plaza east
play

Plaza East Chantilly , Virginia Steven M. Miller Senior Thesis - PowerPoint PPT Presentation

Plaza East Chantilly , Virginia Steven M. Miller Senior Thesis 2008 Construction Management Plaza East Chantilly, Virginia Project Overview Presentation Topics Analysis 1: Building Envelope Analysis 2: Green Building Envelope Roof


  1. Plaza East Chantilly , Virginia Steven M. Miller Senior Thesis 2008 Construction Management

  2. Plaza East Chantilly, Virginia Project Overview Presentation Topics Analysis 1: Building Envelope Analysis 2: Green Building Envelope Roof Investigation Implementation Green Roof Analysis 3: Im plem entation Checking Green Roof Loads New Roof Loads Analysis Research: Implementation of Research Topic: Steel Software for Steel Buildings Erection Software Q & A Steve Miller Construction Management

  3. Plaza East Chantilly, Virginia Project Overview Goals Analysis 1: Building Envelope 1. Save tim e and m oney with new building façade m aterial Analysis 2: Green Roof 2. Use m oney saved to install a Implementation green roof 3. Save energy and m oney with Analysis 3: new building façade m aterial Checking Green Roof Loads and green roof 4. Inform others of the perks in the paperless process of steel Research: Implementation of buildings Software for Steel Buildings Q & A Steve Miller Construction Management

  4. Plaza East Chantilly, Virginia Project Overview Proj ect Overview Analysis 1: Building Envelope Basic Project Inform ation: • 5 stories above grade Analysis 2: Green Roof • 123,000 sqf per building Implementation • Design ‐ Bid ‐ Build • Function ‐ General Office Building • Duration ‐ March 2006 to August 2007 Analysis 3: • Cost ‐ $28 to $29.5 million Checking Green Roof Loads • Total Project Cost $ 54 million Project Team : • Owner - Tishman Speyer Properties Research: • Architect - Hellmuth, Obata + Kassabaum, P.C. Implementation of Software for Steel • Mechanical Contractor - GHT Limited Buildings • Structural Contractor - Smislova, Kehnemui & Associates, P.C. • General Contractor: James G. DAVIS Construction Q & A • Civil Engineer - VIKA, Inc. Steve Miller Construction Management

  5. Plaza East Chantilly, Virginia Project Overview Proj ect Overview Analysis 1: Building Envelope Analysis 2: Green Roof Implementation Analysis 3: Checking Green Roof Loads Research: Implementation of Software for Steel Buildings Q & A Steve Miller Construction Management

  6. Plaza East Chantilly, Virginia Project Overview Building Envelope Analysis 1: Building Envelope CENTRIA Form awall Dim ension Series with Duracast Coating Analysis 2: Green And CENTRIA Versawall with Duracst Coating Roof vs Implementation Architectural Precast Concrete Analysis 3: Checking Green Roof Loads Research: Implementation of Software for Steel Buildings Q & A Steve Miller Construction Management

  7. Plaza East Chantilly, Virginia Project Overview Building Envelope Analysis 1: Building Envelope CENTRIA Form awall and Versawall Architectural Precast Analysis 2: Green Roof Pros Pros Implementation Reduces structural requirements Highly Durable Reduces installation costs Good Acoustics Shortens material lead time Molds can be easily replicated Analysis 3: Faster Installation Usually Cheap Checking Green Higher R-Value Roof Loads LEED Points Cons Degradation from acid rain and alkali runoff etches glass and Research: Cons Implementation of deteriorates metals Plain looking compared to the Software for Steel Surface Finishes inconsistent architectural precast Buildings Accidents usually fatal Q & A Steve Miller Construction Management

  8. Plaza East Chantilly, Virginia Project Overview Building Envelope Analysis 1: Building Envelope LEED Points Analysis 2: Green Roof • Up to 10 for optim izing energy perform ance Implementation • 2 for recycling content • 2 for low-em itting m aterials Analysis 3: Checking Green ▫ Adhesives and Sealants Roof Loads ▫ Paints and Coatings Research: Implementation of Software for Steel Buildings Q & A Steve Miller Construction Management

  9. Plaza East Chantilly, Virginia Project Overview Building Envelope Analysis 1: Building Envelope Area and cost Calculations Analysis 2: Green Roof Estimated Façade Costs Implementation Quantity Unit Total Unit Cost Total Cost 23,663 Precast (original) sf ‐‐ $2,600,000.00 23,663 Versawall sf 30 $709,890.00 23,663 Formawall Dim. Series sf 60 $1,419,780.00 Analysis 3: Checking Green Roof Loads Savings: 4” Versawall with Duracast Finishing Actual precast cost (not including change orders): $2,600,000.00 ‐ $709,890.00 = $1,8 9 0 ,110 .0 0 Research: Implementation of Formawall Dimension Series with Duracast Finishing Software for Steel Actual precast cost (not including change orders): Buildings $2,600,000.00 ‐ $1,419,780.00 = $ 1,18 0 ,220 .0 0 Q & A Steve Miller Construction Management

  10. Plaza East Chantilly, Virginia Project Overview Building Envelope Analysis 1: Building Envelope Analysis 2: Green Roof Implementation Analysis 3: Checking Green Roof Loads Research: Implementation of Software for Steel Buildings Q & A Steve Miller Construction Management

  11. Plaza East Chantilly, Virginia Project Overview Building Envelope Analysis 1: Building Envelope Top Floor Only Analysis 2: Green Existing Form awall and Versawall Roof R-Value of 10 for Walls R-Value of 20 and 30 for Walls Implementation R-Value of 18 to 19 for Roof R-Value of 18 to 19 for Roof Analysis 3: Checking Green Roof Loads Research: Implementation of Software for Steel Buildings Q & A Steve Miller Construction Management

  12. Plaza East Chantilly, Virginia Project Overview Building Envelope Analysis 1: Building Envelope Energy Savings Analysis 2: Green Roof Form awall 1.90 kBtu/ft 2 Heating Implementation ‐ 0.1 kBtu/ft 2 Cooling 1.8 kBtu/ft 2 Total Analysis 3: Checking Green Annual Energy Costs Savings were $0.021/ft 2 Roof Loads Versawall 1.6 kBtu/ft 2 Heating Research: ‐ 0.3 kBtu/ft 2 Cooling Implementation of Software for Steel ‐ 0.1 kBtu/ft 2 Other Buildings 1.2 kBtu/ft 2 Total Annual Energy Costs savings were $0.012/ft 2 Q & A Steve Miller Construction Management

  13. Plaza East Chantilly, Virginia Project Overview Green R oof Implementation Analysis 1: Building Envelope Proposal: Use m oney saved from different façade to add a Green Roof to help with Energy Savings Analysis 2: Green Roof Implementation Som e Green Advantages Helps manage storm water – almost 1000 parking spots • Reduce noise pollution • Analysis 3: Long life span from ultraviolent protection • Checking Green Creates habitat for birds and other animals • Roof Loads Helps with the urban heat island effect • Research: Implementation of Software for Steel Buildings Q & A Steve Miller Construction Management

  14. Plaza East Chantilly, Virginia Project Overview Green R oof Implementation Analysis 1: Building Envelope Top Floor Only Analysis 2: Green Existing Green Roof Roof R-Value of 10 for Walls R-Value of 10 for Walls Implementation R-Value of 18 to 19 for Roof R-Value of 30 for Roof Solar Absorption 0 .6 Solar Absorption 0 .2 Analysis 3: Checking Green Roof Loads Research: Implementation of Software for Steel Buildings Q & A Steve Miller Construction Management

  15. Plaza East Chantilly, Virginia Project Overview Green R oof Implementation Analysis 1: Building Envelope Energy Savings Analysis 2: Green Green Roof 4.5 kBtu/ft 2 Heating Roof Implementation 0.1 kBtu/ft 2 Cooling 0.2 kBtu/ft 2 Other 4.8 kBtu/ft 2 Total Analysis 3: Checking Green Annual Energy Costs Savings were $0.003/ft 2 Roof Loads Cost of Existing Roof Cost of Green Roof $9 per ft 2 at 20 years life span $8 to $12 per ft 2 additional to existing price at 40 to 50 years life span Research: Implementation of $17/ft 2 x 26000 = $442,000 Software for Steel Buildings $ 208,000 additional original cost Q & A Steve Miller Construction Management

  16. Plaza East Chantilly, Virginia Project Overview Green R oof Implementation Analysis 1: Building Envelope Years needed to m ake m oney back? Analysis 2: Green $442,000 ‐ $234,000 = $208,000 Roof Implementation Annual Energy Cost Savings does not apply Analysis 3: After 20 years build up roof needs replaced: Checking Green Roof Loads ($9/ft 2 )(26,000ft 2 )(2 nd roof) = $468,000 > $442,000 Research: Implementation of Software for Steel Green roof pays for itself after 20 years… Buildings …and lasts up to the next 20 to 30 years Q & A Steve Miller Construction Management

  17. Plaza East Chantilly, Virginia Project Overview Green R oof Implementation Analysis 1: Building Envelope Individually - Building façade Not much energy or cost savings Analysis 2: Green Roof Implementation -Green Roof Not much energy or cost savings Decided to com bine green roof and new building envelope Analysis 3: Checking Green Versawall and Green Roof Form awall and Green Roof Roof Loads Research: Implementation of Software for Steel Buildings Q & A Steve Miller Construction Management

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend