

  • Concep

eptua ual d l des esigns prepared for key project components allowed for better understanding of unknown conditions

  • Informed how the project will be constructed and implications for the cost, schedule and risk
  • Ref

efined ed Pro rojec ect s scope e to better balance flood protection and development-enabling infrastructure in light of the new cost, schedule and risk information

  • Upda

pdated d const structio ion c cost st esti timate ate based on the concept design and refined project scope

  • Updated

ed pro rojec ect s sched edule ule that includes design, regulatory and environmental approvals and construction

  • Risk

isk R Regist ister comprehensive list of potential risks and opportunities,

  • Probabil

ilist istic ic r risk isk sim simulatio ion model developed using updated schedule, cost and risk register

  • Identified the probability of the project meeting its cost and schedule goals
  • Informed decision making on schedule, cost estimate and risks contingencies
slide-14
SLIDE 14

Contents

1. 1. The he Por

  • rt L

Lands ds 2. 2. Don

  • n R

River F Flood

  • od Prot
  • tection
  • n

3. 3. The P e Pro rojec ect 4. 4. Why Undert ertake D e Due D ue Dili ligen ence 5. 5. Du Due Dil Dilig igence F Fin indin ings 6. 6. Pro rojec ect B Ben enef efits 7. 7. Ques Questions

slide-15
SLIDE 15

Due Diligence: Key Findings

Cost Estimate: $1.25 billion Probability of completion within $1.25 billion: 90% Major Risks/Cost Drivers:

  • Site Conditions: flowing sand, compressible peat
  • No established regulatory approval process for creating a river in brownfield

Contingency: 30% Timeline: Seven-year construction period

slide-16
SLIDE 16

Due Diligence: Key Findings

slide-17
SLIDE 17

Due Diligence Findings: Soil and Water Contamination Profile

slide-18
SLIDE 18

Due Diligence Findings: Excavation and Fill Sequencing, Stage 1

slide-19
SLIDE 19

Due Diligence Findings: Excavation and Fill Sequencing, Stage 2

slide-20
SLIDE 20

Due Diligence Findings: Excavation and Fill Sequencing, Stage 3

slide-21
SLIDE 21

Due Diligence Findings: Excavation and Fill Sequencing, Stage 4

slide-22
SLIDE 22

Due Diligence Findings: Site Grading

1.0m

slide-23
SLIDE 23

Due Diligence Findings: Interim Road Network and Building Removal/Relocation

slide-24
SLIDE 24

Due Diligence Findings: Flood Protection Components

slide-25
SLIDE 25

Due Diligence Findings: Wetland Habitat and Park Components

slide-26
SLIDE 26

Due Diligence Findings: Bridges and Roads

Don Roadway New Cherry Street Commissioners Street

slide-27
SLIDE 27

Due Diligence Findings: New and Replacement Services

slide-28
SLIDE 28

Due Diligence Findings: Project Scope and Cost Estimate Original Cost Estimate ($YoE): $975 million Current Cost Estimate ($YoE): $1.25 billion

  • 1. Key finding that shaped revised cost estimate
  • Site Conditions: flowing sand, compressible peat =

additional soil excavation, soil/groundwater treatment

  • Escalation/Inflation
  • 2. Re-evaluated Project Scope
  • Three new components identified
  • Three components deferred
  • Scope reductions

Includes:

  • Contingency
  • Design Allowance
  • Indirect Contractor Costs
  • Soft costs (legal, approvals, engineering)
  • Non-recoverable HST

Due Diligence Report, Page 83

slide-29
SLIDE 29

Project Approvals and Construction Timeline

Due Diligence Report, Page 101

slide-30
SLIDE 30

Due Diligence Key Findings: Construction Coordination

4 6

slide-31
SLIDE 31

Due Diligence Key Findings: Peer Review

  • Unprecedented Project
  • Important to Peer Review
  • Independent review by qualified organizations
  • Examine Report’s adequacy and accuracy

The Netherlands Ministry of Infrastructure and Environment A global construction services provider specializing in water and marine-based projects.

slide-32
SLIDE 32

Contents

1. 1. The he Por

  • rt L

Lands ds 2. 2. Don

  • n R

River F Flood

  • od Prot
  • tection
  • n

3. 3. The P e Pro rojec ect 4. 4. Why Undert ertake D e Due D ue Dili ligen ence 5. 5. Du Due Dil Dilig igence F Fin indin ings 6. 6. Pro rojec ect B Ben enef efits 7. 7. Timeli eline e and N Nex ext S Step eps

slide-33
SLIDE 33

Project Benefits: Economic Impact and Jobs

Source: Economic Impacts of Planned Investments, urbanMetrics, 2016

slide-34
SLIDE 34

Unlocking Future Development: Port Lands and First Gulf/Unilever Site

slide-35
SLIDE 35

Sustainable, Livable & Beautiful Communities

slide-36
SLIDE 36

Sustainable, Livable & Beautiful Communities

slide-37
SLIDE 37

Sustainable, Livable & Beautiful Communities

slide-38
SLIDE 38

Sustainable, Livable & Beautiful Communities

slide-39
SLIDE 39

Sustainable, Livable & Beautiful Communities

slide-40
SLIDE 40

Sustainable, Livable & Beautiful Communities

slide-41
SLIDE 41

Contents

1. 1. The he Por

  • rt L

Lands ds 2. 2. Don

  • n R

River F Flood

  • od Prot
  • tection
  • n

3. 3. The P e Pro rojec ect 4. 4. Why Undert ertake D e Due D ue Dili ligen ence 5. 5. Du Due Dil Dilig igence F Fin indin ings 6. 6. Pro rojec ect B Ben enef efits 7. 7. Timeli eline e and N Nex ext S Step eps

slide-42
SLIDE 42

Next Steps

The Project:

Funding: City of Toronto Council has directed staff to identify funding its one-third share through the 2017-2026 capital budget process. The Government of Canada and Province of Ontario have not yet committed funding . Start Date: The Project is not yet fully funded and, as a result, there is no official start date for construction at this time, with the exception

  • f the Essroc Quay Lakefilling Project

Essroc Quay Lakefilling:

Funding: Committed Start Date: Detailed Design Starts February 2017 Construction Starts August 2017 Consultation: Stakeholder engagement in early 2017

Port Lands Framework Plan, Villiers Island Precinct Plan, and Transportation and Servicing Master Plan:

Waterfront Toronto and the City of Toronto have continued to refine the plans since the public and stakeholder consultation in Fall 2015 Stakeholder update will follow in early 2017