SLIDE 1
Port Lands Flood Protection and Enabling Infrastructure Due Diligence Presentation
1/25/2017
SLIDE 2 Contents
1. 1. The he Por
Lands ds 2. 2. Don
River F Flood
3. 3. The P e Pro rojec ect 4. 4. Why Undert ertake D e Due D ue Dili ligen ence 5. 5. Du Due Dil Dilig igence F Fin indin ings 6. 6. Pro rojec ect B Ben enef efits 7. 7. Timeli eline e and N Nex ext S Step eps
SLIDE 3
The Port Lands
SLIDE 4
The Port Lands
SLIDE 5 Contents
1. 1. The he Por
Lands ds 2. 2. Don
River F Flood
3. 3. The P e Pro rojec ect 4. 4. Why Undert ertake D e Due D ue Dili ligen ence 5. 5. Du Due Dil Dilig igence F Fin indin ings 6. 6. Pro rojec ect B Ben enef efits 7. 7. Timeli eline e and N Nex ext S Step eps
SLIDE 6
Don River Flood Protection
Flood Plain Flood Protected Flood Protection Landform
SLIDE 7 Contents
1. 1. The he Por
Lands ds 2. 2. Don
River F Flood
3. 3. The P e Pro rojec ect 4. 4. Why Undert ertake D e Due D ue Dili ligen ence 5. 5. Du Due Dil Dilig igence F Fin indin ings 6. 6. Pro rojec ect B Ben enef efits 7. 7. Timeli eline e and N Nex ext S Step eps
SLIDE 8
The Project: The Port Lands Today
SLIDE 9 The Project: The Port Lands Flood protection Project Uniqu que e and Unprec eced eden ented ed:
- River Mouth concept as flood protection
- No established regulatory approval process
for creating a river in brownfield
After er Flood
ection
- n:
- New Don River mouth
- Don Greenway (north of the Ship Channel)
- Improved Keating Channel
- Additional Infrastructure to drive
development
SLIDE 10
Project Scope: individual Components
SLIDE 11 Contents
1. 1. The he Por
Lands ds 2. 2. Don
River F Flood
3. 3. The P e Pro rojec ect 4. 4. Why Undert ertake D e Due D ue Dili ligen ence 5. 5. Du Due Dil Dilig igence F Fin indin ings 6. 6. Pro rojec ect B Ben enef efits 7. 7. Timeli eline e and N Nex ext S Step eps
SLIDE 12 Why Due Diligence?
Und nderstand nd the project’s u unk nkno nowns wns and nd pr prov
de as m muc uch assura urance e as pos possibl ble on
sts, s, r risk isks, s, and nd sched edule ule to red reduc uce e un uncert ertainty
- Develop the design concept for the project – beyond the EA design
- Define project scope
- Detailed site-specific information on soils, etc.
- Environmental and regulatory approval requirements and processes
- Construction logistics
- Risk identification, assessment and quantification = contingency setting
- Implementation strategies and schedule
Achiev eves es an ex excep eption
evel el of
e diligen gence e for for a larg arge pub ubli lic c inf nfrastruct uctur ure proj
ect
SLIDE 13 Due Diligence: Deliverables
eptua ual d l des esigns prepared for key project components allowed for better understanding of unknown conditions
- Informed how the project will be constructed and implications for the cost, schedule and risk
- Ref
efined ed Pro rojec ect s scope e to better balance flood protection and development-enabling infrastructure in light of the new cost, schedule and risk information
pdated d const structio ion c cost st esti timate ate based on the concept design and refined project scope
ed pro rojec ect s sched edule ule that includes design, regulatory and environmental approvals and construction
isk R Regist ister comprehensive list of potential risks and opportunities,
ilist istic ic r risk isk sim simulatio ion model developed using updated schedule, cost and risk register
- Identified the probability of the project meeting its cost and schedule goals
- Informed decision making on schedule, cost estimate and risks contingencies
SLIDE 14 Contents
1. 1. The he Por
Lands ds 2. 2. Don
River F Flood
3. 3. The P e Pro rojec ect 4. 4. Why Undert ertake D e Due D ue Dili ligen ence 5. 5. Du Due Dil Dilig igence F Fin indin ings 6. 6. Pro rojec ect B Ben enef efits 7. 7. Ques Questions
SLIDE 15 Due Diligence: Key Findings
Cost Estimate: $1.25 billion Probability of completion within $1.25 billion: 90% Major Risks/Cost Drivers:
- Site Conditions: flowing sand, compressible peat
- No established regulatory approval process for creating a river in brownfield
Contingency: 30% Timeline: Seven-year construction period
SLIDE 16
Due Diligence: Key Findings
SLIDE 17
Due Diligence Findings: Soil and Water Contamination Profile
SLIDE 18
Due Diligence Findings: Excavation and Fill Sequencing, Stage 1
SLIDE 19
Due Diligence Findings: Excavation and Fill Sequencing, Stage 2
SLIDE 20
Due Diligence Findings: Excavation and Fill Sequencing, Stage 3
SLIDE 21
Due Diligence Findings: Excavation and Fill Sequencing, Stage 4
SLIDE 22 Due Diligence Findings: Site Grading
1.0m
SLIDE 23
Due Diligence Findings: Interim Road Network and Building Removal/Relocation
SLIDE 24
Due Diligence Findings: Flood Protection Components
SLIDE 25
Due Diligence Findings: Wetland Habitat and Park Components
SLIDE 26 Due Diligence Findings: Bridges and Roads
Don Roadway New Cherry Street Commissioners Street
SLIDE 27
Due Diligence Findings: New and Replacement Services
SLIDE 28 Due Diligence Findings: Project Scope and Cost Estimate Original Cost Estimate ($YoE): $975 million Current Cost Estimate ($YoE): $1.25 billion
- 1. Key finding that shaped revised cost estimate
- Site Conditions: flowing sand, compressible peat =
additional soil excavation, soil/groundwater treatment
- Escalation/Inflation
- 2. Re-evaluated Project Scope
- Three new components identified
- Three components deferred
- Scope reductions
Includes:
- Contingency
- Design Allowance
- Indirect Contractor Costs
- Soft costs (legal, approvals, engineering)
- Non-recoverable HST
Due Diligence Report, Page 83
SLIDE 29 Project Approvals and Construction Timeline
Due Diligence Report, Page 101
SLIDE 30
Due Diligence Key Findings: Construction Coordination
4 6
SLIDE 31 Due Diligence Key Findings: Peer Review
- Unprecedented Project
- Important to Peer Review
- Independent review by qualified organizations
- Examine Report’s adequacy and accuracy
The Netherlands Ministry of Infrastructure and Environment A global construction services provider specializing in water and marine-based projects.
SLIDE 32 Contents
1. 1. The he Por
Lands ds 2. 2. Don
River F Flood
3. 3. The P e Pro rojec ect 4. 4. Why Undert ertake D e Due D ue Dili ligen ence 5. 5. Du Due Dil Dilig igence F Fin indin ings 6. 6. Pro rojec ect B Ben enef efits 7. 7. Timeli eline e and N Nex ext S Step eps
SLIDE 33
Project Benefits: Economic Impact and Jobs
Source: Economic Impacts of Planned Investments, urbanMetrics, 2016
SLIDE 34
Unlocking Future Development: Port Lands and First Gulf/Unilever Site
SLIDE 35
Sustainable, Livable & Beautiful Communities
SLIDE 36
Sustainable, Livable & Beautiful Communities
SLIDE 37
Sustainable, Livable & Beautiful Communities
SLIDE 38
Sustainable, Livable & Beautiful Communities
SLIDE 39
Sustainable, Livable & Beautiful Communities
SLIDE 40
Sustainable, Livable & Beautiful Communities
SLIDE 41 Contents
1. 1. The he Por
Lands ds 2. 2. Don
River F Flood
3. 3. The P e Pro rojec ect 4. 4. Why Undert ertake D e Due D ue Dili ligen ence 5. 5. Du Due Dil Dilig igence F Fin indin ings 6. 6. Pro rojec ect B Ben enef efits 7. 7. Timeli eline e and N Nex ext S Step eps
SLIDE 42 Next Steps
The Project:
Funding: City of Toronto Council has directed staff to identify funding its one-third share through the 2017-2026 capital budget process. The Government of Canada and Province of Ontario have not yet committed funding . Start Date: The Project is not yet fully funded and, as a result, there is no official start date for construction at this time, with the exception
- f the Essroc Quay Lakefilling Project
Essroc Quay Lakefilling:
Funding: Committed Start Date: Detailed Design Starts February 2017 Construction Starts August 2017 Consultation: Stakeholder engagement in early 2017
Port Lands Framework Plan, Villiers Island Precinct Plan, and Transportation and Servicing Master Plan:
Waterfront Toronto and the City of Toronto have continued to refine the plans since the public and stakeholder consultation in Fall 2015 Stakeholder update will follow in early 2017