Perth Transport Future Project Phase 2 -Cross Tay Link Road CIHT - - PowerPoint PPT Presentation

perth transport future project phase 2 cross tay link road
SMART_READER_LITE
LIVE PREVIEW

Perth Transport Future Project Phase 2 -Cross Tay Link Road CIHT - - PowerPoint PPT Presentation

Perth Transport Future Project Phase 2 -Cross Tay Link Road CIHT Presentation 25 February 2020 AK Bell Library ROSS FLETCHER SENIOR ENGINEER ROADS INFRASTRUCTURE (PLANNING & DEVELOPMENT) Introduction Welcome Housekeeping


slide-1
SLIDE 1

Perth Transport Future Project Phase 2 -Cross Tay Link Road

CIHT Presentation 25 February 2020 – AK Bell Library

ROSS FLETCHER SENIOR ENGINEER – ROADS INFRASTRUCTURE (PLANNING & DEVELOPMENT)

slide-2
SLIDE 2

Introduction

 Welcome  Housekeeping  Ross Fletcher – Background to Perth Transport Futures

Project & Cross Tay Link Road

 Denise Ritchie – Design of Cross Tay Link Road  Emma Cooper – EIA & Planning Application for the

Cross Tay Link Road

 Ross Fletcher – Procurement & Next Steps

slide-3
SLIDE 3

Roads Infrastructure Team

 Small client team of 5  Set up in 2013/14  Situated within Planning & Development (Corporate & Democratic

Services)

 Work closely with Transport Planning colleagues who progress proposed

large roads schemes to end of DMRB Stage 2

 Once there is a Business Case and Budget for a scheme it is handed to

the Roads Infrastructure Team

 We manage the delivery phase which generally consists of site

investigations, design through to DMRB Stage 3, land purchase, planning process and construction.

 We rely on support from colleagues in Legal, Planning, Estates, Finance

and many others. Also rely on external support from consultants, DVS, Legal Advisors etc.

slide-4
SLIDE 4

Perth Transport Futures Project

 Strategic Rationale

 Perth – major strategic hub  Delivery of sustainable growth in the Tay Cities region  Support the Northwest expansion of Perth as envisaged

in the Local Development Plan (new LDP recently launched)

 Perth – AQMA. High priority given current climate crisis.  Ambitious City Plan

 Integrated Series of Measures over Four Phases

 Phase 1 – A9/A85 scheme (complete)  Phase 2 – CTLR  Phase 3 – Bertha Park connection  Phase 4 – City centre improvements (including greener

travel – Perth, People, Place with SUSTRANS)

slide-5
SLIDE 5

Phase 1 – A9/A85 Scheme

 Commenced on-site September 2016  Designer – CH2M  Contractor – Balfour Beatty  Complete May 2019 (roads opened

January 2019 – 3 months early)

 Benefits / Features

 New grade separated junction on A9  Link road to Bertha Park development

(including new school)

 New access to industrial estate  Relieve pressure on Inveralmond

Roundabout and Crieff Road corridor

slide-6
SLIDE 6

Phase 1 – A9/A85 Scheme

 NEC3 Option A Contract (Scape Procure)  £37.9m final cost (within 7% of initial price)  Collaborative approach  Significant Community Benefits Programme  Social Value of £12.9 or £0.42 per £1 spent  Recognised for collaborative approach  Various Awards including:

 NEC Contract of the Year 2019  CECA Community Award 2019  National Social Value Award 2018

 End of Project Review – Lessons learned

fed into CTLR strategies

slide-7
SLIDE 7

AIMS OF THE CROSS TAY LINK ROAD

Reduced congestion and improved air quality in the city centre and Bridgend

Enable new, planned and committed developments – sustainable economic growth

Enable city centre improvements including a move towards greener travel

Connecting communities and improving access to Scone Palace and Perth Racecourse for events

Phase 2 - Cross Tay Link Road

MAIN FEATURES OF THE CROSS TAY LINK ROAD

New crossing of River Tay north of Perth

New grade separated junction between Inveralmond Roundabout and Luncarty

New link road from the A9 to the A94 (with roundabouts on Stormontfield Road, A93 and Highfield Track)

Active travel route for full length of new road

slide-8
SLIDE 8

LOCAL DEVELOPMENT PLAN 2

Phase 2 - Cross Tay Link Road

slide-9
SLIDE 9

Phase 2 - Cross Tay Link Road

Reduction in traffic congestion – modelling by SYSTRA / Transport Planning – air quality improvement evident as shown

slide-10
SLIDE 10

SCHEME TIMELINE

2010 to 2016 Technical Assessment (DMRB – Stages 1 & 2 complete)

June 2016 – Council commits Capital funding of £78 million

December 2016 - Council approved the Preferred Route

Early 2017 – Scheme passed to Roads Infrastructure Team for delivery

Early 2017 to Present - liaison with land owners (ongoing_

July 2017 - SWECO appointed as designers (for specimen design)

July 2017 to Present - consultation with statutory bodies / environmental groups (ongoing)

Early 2018 to mid 2019 Site Investigations / Surveys

Phase 2 - Cross Tay Link Road

slide-11
SLIDE 11

SCHEME TIMELINE

April 2018 to January 2019 Early Contractor Involvement (Balfour Beatty)

Summer 2018 – First Public Consultations

December 2018 – First draft of Specimen Design completed

January 2019 – Scottish Government commits £40 million to project

February to June 2019 – Alignment review between A93 and A94 (caused a six month delay)

Summer 2019 – Final round of public consultations in advance of planning application

Phase 2 - Cross Tay Link Road

slide-12
SLIDE 12

SCHEME TIMELINE

September 2019 – Design layout finalised for planning application and land purchase

September 2019 – Council approval to proceed with Compulsory Purchase of land required

Compulsory Purchase Order made on 30 October 2019 (with Scottish Ministers)

Planning Application (including EIA) submitted in November 2019 (decision expected by April 2020)

Phase 2 - Cross Tay Link Road

slide-13
SLIDE 13

CROSS TAY LINK ROAD

CIHT PRESENTATION – SWECO

25 FEBRUARY 2020 DENISE RITCHIE EMMA COOPER

2020-03-03 13

slide-14
SLIDE 14

CROSS TAY LINK ROAD SWECO – Stage 3 Input

  • Scheme Overview and Key Infrastructure
  • Site Investigations
  • Constraints
  • Current Specimen Design Status
  • Stakeholders and Landowners
  • Environmental Impact Assessment and Planning
  • Project Risks
  • Bulk Quantities

2020-03-03 14

slide-15
SLIDE 15

CROSS TAY LINK ROAD SCHEME OVERVIEW

2020-03-03 15

slide-16
SLIDE 16

CROSS TAY LINK ROAD SCHEME OVERVIEW (PART 1 of 4)

2020-03-03 16

slide-17
SLIDE 17

CROSS TAY LINK ROAD SCHEME OVERVIEW PART 2 of 4

2020-03-03 GENDIATUR, QUE REIUNT EXPLABO. UT ASINCTIIS DE VOLLACCAB ISUNT ET EOS QUATIANDANDI DELLECU LLUPTIIST 17

slide-18
SLIDE 18

CROSS TAY LINK ROAD SCHEME OVERVIEW PART 3 of 4

2020-03-03 18

slide-19
SLIDE 19

CROSS TAY LINK ROAD SCHEME OVERVIEW PART 4 of 4

2020-03-03 GENDIATUR, QUE REIUNT EXPLABO. UT ASINCTIIS DE VOLLACCAB ISUNT ET EOS QUATIANDANDI DELLECU LLUPTIIST 19

slide-20
SLIDE 20

CROSS TAY LINK ROAD KEY INFRASTRUCTURE – A9 JUNCTION

2020-03-03 20

  • Agreed design
  • Loop arrangement

is compact

  • Future proofed
slide-21
SLIDE 21

CROSS TAY LINK ROAD KEY INFRASTRUCTURE – A9 OVERBRIDGE

2020-03-03 21

  • Structural form
  • Aesthetics
  • Piled foundations
slide-22
SLIDE 22

CROSS TAY LINK ROAD KEY INFRASTRUCTURE – RIVER TAY CROSSING

2020-03-03 22

  • Structural form
  • Clearances and temporary works
  • Fishing rights, and
  • Access options to the western pier
slide-23
SLIDE 23

CROSS TAY LINK ROAD KEY INFRASTRUCTURE – CTLR ROAD CROSS SECTION

2020-03-03 23

  • single carriageway
  • 85kph design speed
  • Segregated cycleway, and
  • Grass verges and separation strip.
slide-24
SLIDE 24

