plaza east plaza east
play

Plaza East Plaza East Analysis 3: Im plem entation Checking Green - PDF document

4/28/2008 Plaza East Chantilly, Virginia Project Overview Presentation Topics Analysis 1: Building Envelope Analysis 2: Green Building Envelope Roof Implementation Investigation Green Roof Green Roof Plaza East Plaza East Analysis 3:


  1. 4/28/2008 Plaza East Chantilly, Virginia Project Overview Presentation Topics Analysis 1: Building Envelope Analysis 2: Green Building Envelope Roof Implementation Investigation Green Roof Green Roof Plaza East Plaza East Analysis 3: Im plem entation Checking Green Roof Loads Chantilly , Virginia New Roof Loads Analysis Research: Implementation of Research Topic: Steel Software for Steel Buildings Erection Software Steven M. Miller Senior Thesis 2008 Q & A Construction Management Steve Miller Construction Management Plaza East Plaza East Chantilly, Virginia Chantilly, Virginia Project Overview Project Overview Goals Proj ect Overview Analysis 1: Building Analysis 1: Building Envelope Envelope 1. Save tim e and m oney with new Basic Project Inform ation: building façade m aterial • 5 stories above grade Analysis 2: Green Analysis 2: Green Roof Roof • 123,000 sqf per building 2. Use m oney saved to install a Implementation Implementation • Design ‐ Bid ‐ Build green roof • Function ‐ General Office Building • Duration ‐ March 2006 to August 2007 • Duration March 2006 to August 2007 3 3. Save energy and m oney with Save energy and m oney with Analysis 3: Analysis 3: new building façade m aterial • Cost ‐ $28 to $29.5 million Checking Green Checking Green Roof Loads and green roof Roof Loads • Total Project Cost $ 54 million Project Team : 4. Inform others of the perks in • Owner - Tishman Speyer Properties the paperless process of steel Research: Research: Implementation of Implementation of • Architect - Hellmuth, Obata + Kassabaum, P.C. buildings Software for Steel Software for Steel • Mechanical Contractor - GHT Limited Buildings Buildings • Structural Contractor - Smislova, Kehnemui & Associates, P.C. • General Contractor: James G. DAVIS Construction Q & A Q & A • Civil Engineer - VIKA, Inc. Steve Miller Steve Miller Construction Management Construction Management 1

  2. 4/28/2008 Plaza East Plaza East Chantilly, Virginia Chantilly, Virginia Project Overview Project Overview Proj ect Overview Building Envelope Analysis 1: Building Analysis 1: Building Envelope Envelope CENTRIA Form awall Dim ension Series with Duracast Coating Analysis 2: Green Analysis 2: Green And CENTRIA Versawall with Duracst Coating Roof Roof vs Implementation Implementation Architectural Precast Concrete Analysis 3: Analysis 3: Checking Green Checking Green Roof Loads Roof Loads Research: Research: Implementation of Implementation of Software for Steel Software for Steel Buildings Buildings Q & A Q & A Steve Miller Steve Miller Construction Management Construction Management Plaza East Plaza East Chantilly, Virginia Chantilly, Virginia Project Overview Project Overview Building Envelope Building Envelope Analysis 1: Building Analysis 1: Building Envelope Envelope CENTRIA Form awall and Versawall Architectural Precast LEED Points Analysis 2: Green Analysis 2: Green Roof Pros Roof • Pros Up to 10 for optim izing energy perform ance Implementation Implementation Reduces structural requirements Highly Durable • 2 for recycling content Good Acoustics Reduces installation costs Shortens material lead time Molds can be easily replicated o ds ca be eas y ep cated • 2 for low em itting m aterials 2 for low-em itting m aterials Analysis 3: Analysis 3: Usually Cheap Faster Installation Checking Green Checking Green Higher R-Value ▫ Roof Loads Roof Loads Adhesives and Sealants LEED Points Cons ▫ Paints and Coatings Degradation from acid rain and alkali runoff etches glass and Research: Cons Research: Implementation of Implementation of deteriorates metals Plain looking compared to the Software for Steel Software for Steel Surface Finishes inconsistent architectural precast Buildings Buildings Accidents usually fatal Q & A Q & A Steve Miller Steve Miller Construction Management Construction Management 2

  3. 4/28/2008 Plaza East Plaza East Chantilly, Virginia Chantilly, Virginia Project Overview Project Overview Building Envelope Building Envelope Analysis 1: Building Analysis 1: Building Envelope Envelope Area and cost Calculations Analysis 2: Green Analysis 2: Green Roof Roof Estimated Façade Costs Implementation Implementation Quantity Unit Total Unit Cost Total Cost Precast (original) 23,663 sf ‐‐ $2,600,000.00 Versawall 23,663 sf 30 $709,890.00 Formawall Dim Series Formawall Dim. Series 23 663 23,663 sf sf 60 60 $1 419 780 00 $1,419,780.00 Analysis 3: Analysis 3: Checking Green Checking Green Roof Loads Roof Loads Savings: 4” Versawall with Duracast Finishing Actual precast cost (not including change orders): $2,600,000.00 ‐ $709,890.00 = $1,8 90 ,110 .0 0 Research: Research: Implementation of Implementation of Formawall Dimension Series with Duracast Finishing Software for Steel Software for Steel Actual precast cost (not including change orders): Buildings Buildings $2,600,000.00 ‐ $1,419,780.00 = $ 1,18 0 ,220 .0 0 Q & A Q & A Steve Miller Steve Miller Construction Management Construction Management Plaza East Plaza East Chantilly, Virginia Chantilly, Virginia Project Overview Project Overview Building Envelope Building Envelope Analysis 1: Building Analysis 1: Building Envelope Envelope Top Floor Only Energy Savings Analysis 2: Green Analysis 2: Green Existing Form awall and Versawall Roof Roof Form awall R-Value of 10 for Walls R-Value of 20 and 30 for Walls Implementation Implementation 1.90 kBtu/ft 2 Heating R-Value of 18 to 19 for Roof R-Value of 18 to 19 for Roof ‐ 0.1 kBtu/ft 2 Cooling 1.8 kBtu/ft 2 Total Analysis 3: Analysis 3: Checking Green Checking Green Annual Energy Costs Savings were $0.021/ft 2 Roof Loads Roof Loads Versawall 1.6 kBtu/ft 2 Heating Research: Research: Implementation of Implementation of ‐ 0.3 kBtu/ft 2 Cooling Software for Steel Software for Steel ‐ 0.1 kBtu/ft 2 Other Buildings Buildings 1.2 kBtu/ft 2 Total Annual Energy Costs savings were $0.012/ft 2 Q & A Q & A Steve Miller Steve Miller Construction Management Construction Management 3

  4. 4/28/2008 Plaza East Plaza East Chantilly, Virginia Chantilly, Virginia Project Overview Project Overview Green R oof Implementation Green R oof Implementation Analysis 1: Building Analysis 1: Building Envelope Envelope Top Floor Only Proposal: Use m oney saved from different façade to add a Green Roof to help with Energy Savings Analysis 2: Green Analysis 2: Green Existing Green Roof Roof Roof Implementation Implementation R-Value of 10 for Walls R-Value of 10 for Walls Som e Green Advantages R-Value of 18 to 19 for Roof R-Value of 30 for Roof Helps manage storm water – almost 1000 parking spots • Solar Absorption 0 .6 Solar Absorption 0 .2 • Reduce noise pollution Analysis 3: Analysis 3: Long life span from ultraviolent protection • Checking Green Checking Green • Creates habitat for birds and other animals Roof Loads Roof Loads Helps with the urban heat island effect • Research: Research: Implementation of Implementation of Software for Steel Software for Steel Buildings Buildings Q & A Q & A Steve Miller Steve Miller Construction Management Construction Management Plaza East Plaza East Chantilly, Virginia Chantilly, Virginia Project Overview Project Overview Green R oof Implementation Green R oof Implementation Analysis 1: Building Analysis 1: Building Envelope Envelope Energy Savings Years needed to m ake m oney back? Analysis 2: Green Analysis 2: Green Green Roof $442,000 ‐ $234,000 = $208,000 4.5 kBtu/ft 2 Heating Roof Roof Implementation Implementation 0.1 kBtu/ft 2 Cooling 0.2 kBtu/ft 2 Other Annual Energy Cost Savings does not apply 4.8 kBtu/ft 2 Total Analysis 3: Analysis 3: After 20 years build up roof needs replaced: Checking Green Checking Green Annual Energy Costs Savings were $0.003/ft 2 Roof Loads Roof Loads ($9/ft 2 )(26,000ft 2 )(2 nd roof) = $468,000 > $442,000 Cost of Existing Roof Cost of Green Roof $9 per ft 2 at 20 years life span $8 to $12 per ft 2 additional to existing price at 40 to 50 years life span Research: Research: Implementation of Implementation of Software for Steel $17/ft 2 x 26000 = $442,000 Software for Steel Green roof pays for itself after 20 years… Buildings Buildings $ 208,000 additional original cost …and lasts up to the next 20 to 30 years Q & A Q & A Steve Miller Steve Miller Construction Management Construction Management 4

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend