planning approaches
play

Planning Approaches Richard Castaneda Senior Project Scheduler - PowerPoint PPT Presentation

Integration of Multiple Planning Approaches Richard Castaneda Senior Project Scheduler Kenneth McBroom, PSP Director Planning and Scheduling 16 th LCI Congress | San Francisco, CA | October 7-10, 2014 Questions How does a Large


  1. Integration of Multiple Planning Approaches Richard Castaneda Senior Project Scheduler Kenneth McBroom, PSP Director Planning and Scheduling 16 th LCI Congress | San Francisco, CA | October 7-10, 2014

  2. Questions • How does a Large Construction Project Integrate Various and Very Different Scheduling Approaches? • What if that project is a 100% Design / Build Project? • And it is Hospital? • On an Existing Fully Functioning Hospital Campus? • In California under the Authority of ? 16 th LCI Congress | San Francisco, CA | October 7-10, 2014

  3. North West Tower – Project Background Prior to NWT Construction 16 th LCI Congress | San Francisco, CA | October 7-10, 2014

  4. North West Tower – Project Background Prior to NWT Construction 16 th LCI Congress | San Francisco, CA | October 7-10, 2014

  5. North West Tower – Project Background Schedule Data • Jan 2011 – Site Make Ready 16 th LCI Congress | San Francisco, CA | October 7-10, 2014

  6. North West Tower – Project Background Schedule Data • August 2011 – Demo of (e) Parking Garage 16 th LCI Congress | San Francisco, CA | October 7-10, 2014

  7. North West Tower – Project Background Schedule Data • May 2012 – Structural Steel for NWT 16 th LCI Congress | San Francisco, CA | October 7-10, 2014

  8. North West Tower – Project Background Schedule Data • August 2014 – Original Contract Completion 16 th LCI Congress | San Francisco, CA | October 7-10, 2014

  9. CPM – the What • Required by Contract; Used to Determine Key Milestone Dates • Approximately 6500 Activities • Resource Loaded • Not Cost Loaded 16 th LCI Congress | San Francisco, CA | October 7-10, 2014

  10. Location Based Scheduling (LBS) – the Where • VICO was required by Contract • BIM Software - Utilizes Location Based Scheduling - Utilizes 3D Model (DWG, SKP, DWF) 16 th LCI Congress | San Francisco, CA | October 7-10, 2014

  11. Location Based Scheduling LBS Process Overview: Step 1 Break the Project into Locations • Levels 1,2,4,5 • West & East or North & South ? Location Breakdown Structure 16 th LCI Congress | San Francisco, CA | October 7-10, 2014

  12. Location Based Scheduling LBS Process Overview: Step 2 Create Tasks that matched the CPM but based on Location 16 th LCI Congress | San Francisco, CA | October 7-10, 2014

  13. Location Based Scheduling 2011 2012 AUG SEP OCT NOV DEC JAN FEB MAR APR MAY 15 22 29 5 12 19 26 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 5 12 19 26 2 9 16 23 30 7 14 6 th 5 th Location (Floors) 4 th Continuous flow • Activities continuous 3 rd but start later 2 nd 1 st 5 10 15 20 25 30 35 Weeks Start later when work can proceed continuously 16 th LCI Congress | San Francisco, CA | October 7-10, 2014

  14. Location Based Scheduling 2011 2012 AUG SEP OCT NOV DEC JAN FEB MAR APR MAY 15 22 29 5 12 19 26 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 5 12 19 26 2 9 16 23 30 7 14 6 th - OH MEP 5 th Location (Floors) - OH MEP 4 th Task: Activities - OH MEP 3 rd - OH MEP 2 nd - OH MEP Crew Flow 1 st - OH MEP 5 10 15 20 25 30 35 3 weeks Weeks Flowline: graphical representation of movement of crews over time 16 th LCI Congress | San Francisco, CA | October 7-10, 2014

  15. Location Based Scheduling LBS Process Overview: Step 3 Assign Quantities to the task from the Model 3D Based Quantities 16 th LCI Congress | San Francisco, CA | October 7-10, 2014

  16. Location Based Scheduling LBS Process Overview: Step 4 Input the Production Rates and Crew Sizes for all the trades to Determine Durations 16 th LCI Congress | San Francisco, CA | October 7-10, 2014

  17. Location Based Scheduling Aligning the CPM Schedule in LBMS 2,432 Activities Converted into 372 Tasks 16 th LCI Congress | San Francisco, CA | October 7-10, 2014

  18. Location Based Scheduling No Work Occurring Trade Stacking 16 th LCI Congress | San Francisco, CA | October 7-10, 2014

  19. Location Based Scheduling Optimization  Used LBS to produce an Optimized Work flow for all trades  Had to revise the Baseline to Match the Dates in LBS  Tolerance = +/- 2 days 16 th LCI Congress | San Francisco, CA | October 7-10, 2014

  20. Location Based Scheduling Production Control – Weekly Updating 16 th LCI Congress | San Francisco, CA | October 7-10, 2014

  21. Location Based Scheduling Weekly - Input Quantity put in place - Completion Report - Review Target Production & Actual Production 16 th LCI Congress | San Francisco, CA | October 7-10, 2014

  22. Location Based Scheduling Late start Behind On-time Complete 16 th LCI Congress | San Francisco, CA | October 7-10, 2014

  23. Location Based Scheduling 16 th LCI Congress | San Francisco, CA | October 7-10, 2014

  24. Location Based Scheduling Control Action Plan (Note for Every Alarm) 16 th LCI Congress | San Francisco, CA | October 7-10, 2014

  25. Last Planner System Pull Planning – the How 16 th LCI Congress | San Francisco, CA | October 7-10, 2014

  26. Last Planner System 16 th LCI Congress | San Francisco, CA | October 7-10, 2014

  27. 4D Scheduling 4D Scheduling – what it will look like • Utilizes CPM Scheduling • Compatible w/ Primavera P6 • Utilizes 3D Model (DGN, DWG, SKP, DWF) • Creates 4D Animation • Show the status of the Project at any point in time 16 th LCI Congress | San Francisco, CA | October 7-10, 2014

  28. 4D Scheduling CPM LBS 16 th LCI Congress | San Francisco, CA | October 7-10, 2014

  29. 4D Scheduling 4D Development - Import Schedule & Model - Link Task with 3D Elements - Add Equipment - Generate 4D Animation 16 th LCI Congress | San Francisco, CA | October 7-10, 2014

  30. 4D Scheduling Safety - Identify current site conditions - Identify high risk area (Path of travel for concrete trucks) 16 th LCI Congress | San Francisco, CA | October 7-10, 2014

  31. 4D Scheduling Safety - Identify crane set-up / location - Identify danger area (Swing Radius) - Blind Spots Created by the Construction 16 th LCI Congress | San Francisco, CA | October 7-10, 2014

  32. 4D Scheduling How does Link Piping (Piping from CUP to Tower) affect Deck Pours? 16 th LCI Congress | San Francisco, CA | October 7-10, 2014

  33. 4D Scheduling 16 th LCI Congress | San Francisco, CA | October 7-10, 2014

  34. 4D Scheduling 16 th LCI Congress | San Francisco, CA | October 7-10, 2014

  35. 4D Scheduling - Displays conflict with original logic - Avoided schedule & cost impacts (Approx. $105,000) 16 th LCI Congress | San Francisco, CA | October 7-10, 2014

  36. 4D Scheduling Improved Communication - Displays work that is complicated to describe in the schedule - Avoids confusion 16 th LCI Congress | San Francisco, CA | October 7-10, 2014

  37. 4D Scheduling Improved Communication - Closed temp road and opening of a new access road - Identified Potential Problem with U/G Plumbing Pipe Delivery 16 th LCI Congress | San Francisco, CA | October 7-10, 2014

  38. 4D Scheduling Improved Communication – Owner (Disruption Notices) - Displays work to be performed - Displays equipment outside construction area - Identifies traffic control personal 16 th LCI Congress | San Francisco, CA | October 7-10, 2014

  39. 4D Scheduling Improved Communication – Owner (Schedule Progress) 16 th LCI Congress | San Francisco, CA | October 7-10, 2014

  40. North West Tower – Project Completion 16 th LCI Congress | San Francisco, CA | October 7-10, 2014

  41. North West Tower – Project Background 16 th LCI Congress | San Francisco, CA | October 7-10, 2014

  42. North West Tower – Project Completion 16 th LCI Congress | San Francisco, CA | October 7-10, 2014

  43. North West Tower – Project Completion 16 th LCI Congress | San Francisco, CA | October 7-10, 2014

  44. North West Tower – Project Completion 16 th LCI Congress | San Francisco, CA | October 7-10, 2014

  45. North West Tower – Project Completion 16 th LCI Congress | San Francisco, CA | October 7-10, 2014

  46. Integration 4D – WHAT/WHEN CPM – WHAT Pull Planning – HOW LBS – WHERE 16 th LCI Congress | San Francisco, CA | October 7-10, 2014

  47. CPM-the WHAT Provides planned work breakdown structure, with key milestones Typically created in Push manner Created early in process CPM – P6 Schedule 16 th LCI Congress | San Francisco, CA | October 7-10, 2014

  48. LBS-the WHERE Identified in P6 where Remaining Durations should be Modified to account for real world production Helped Create a Better Master Plan Provides “should start” dates rather than CPM – P6 Schedule CPM early start or late start dates Ensures continuous work between locations Identified bottle necks & inefficiencies 16 th LCI Congress | San Francisco, CA | October 7-10, 2014

  49. PULL – the HOW Communication – Trades; Last Planners of the Work Create Daily Measurable Detailed Used CPM Milestones to Tasks and then held the Trades Create 3 to 6 Week Detailed accountable Schedules CPM – P6 Schedule Actuals in P6 would Reflect the Promises Kept by the Trades Flushed Out Field Conflicts Pull Planning and Issues Prior to starting the work 16 th LCI Congress | San Francisco, CA | October 7-10, 2014

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend