Planning Approaches Richard Castaneda Senior Project Scheduler - - PowerPoint PPT Presentation

planning approaches
SMART_READER_LITE
LIVE PREVIEW

Planning Approaches Richard Castaneda Senior Project Scheduler - - PowerPoint PPT Presentation

Integration of Multiple Planning Approaches Richard Castaneda Senior Project Scheduler Kenneth McBroom, PSP Director Planning and Scheduling 16 th LCI Congress | San Francisco, CA | October 7-10, 2014 Questions How does a Large


slide-1
SLIDE 1

16th LCI Congress | San Francisco, CA | October 7-10, 2014

Integration of Multiple Planning Approaches

Richard Castaneda Senior Project Scheduler Kenneth McBroom, PSP Director Planning and Scheduling

slide-2
SLIDE 2

16th LCI Congress | San Francisco, CA | October 7-10, 2014

Questions

  • How does a Large Construction Project Integrate Various and Very Different

Scheduling Approaches?

  • What if that project is a 100% Design / Build Project?
  • And it is Hospital?
  • On an Existing Fully Functioning Hospital Campus?
  • In California under the Authority of ?
slide-3
SLIDE 3

16th LCI Congress | San Francisco, CA | October 7-10, 2014

Prior to NWT Construction

North West Tower – Project Background

slide-4
SLIDE 4

16th LCI Congress | San Francisco, CA | October 7-10, 2014

North West Tower – Project Background

Prior to NWT Construction

slide-5
SLIDE 5

16th LCI Congress | San Francisco, CA | October 7-10, 2014

Schedule Data

  • Jan 2011 – Site Make Ready

North West Tower – Project Background

slide-6
SLIDE 6

16th LCI Congress | San Francisco, CA | October 7-10, 2014

Schedule Data

  • August 2011 – Demo of (e) Parking Garage

North West Tower – Project Background

slide-7
SLIDE 7

16th LCI Congress | San Francisco, CA | October 7-10, 2014

Schedule Data

  • May 2012 – Structural Steel for NWT

North West Tower – Project Background

slide-8
SLIDE 8

16th LCI Congress | San Francisco, CA | October 7-10, 2014

Schedule Data

  • August 2014 – Original Contract Completion

North West Tower – Project Background

slide-9
SLIDE 9

16th LCI Congress | San Francisco, CA | October 7-10, 2014

CPM – the What

  • Required by Contract; Used to Determine Key Milestone Dates
  • Approximately 6500 Activities
  • Resource Loaded
  • Not Cost Loaded
slide-10
SLIDE 10

16th LCI Congress | San Francisco, CA | October 7-10, 2014

Location Based Scheduling (LBS) – the Where

  • VICO was required by Contract
  • BIM Software
  • Utilizes Location Based

Scheduling

  • Utilizes 3D Model (DWG, SKP,

DWF)

slide-11
SLIDE 11

16th LCI Congress | San Francisco, CA | October 7-10, 2014

LBS Process Overview: Step 1

Location Breakdown Structure

Break the Project into Locations

  • Levels 1,2,4,5
  • West & East or

North & South ?

Location Based Scheduling

slide-12
SLIDE 12

16th LCI Congress | San Francisco, CA | October 7-10, 2014

LBS Process Overview: Step 2

Create Tasks that matched the CPM but based on Location

Location Based Scheduling

slide-13
SLIDE 13

16th LCI Congress | San Francisco, CA | October 7-10, 2014

Location (Floors) 5 10 15 20 25 30 35 Weeks 1st 2nd 3rd 4th 5th 6th

15 22 29 5 12 19 26 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 5 12 19 26 2 9 16 23 30 7 14 AUG SEP OCT NOV DEC JAN FEB MAR APR MAY 2011 2012

Continuous flow

  • Activities continuous

but start later

Start later when work can proceed continuously

Location Based Scheduling

slide-14
SLIDE 14

16th LCI Congress | San Francisco, CA | October 7-10, 2014

Location (Floors) Weeks

15 22 29 5 12 19 26 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 5 12 19 26 2 9 16 23 30 7 14 AUG SEP OCT NOV DEC JAN FEB MAR APR MAY 2011 2012

  • OH MEP
  • OH MEP
  • OH MEP
  • OH MEP
  • OH MEP
  • OH MEP

Task: Activities

Crew Flow

Flowline: graphical representation of movement of crews

  • ver time

3 weeks

1st 2nd 3rd 4th 5th 6th

5 10 15 20 25 30 35

Location Based Scheduling

slide-15
SLIDE 15

16th LCI Congress | San Francisco, CA | October 7-10, 2014

LBS Process Overview: Step 3

3D Based Quantities

Assign Quantities to the task from the Model

Location Based Scheduling

slide-16
SLIDE 16

16th LCI Congress | San Francisco, CA | October 7-10, 2014

LBS Process Overview: Step 4

Input the Production Rates and Crew Sizes for all the trades to Determine Durations

Location Based Scheduling

slide-17
SLIDE 17

16th LCI Congress | San Francisco, CA | October 7-10, 2014

Aligning the CPM Schedule in LBMS

2,432 Activities Converted into 372 Tasks

Location Based Scheduling

slide-18
SLIDE 18

16th LCI Congress | San Francisco, CA | October 7-10, 2014

Location Based Scheduling

Trade Stacking No Work Occurring

slide-19
SLIDE 19

16th LCI Congress | San Francisco, CA | October 7-10, 2014

Optimization

  • Used LBS to produce an Optimized Work flow for all trades
  • Had to revise the Baseline to Match the Dates in LBS
  • Tolerance = +/- 2 days

Location Based Scheduling

slide-20
SLIDE 20

16th LCI Congress | San Francisco, CA | October 7-10, 2014

Production Control – Weekly Updating

Location Based Scheduling

slide-21
SLIDE 21

16th LCI Congress | San Francisco, CA | October 7-10, 2014

  • Completion Report
  • Review Target Production & Actual Production

Location Based Scheduling Weekly - Input Quantity put in place

slide-22
SLIDE 22

16th LCI Congress | San Francisco, CA | October 7-10, 2014

Location Based Scheduling

Late start Complete Behind On-time

slide-23
SLIDE 23

16th LCI Congress | San Francisco, CA | October 7-10, 2014

Location Based Scheduling

slide-24
SLIDE 24

16th LCI Congress | San Francisco, CA | October 7-10, 2014

Control Action Plan (Note for Every Alarm)

Location Based Scheduling

slide-25
SLIDE 25

16th LCI Congress | San Francisco, CA | October 7-10, 2014

Pull Planning – the How

Last Planner System

slide-26
SLIDE 26

16th LCI Congress | San Francisco, CA | October 7-10, 2014

Last Planner System

slide-27
SLIDE 27

16th LCI Congress | San Francisco, CA | October 7-10, 2014

4D Scheduling – what it will look like

  • Utilizes CPM Scheduling
  • Compatible w/ Primavera P6
  • Utilizes 3D Model (DGN, DWG, SKP, DWF)
  • Creates 4D Animation
  • Show the status of the Project at any point in time

4D Scheduling

slide-28
SLIDE 28

16th LCI Congress | San Francisco, CA | October 7-10, 2014

4D Scheduling

CPM

LBS

slide-29
SLIDE 29

16th LCI Congress | San Francisco, CA | October 7-10, 2014

4D Development

  • Import Schedule & Model
  • Link Task with 3D Elements

4D Scheduling

  • Add Equipment
  • Generate 4D Animation
slide-30
SLIDE 30

16th LCI Congress | San Francisco, CA | October 7-10, 2014

Safety

4D Scheduling

  • Identify current site conditions
  • Identify high risk area (Path of travel for concrete trucks)
slide-31
SLIDE 31

16th LCI Congress | San Francisco, CA | October 7-10, 2014

4D Scheduling

Safety

  • Identify crane set-up / location
  • Identify danger area (Swing

Radius)

  • Blind Spots Created by the

Construction

slide-32
SLIDE 32

16th LCI Congress | San Francisco, CA | October 7-10, 2014

How does Link Piping (Piping from CUP to Tower) affect Deck Pours?

