Photon Detector Consor-um Weekly Mee-ng January 15, 2019 Dave - - PowerPoint PPT Presentation
Photon Detector Consor-um Weekly Mee-ng January 15, 2019 Dave - - PowerPoint PPT Presentation
Photon Detector Consor-um Weekly Mee-ng January 15, 2019 Dave Warner Outline APA ground screen connec-ons Integra-on/installa-on discussions Implica-ons for PD produc-on Upcoming Technical Milestones Mesh Panel Fixing (4
Outline
- APA ground screen connec-ons
- Integra-on/installa-on discussions
- Implica-ons for PD produc-on
- Upcoming Technical Milestones
Mesh Panel Fixing (4” Frame)
Head end L/H + R/H (2 off of each) 5 panel types Foot end L/H + R/H (2 off of each) Centre panels all iden-cal (12 off)
Fixing bracket loca-ons. Fixing bracket loca-ons. LiV plates and nut plate widths reduced to 79.5mm
Sec-on Through Outer Tube
Mesh frame fixing
- bracket. 1.6mm stainless
- steel. Very low profile to
allow passage of cables. Nut plates, not used for mesh frame fixing, they are part of the APA frame design. They are ½” thick Mesh frame 20mm x 10mm x 1.5mm 8.3mm
Dimension from top of the nut plates to the top surface of the mesh frame.
View of PD cable rou-ng without mesh window View of PD cable rou-ng with mesh window
PD Cable rou,ng along the APA side tube
Side tube Rib Foot tube Bundle of 5 x 6.75mm diameter PD cables
PD Integra-on
- ITF (APA horizontal)?
– In Rapid City? – At SURF?
- “Underground ITF”
– In SAS or cleanroom between detector caverns (APA possibly ver-cal like ProtoDUNE) – In cavern 2 during detector 1 assembly, not clear what happens for second SP detector
PD Module Fabrica-on & Integra-on
- Current plan calls for first produc-on PDs arriving
(and integra-on beginning at ITF) in early 2022
- Probably need to consider PD produc-on
beginning mid 2021.
- N.B.: Some number of final-design PDs will be
needed early for PD/APA installa-on tests
- Assume 2 APAs per week
- 20 PDs per week
- 18 months per FD cryostat
PD Cables/Connectors
- APA frame construc-on will begin January
2021
- PD cables and connectors will need to begin
fabrica-on in mid-2020
- Cable tes-ng/cer-fica-on is clearly a cri-cal
path item for the PD consor-um
– Beginning at CSU – Supported in ICEBERG, other sites
Interface Documents
- Two important workshops associated with upcoming
collabora-on mee-ng:
- Integra-on/Installa-on Workshop: Jan 24-25 @ CERN
- Compu-ng & SoVware Interfaces Workshop: Jan 30 @
CERN
- Coming out of these workshops, we will need to
update our interface documents and place them under signature control
- Process needs to be completed on -me scale of final TDR
submission
Sub-system Cost Estimates
- I have been promising an example that we
can use as a template to help “standardize”
- ur cost estimates for the next round of
review
- Hoped to have this ready for today, but it will require
another week to finalize
- The required time scale for updated cost
estimates is end-of-February
- NCG will ini-ate next round of review aVer the RRB
mee-ng in March
Schedule
- Big question is how to converge on updated
dates for the start of installation of the first two far detectors
- LBNF is expected to converge on dates as part of its reconcilia-on
- f the 90% final conven-onal facili-es designs in April/May
- We expect to have a discussion at the upcoming collabora-on
mee-ng on how we will handle this issue in the TDR
- In the meantime, will continue to work with
consortia individually on further developing the global schedule
Reviews
- Need to schedule design reviews for each sub-
system between now and July TDR submission date
- Currently,
- CE Mechanicals: Feb 11-12 @ BNL
- APA: March 27-28 @ PSL (TBC)
- Engineering team has been developing safety
review requirements in context of APA review – will iterate with each consortia on its requirements
- PD 60% review likely to occur in May 2019!!!