Pitstone to Tring Cycle Route 12 March 2020 Andrew Freeman Kristen - - PowerPoint PPT Presentation

pitstone to tring cycle route
SMART_READER_LITE
LIVE PREVIEW

Pitstone to Tring Cycle Route 12 March 2020 Andrew Freeman Kristen - - PowerPoint PPT Presentation

Pitstone to Tring Cycle Route 12 March 2020 Andrew Freeman Kristen Ferma Strategy & Programme Manager Engineer www.hertfordshire.gov.uk www.hertfordshire.gov.uk Background & Introduction 1. 100k S106 contribution handed from Bucks


slide-1
SLIDE 1

www.hertfordshire.gov.uk www.hertfordshire.gov.uk

Pitstone to Tring Cycle Route

Andrew Freeman Kristen Ferma

Strategy & Programme Manager Engineer 12 March 2020

slide-2
SLIDE 2

www.hertfordshire.gov.uk

  • 1. £100k S106 contribution handed from Bucks

CC to Herts “for the provision of a cycle footway link from the roundabout on B488 Tring Station”

  • 2. Refund date 10/06/2024
  • 3. Feasibility work commenced in 2015
  • 4. Meeting with Parish, Bucks CC & cycle groups

2018

Background & Introduction

slide-3
SLIDE 3

www.hertfordshire.gov.uk

Scheme extents

slide-4
SLIDE 4

www.hertfordshire.gov.uk

  • The aim of the audit is to

breakdown the existing network into a set of cycle performance levels in order to determine the shortfalls in cycle facility provision.

  • Bikeability levels for Northfield

road is level 3.

Bikeability Cycle Audit (2013)

slide-5
SLIDE 5

www.hertfordshire.gov.uk

Bikeability levels

slide-6
SLIDE 6

www.hertfordshire.gov.uk

  • Five options:
  • 1. Shared footway and Cycleway off carriageway
  • 2. Cycle lanes on carriageway
  • 3. Signed cycle route on carriageway
  • 4. Cycle route utilising existing rights of way
  • 5. Do nothing
  • Option 1 was preferred as it will provide a more direct route that is

visible to others highway users and more appeal to end users.

  • Option 1 will require purchasing of private land
  • Option 1 will cost in the region of £1,284,000 + VAT

Technical Feasibility Study (2015)

slide-7
SLIDE 7

www.hertfordshire.gov.uk

Options

slide-8
SLIDE 8

www.hertfordshire.gov.uk

Speed & Volume Traffic Data

Volume: ~ 5500 vehicles

Highest Mean Avg (7days): 44 Highest Mean Avg (7days): 49 Highest Mean Avg (7days): 30

slide-9
SLIDE 9

www.hertfordshire.gov.uk

Cycle Design – Sustrans Guidance

slide-10
SLIDE 10

www.hertfordshire.gov.uk

Highway Boundary

slide-11
SLIDE 11

www.hertfordshire.gov.uk

Bikeability Audit option 1

slide-12
SLIDE 12

www.hertfordshire.gov.uk

Alternative Route

slide-13
SLIDE 13

www.hertfordshire.gov.uk

  • Presented option along Marshcroft Lane/towpath, which we heard

would not be used and shouldn’t be pursued.

  • Reduction in speed along the Northfield Road was brought up but

due to it not meeting the Speed management strategy it cannot be implemented along the route.

  • Low cost carriageway marking.
  • Possible survey to be produced for demands for cycle improvement
  • n the area and near Tring station.
  • Attendees suggested vegetation clearance for improved visibility.

Meeting with Parish Council – July 2018

slide-14
SLIDE 14

www.hertfordshire.gov.uk

  • Vegetation clearance before/after photos

Vegetation Clearance

slide-15
SLIDE 15

www.hertfordshire.gov.uk

Drawing 1

slide-16
SLIDE 16

www.hertfordshire.gov.uk

  • To reduce the speed limit the proposal should be

assessed against the HCC Speed Management

  • Strategy. It is unlikely to happen given the profile of the

road but if so, reduction may only be to 50mph.

  • Both side of Northfield Road is densely vegetated.
  • The amount of light is restricted on Northfield Road

between Upper Icknield Way & Marshcroft Lane due to the dense vegetation.

Road Safety Audit

slide-17
SLIDE 17

www.hertfordshire.gov.uk

  • In addition to civil design, cycle route would

require: – Drainage design – Lighting design – Signage design

Additional design required

slide-18
SLIDE 18

www.hertfordshire.gov.uk

  • Physical interventions for speed reduction,

ARUP landscape architect

  • \\Hertscc.gov.uk\Shared3\HERTFORD\HIGHWA

YS\CST\G-I0000\G-I1500\G-I1503\G- I1503.5X\Scan - sketch of physical and visual interventions.pdf

Physical interventions for speed reduction, ARUP landscape architect

slide-19
SLIDE 19

www.hertfordshire.gov.uk

Drawing 2

slide-20
SLIDE 20

www.hertfordshire.gov.uk

  • Further investigation work?
  • Funding opportunities
  • Options for remainder of s106 funding

– Towpath/community bus/cycle facilities at station/gateway features

  • Dialogue with Bucks CC

Discussion & next steps

slide-21
SLIDE 21

www.hertfordshire.gov.uk www.hertfordshire.gov.uk

Thank you

slide-22
SLIDE 22

www.hertfordshire.gov.uk