4D Scheduling

slide-33
SLIDE 33

16th LCI Congress | San Francisco, CA | October 7-10, 2014

4D Scheduling

slide-34
SLIDE 34

16th LCI Congress | San Francisco, CA | October 7-10, 2014

4D Scheduling

slide-35
SLIDE 35

16th LCI Congress | San Francisco, CA | October 7-10, 2014

  • Displays conflict with original logic
  • Avoided schedule & cost impacts (Approx. $105,000)

4D Scheduling

slide-36
SLIDE 36

16th LCI Congress | San Francisco, CA | October 7-10, 2014

  • Displays work that is complicated to describe in the schedule
  • Avoids confusion

4D Scheduling

Improved Communication

slide-37
SLIDE 37

16th LCI Congress | San Francisco, CA | October 7-10, 2014

  • Closed temp road

and opening of a new access road

  • Identified Potential

Problem with U/G Plumbing Pipe Delivery

4D Scheduling

Improved Communication

slide-38
SLIDE 38

16th LCI Congress | San Francisco, CA | October 7-10, 2014

  • Displays work to be performed
  • Displays equipment outside construction area
  • Identifies traffic control personal

4D Scheduling

Improved Communication – Owner (Disruption Notices)

slide-39
SLIDE 39

16th LCI Congress | San Francisco, CA | October 7-10, 2014

4D Scheduling

Improved Communication – Owner (Schedule Progress)

slide-40
SLIDE 40

16th LCI Congress | San Francisco, CA | October 7-10, 2014

North West Tower – Project Completion

slide-41
SLIDE 41

16th LCI Congress | San Francisco, CA | October 7-10, 2014

North West Tower – Project Background

slide-42
SLIDE 42

16th LCI Congress | San Francisco, CA | October 7-10, 2014

North West Tower – Project Completion

slide-43
SLIDE 43

16th LCI Congress | San Francisco, CA | October 7-10, 2014

North West Tower – Project Completion

slide-44
SLIDE 44

16th LCI Congress | San Francisco, CA | October 7-10, 2014

North West Tower – Project Completion

slide-45
SLIDE 45

16th LCI Congress | San Francisco, CA | October 7-10, 2014

North West Tower – Project Completion

slide-46
SLIDE 46

16th LCI Congress | San Francisco, CA | October 7-10, 2014

Integration

CPM – WHAT LBS – WHERE Pull Planning – HOW 4D – WHAT/WHEN

slide-47
SLIDE 47

16th LCI Congress | San Francisco, CA | October 7-10, 2014

CPM – P6 Schedule

CPM-the WHAT

Typically created in Push manner Provides planned work breakdown structure, with key milestones Created early in process

slide-48
SLIDE 48

16th LCI Congress | San Francisco, CA | October 7-10, 2014

CPM – P6 Schedule

LBS-the WHERE

Helped Create a Better Master Plan Identified in P6 where Remaining Durations should be Modified to account for real world production Provides “should start” dates rather than CPM early start or late start dates Ensures continuous work between locations Identified bottle necks & inefficiencies

slide-49
SLIDE 49

16th LCI Congress | San Francisco, CA | October 7-10, 2014

CPM – P6 Schedule Pull Planning Used CPM Milestones to Create 3 to 6 Week Detailed Schedules Actuals in P6 would Reflect the Promises Kept by the Trades Communication – Trades; Last Planners of the Work Flushed Out Field Conflicts and Issues Prior to starting the work Create Daily Measurable Detailed Tasks and then held the Trades accountable

PULL – the HOW

slide-50
SLIDE 50

16th LCI Congress | San Francisco, CA | October 7-10, 2014

CPM – P6 Schedule P6 Schedule Imported to Create 3D Project Animation 3D conflicts led to Logic changes in the CPM Communication – Master Plan with the Hospital and Trades

4D – the WHAT / WHEN

Displayed actual field conditions for better planning Allowed for what-if scenarios

slide-51
SLIDE 51

16th LCI Congress | San Francisco, CA | October 7-10, 2014

= 4 Months Ahead of Schedule; April 1, 2014

Pull Planning CPM – P6 Schedule

slide-52
SLIDE 52

16th LCI Congress | San Francisco, CA | October 7-10, 2014

Resources

Ken McBroom, PSP Director Planning & Scheduling McCarthy Building Companies, Inc. Southern California Division kmcbroom@mccarthy.com Richard Castaneda

  • Sr. Project Scheduler

McCarthy Building Companies, Inc. rcastaneda@mccarthy.com