CROSS TAY LINK ROAD KEY INFRASTRUCTURE – JUNCTIONS

2020-03-03 24

Stormontfield Road Roundabout

A94 Roundabout

A93 Roundabout

slide-25
SLIDE 25

CROSS TAY LINK ROAD KEY INFRASTRUCTURE – HIGHFIELD GREEN BRIDGE

2020-03-03 25

  • Buried precast

concrete arch

  • Aesthetics
  • Connects NMU

infrastructure, and

  • Provides ecological

and landscape connectivity.

slide-26
SLIDE 26

CROSS TAY LINK ROAD KEY INFRASTRUCTURE – LANDSCAPE

2020-03-03 26

  • High quality

landscape

  • Wetland area, and
  • Park and cycle

facility

slide-27
SLIDE 27

CROSS TAY LINK ROAD SITE INVESTIGATIONS

The following were completed early in Stage 3:

  • Ecological surveys
  • Tree surveys;
  • Topographical, bathymetric and drainage surveys;
  • NMU CCTV surveys;
  • Ground investigation in 2018; and
  • Intrusive archaeological investigations (trial trenching and geophysical surveys) in early 2019

2020-03-03 27

slide-28
SLIDE 28

CROSS TAY LINK ROAD SITE INVESTIGATIONS

  • A9 Ground Conditions

– A9 Mainline south - raised tidal flat deposits and alluvium; – Broxy Wood is a drumlin of glacial till; – Grade separated junction - raised marine deposits; and – North of Broxy Kennels - glacial deposits.

  • CTLR Ground Conditions

– Marine deposits and alluvium to Balboughty Farm. Tay Crossing Bridge piles estimated at 40m to 55m in length; and – Glacial deposits with shallow bedrock beyond Balboughty Farm .

2020-03-03 28

slide-29
SLIDE 29

CROSS TAY LINK ROAD CONSTRAINTS

2020-03-03 29

slide-30
SLIDE 30

CROSS TAY LINK ROAD SPECIMEN DESIGN STATUS

2020-03-03 30

  • Specimen Design concluded
  • Stage 1 Road Safety Audit
  • Final Stage 3 Cost Estimate
  • Stage 3 Report
  • (Draft) CAR licenses
slide-31
SLIDE 31

CROSS TAY LINK ROAD STAKEHOLDERS AND LANDOWNERS

2020-03-03 31

  • Consultations with key stakeholders, including:

– Transport Scotland (and BEAR); – Network Rail; – HES, SNH and SF; – SEPA; and – Public Utilities.

  • PKC meetings with landowners/developers with:

– Mansfield Estate; – AJ Stephen; – Ritchie; and – I&H Brown.

  • Early public consultation events / ongoing engagement
slide-32
SLIDE 32

CROSS TAY LINK ROAD ENVIRONMENTAL IMPACT ASSESSMENT

2020-03-03 32

  • Background
  • Key features
  • Air Quality
  • Active travel
  • Climate change
  • Biodiversity
  • Environmental Enhancement
slide-33
SLIDE 33

CROSS TAY LINK ROAD ENVIRONMENTAL IMPACT ASSESSMENT

  • Cumulative Assessment
  • Overall Environmental Effects
  • Schedule of Mitigation

2020-03-03 33

A copy of the EIAR is available on the CTLR website and on the Perth and Kinross Council planning portal: https://planningapps.pkc.gov.uk/online-applications/search.do?action=simple&searchType=Application

  • Ref. No: 19/01837/FLM
slide-34
SLIDE 34

CROSS TAY LINK ROAD PLANNING

2020-03-03 34

  • Proposal of Application Notice

(PAN)

– 10th July 2019

  • Pre-application consultation

– Public events – Landowners, statutory consultees, elected members

  • Planning Application

– Pre-validation – Final submission on 15th November 2019 – Responses

The planning application can be found on Perth and Kinross Council’s online planning portal at: https://planningapps.pkc.gov.uk/online-applications/search.do?action=simple&searchType=Application

  • Ref. No: 19/01837/FLM
slide-35
SLIDE 35

CROSS TAY LINK ROAD PROJECT RISKS

2020-03-03 35

  • Management of stakeholders
  • Ground conditions
  • Ecology, seasonal constraints
  • Existing roads
  • Perth to Inverness railway
  • Unknown archaeology
  • Agricultural drainage
  • Public utilities
  • Associated development
slide-36
SLIDE 36

CROSS TAY LINK ROAD PROJECT RISKS

2020-03-03 36

  • Access to Tay Crossing

bridge – west pier

– Option 1 – access from the south via a temporary bridge over the River Almond; – Option 2 – access from the west

  • ver and under the Perth to

Inverness railway; and – Option 3 – access from the north via the existing Luncarty junction.

slide-37
SLIDE 37

CROSS TAY LINK ROAD BULK QUANTITIES

2020-03-03 37

DMRB Series Location Item Quantity 400 Road Restraints Scheme wide N2 barrier 4,700m 500 Drainage Scheme wide Filter Drains 24,000m 500 Drainage Scheme wide Carrier Drains 3,900m 600 Earthworks A9 section Cut 609,500m³ 600 Earthworks A9 section Fill (inc landscaping) 700,500m³ 600 Earthworks CTLR section Cut 220,500m³ 600 Earthworks CTLR section Fill (inc landscaping) 257,900m³ 700 Pavement Scheme wide Area of Surface Course 175,000m² 1700 Structures Scheme wide Principal Structures 3 No. 1700 Structures Scheme wide RC Box Culverts 4 No. 1700 Structures Scheme wide VMS Foundations 1 No.

slide-38
SLIDE 38

Phase 2 - Cross Tay Link Road

PROCUREMENT / CONTRACT

 Market engagement days in March 2019 – positive feedback / interest

from the market

 Presentation  Questionnaires  Interviews

 Regular scheme updates provided to the market  Procurement strategy approved by project board October 2019

 Two stage competitive procedure  Design and build NEC4 contract  Target cost (option C)  Option X22 used: One year period of early contractor involvement in advance of main construction

slide-39
SLIDE 39

Phase 2 - Cross Tay Link Road

PROCUREMENT / CONTRACT

 PIN notice published 9 January 2020

 Draft One of Contract Data attached – feedback received

 ESPD (PQQ) published 17 February 2020 for return by 23 March 2020

 Draft Two of Contract Data attached – awaiting feedback

 ITT to be issued to successful bidders in April 2020

 Intention to have list of four bidders for second stage

slide-40
SLIDE 40

Phase 2 - Cross Tay Link Road

EARLY CONTRACTOR INVOLVEMENT

 Important to the success of the project. Lessons learned from Phase 1.  Benefits of a successful period of ECI:

 Ensure everyone fully understands objectives of the scheme prior to main works starting  Carry out enabling works to de-risk the programme  Able to fully discuss and fairly apportion risks before main works starting  Period of time for contractor to scrutinise specimen design and employers requirements and

recommend changes

 Changes in ECI period much cheaper than being reactive during main works  More time to deal with seasonal environmental constraints  More time to plan for meaningful community benefits

slide-41
SLIDE 41

Phase 2 - Cross Tay Link Road

COMMUNITY BENEFITS

 Strategy being developed to include in the contract:

 Involving local communities in the project  Helping local communities  Assisting local charities and organisations  Inspiring the next generation of engineers  Getting local unemployed people back to work  Looking after our local and the wider environment  Ensuring maximum local spend  Caring for and developing the local workforce

 We want to build on the award winning work on Phase 1 and push for

even more community benefit in phase 2

slide-42
SLIDE 42

Phase 2 - Cross Tay Link Road

CHALLENGES FACED:

 Environmentally sensitive landscape  Consultation with numerous statutory bodies  Access to the west bank of the River Tay – Scheduled Monument

Consent

 Communication with the public / local stakeholders  Largest capital project ever undertaken by the Council – no

precedents

 Communicating the message of Perth Transport Futures – more than

just new roads!

 Technical complexity of high embankments on poor ground within a

physically constrained location

slide-43
SLIDE 43

Phase 2 - Cross Tay Link Road

NEXT STEPS

 Finalise the contract documentation and issue ITT in April 2020

(pending planning approval)

 Contract Award – One Year ECI period commences September /

October 2020 including:

 Final site investigations  Detailed design including exploring options for efficiencies / improvements (by contractor)  Enabling works (temporary haul routes, site compounds, NRSWA diversions etc.)  Site clearance

 Land vested by September 2021 (worst case)  Main construction commences Autumn 2021  Works completed by Spring 2024

slide-44
SLIDE 44

Questions?