Perth Transport Future Project Phase 2 -Cross Tay Link Road CIHT - - PowerPoint PPT Presentation
Perth Transport Future Project Phase 2 -Cross Tay Link Road CIHT - - PowerPoint PPT Presentation
Perth Transport Future Project Phase 2 -Cross Tay Link Road CIHT Presentation 25 February 2020 AK Bell Library ROSS FLETCHER SENIOR ENGINEER ROADS INFRASTRUCTURE (PLANNING & DEVELOPMENT) Introduction Welcome Housekeeping
Introduction
Welcome Housekeeping Ross Fletcher – Background to Perth Transport Futures
Project & Cross Tay Link Road
Denise Ritchie – Design of Cross Tay Link Road Emma Cooper – EIA & Planning Application for the
Cross Tay Link Road
Ross Fletcher – Procurement & Next Steps
Roads Infrastructure Team
Small client team of 5 Set up in 2013/14 Situated within Planning & Development (Corporate & Democratic
Services)
Work closely with Transport Planning colleagues who progress proposed
large roads schemes to end of DMRB Stage 2
Once there is a Business Case and Budget for a scheme it is handed to
the Roads Infrastructure Team
We manage the delivery phase which generally consists of site
investigations, design through to DMRB Stage 3, land purchase, planning process and construction.
We rely on support from colleagues in Legal, Planning, Estates, Finance
and many others. Also rely on external support from consultants, DVS, Legal Advisors etc.
Perth Transport Futures Project
Strategic Rationale
Perth – major strategic hub Delivery of sustainable growth in the Tay Cities region Support the Northwest expansion of Perth as envisaged
in the Local Development Plan (new LDP recently launched)
Perth – AQMA. High priority given current climate crisis. Ambitious City Plan
Integrated Series of Measures over Four Phases
Phase 1 – A9/A85 scheme (complete) Phase 2 – CTLR Phase 3 – Bertha Park connection Phase 4 – City centre improvements (including greener
travel – Perth, People, Place with SUSTRANS)
Phase 1 – A9/A85 Scheme
Commenced on-site September 2016 Designer – CH2M Contractor – Balfour Beatty Complete May 2019 (roads opened
January 2019 – 3 months early)
Benefits / Features
New grade separated junction on A9 Link road to Bertha Park development
(including new school)
New access to industrial estate Relieve pressure on Inveralmond
Roundabout and Crieff Road corridor
Phase 1 – A9/A85 Scheme
NEC3 Option A Contract (Scape Procure) £37.9m final cost (within 7% of initial price) Collaborative approach Significant Community Benefits Programme Social Value of £12.9 or £0.42 per £1 spent Recognised for collaborative approach Various Awards including:
NEC Contract of the Year 2019 CECA Community Award 2019 National Social Value Award 2018
End of Project Review – Lessons learned
fed into CTLR strategies
AIMS OF THE CROSS TAY LINK ROAD
Reduced congestion and improved air quality in the city centre and Bridgend
Enable new, planned and committed developments – sustainable economic growth
Enable city centre improvements including a move towards greener travel
Connecting communities and improving access to Scone Palace and Perth Racecourse for events
Phase 2 - Cross Tay Link Road
MAIN FEATURES OF THE CROSS TAY LINK ROAD
New crossing of River Tay north of Perth
New grade separated junction between Inveralmond Roundabout and Luncarty
New link road from the A9 to the A94 (with roundabouts on Stormontfield Road, A93 and Highfield Track)
Active travel route for full length of new road
LOCAL DEVELOPMENT PLAN 2
Phase 2 - Cross Tay Link Road
Phase 2 - Cross Tay Link Road
Reduction in traffic congestion – modelling by SYSTRA / Transport Planning – air quality improvement evident as shown
SCHEME TIMELINE
2010 to 2016 Technical Assessment (DMRB – Stages 1 & 2 complete)
June 2016 – Council commits Capital funding of £78 million
December 2016 - Council approved the Preferred Route
Early 2017 – Scheme passed to Roads Infrastructure Team for delivery
Early 2017 to Present - liaison with land owners (ongoing_
July 2017 - SWECO appointed as designers (for specimen design)
July 2017 to Present - consultation with statutory bodies / environmental groups (ongoing)
Early 2018 to mid 2019 Site Investigations / Surveys
Phase 2 - Cross Tay Link Road
SCHEME TIMELINE
April 2018 to January 2019 Early Contractor Involvement (Balfour Beatty)
Summer 2018 – First Public Consultations
December 2018 – First draft of Specimen Design completed
January 2019 – Scottish Government commits £40 million to project
February to June 2019 – Alignment review between A93 and A94 (caused a six month delay)
Summer 2019 – Final round of public consultations in advance of planning application
Phase 2 - Cross Tay Link Road
SCHEME TIMELINE
September 2019 – Design layout finalised for planning application and land purchase
September 2019 – Council approval to proceed with Compulsory Purchase of land required
Compulsory Purchase Order made on 30 October 2019 (with Scottish Ministers)
Planning Application (including EIA) submitted in November 2019 (decision expected by April 2020)
Phase 2 - Cross Tay Link Road
CROSS TAY LINK ROAD
CIHT PRESENTATION – SWECO
25 FEBRUARY 2020 DENISE RITCHIE EMMA COOPER
2020-03-03 13
CROSS TAY LINK ROAD SWECO – Stage 3 Input
- Scheme Overview and Key Infrastructure
- Site Investigations
- Constraints
- Current Specimen Design Status
- Stakeholders and Landowners
- Environmental Impact Assessment and Planning
- Project Risks
- Bulk Quantities
2020-03-03 14
CROSS TAY LINK ROAD SCHEME OVERVIEW
2020-03-03 15
CROSS TAY LINK ROAD SCHEME OVERVIEW (PART 1 of 4)
2020-03-03 16
CROSS TAY LINK ROAD SCHEME OVERVIEW PART 2 of 4
2020-03-03 GENDIATUR, QUE REIUNT EXPLABO. UT ASINCTIIS DE VOLLACCAB ISUNT ET EOS QUATIANDANDI DELLECU LLUPTIIST 17
CROSS TAY LINK ROAD SCHEME OVERVIEW PART 3 of 4
2020-03-03 18
CROSS TAY LINK ROAD SCHEME OVERVIEW PART 4 of 4
2020-03-03 GENDIATUR, QUE REIUNT EXPLABO. UT ASINCTIIS DE VOLLACCAB ISUNT ET EOS QUATIANDANDI DELLECU LLUPTIIST 19
CROSS TAY LINK ROAD KEY INFRASTRUCTURE – A9 JUNCTION
2020-03-03 20
- Agreed design
- Loop arrangement
is compact
- Future proofed
CROSS TAY LINK ROAD KEY INFRASTRUCTURE – A9 OVERBRIDGE
2020-03-03 21
- Structural form
- Aesthetics
- Piled foundations
CROSS TAY LINK ROAD KEY INFRASTRUCTURE – RIVER TAY CROSSING
2020-03-03 22
- Structural form
- Clearances and temporary works
- Fishing rights, and
- Access options to the western pier
CROSS TAY LINK ROAD KEY INFRASTRUCTURE – CTLR ROAD CROSS SECTION
2020-03-03 23
- single carriageway
- 85kph design speed
- Segregated cycleway, and
- Grass verges and separation strip.
CROSS TAY LINK ROAD KEY INFRASTRUCTURE – JUNCTIONS
2020-03-03 24
Stormontfield Road Roundabout
A94 Roundabout
A93 Roundabout
CROSS TAY LINK ROAD KEY INFRASTRUCTURE – HIGHFIELD GREEN BRIDGE
2020-03-03 25
- Buried precast
concrete arch
- Aesthetics
- Connects NMU
infrastructure, and
- Provides ecological
and landscape connectivity.
CROSS TAY LINK ROAD KEY INFRASTRUCTURE – LANDSCAPE
2020-03-03 26
- High quality
landscape
- Wetland area, and
- Park and cycle
facility
CROSS TAY LINK ROAD SITE INVESTIGATIONS
The following were completed early in Stage 3:
- Ecological surveys
- Tree surveys;
- Topographical, bathymetric and drainage surveys;
- NMU CCTV surveys;
- Ground investigation in 2018; and
- Intrusive archaeological investigations (trial trenching and geophysical surveys) in early 2019
2020-03-03 27
CROSS TAY LINK ROAD SITE INVESTIGATIONS
- A9 Ground Conditions
– A9 Mainline south - raised tidal flat deposits and alluvium; – Broxy Wood is a drumlin of glacial till; – Grade separated junction - raised marine deposits; and – North of Broxy Kennels - glacial deposits.
- CTLR Ground Conditions
– Marine deposits and alluvium to Balboughty Farm. Tay Crossing Bridge piles estimated at 40m to 55m in length; and – Glacial deposits with shallow bedrock beyond Balboughty Farm .
2020-03-03 28
CROSS TAY LINK ROAD CONSTRAINTS
2020-03-03 29
CROSS TAY LINK ROAD SPECIMEN DESIGN STATUS
2020-03-03 30
- Specimen Design concluded
- Stage 1 Road Safety Audit
- Final Stage 3 Cost Estimate
- Stage 3 Report
- (Draft) CAR licenses
CROSS TAY LINK ROAD STAKEHOLDERS AND LANDOWNERS
2020-03-03 31
- Consultations with key stakeholders, including:
– Transport Scotland (and BEAR); – Network Rail; – HES, SNH and SF; – SEPA; and – Public Utilities.
- PKC meetings with landowners/developers with:
– Mansfield Estate; – AJ Stephen; – Ritchie; and – I&H Brown.
- Early public consultation events / ongoing engagement
CROSS TAY LINK ROAD ENVIRONMENTAL IMPACT ASSESSMENT
2020-03-03 32
- Background
- Key features
- Air Quality
- Active travel
- Climate change
- Biodiversity
- Environmental Enhancement
CROSS TAY LINK ROAD ENVIRONMENTAL IMPACT ASSESSMENT
- Cumulative Assessment
- Overall Environmental Effects
- Schedule of Mitigation
2020-03-03 33
A copy of the EIAR is available on the CTLR website and on the Perth and Kinross Council planning portal: https://planningapps.pkc.gov.uk/online-applications/search.do?action=simple&searchType=Application
- Ref. No: 19/01837/FLM
CROSS TAY LINK ROAD PLANNING
2020-03-03 34
- Proposal of Application Notice
(PAN)
– 10th July 2019
- Pre-application consultation
– Public events – Landowners, statutory consultees, elected members
- Planning Application
– Pre-validation – Final submission on 15th November 2019 – Responses
The planning application can be found on Perth and Kinross Council’s online planning portal at: https://planningapps.pkc.gov.uk/online-applications/search.do?action=simple&searchType=Application
- Ref. No: 19/01837/FLM
CROSS TAY LINK ROAD PROJECT RISKS
2020-03-03 35
- Management of stakeholders
- Ground conditions
- Ecology, seasonal constraints
- Existing roads
- Perth to Inverness railway
- Unknown archaeology
- Agricultural drainage
- Public utilities
- Associated development
CROSS TAY LINK ROAD PROJECT RISKS
2020-03-03 36
- Access to Tay Crossing
bridge – west pier
– Option 1 – access from the south via a temporary bridge over the River Almond; – Option 2 – access from the west
- ver and under the Perth to
Inverness railway; and – Option 3 – access from the north via the existing Luncarty junction.
CROSS TAY LINK ROAD BULK QUANTITIES
2020-03-03 37
DMRB Series Location Item Quantity 400 Road Restraints Scheme wide N2 barrier 4,700m 500 Drainage Scheme wide Filter Drains 24,000m 500 Drainage Scheme wide Carrier Drains 3,900m 600 Earthworks A9 section Cut 609,500m³ 600 Earthworks A9 section Fill (inc landscaping) 700,500m³ 600 Earthworks CTLR section Cut 220,500m³ 600 Earthworks CTLR section Fill (inc landscaping) 257,900m³ 700 Pavement Scheme wide Area of Surface Course 175,000m² 1700 Structures Scheme wide Principal Structures 3 No. 1700 Structures Scheme wide RC Box Culverts 4 No. 1700 Structures Scheme wide VMS Foundations 1 No.
Phase 2 - Cross Tay Link Road
PROCUREMENT / CONTRACT
Market engagement days in March 2019 – positive feedback / interest
from the market
Presentation Questionnaires Interviews
Regular scheme updates provided to the market Procurement strategy approved by project board October 2019
Two stage competitive procedure Design and build NEC4 contract Target cost (option C) Option X22 used: One year period of early contractor involvement in advance of main construction
Phase 2 - Cross Tay Link Road
PROCUREMENT / CONTRACT
PIN notice published 9 January 2020
Draft One of Contract Data attached – feedback received
ESPD (PQQ) published 17 February 2020 for return by 23 March 2020
Draft Two of Contract Data attached – awaiting feedback
ITT to be issued to successful bidders in April 2020
Intention to have list of four bidders for second stage
Phase 2 - Cross Tay Link Road
EARLY CONTRACTOR INVOLVEMENT
Important to the success of the project. Lessons learned from Phase 1. Benefits of a successful period of ECI:
Ensure everyone fully understands objectives of the scheme prior to main works starting Carry out enabling works to de-risk the programme Able to fully discuss and fairly apportion risks before main works starting Period of time for contractor to scrutinise specimen design and employers requirements and
recommend changes
Changes in ECI period much cheaper than being reactive during main works More time to deal with seasonal environmental constraints More time to plan for meaningful community benefits
Phase 2 - Cross Tay Link Road
COMMUNITY BENEFITS
Strategy being developed to include in the contract:
Involving local communities in the project Helping local communities Assisting local charities and organisations Inspiring the next generation of engineers Getting local unemployed people back to work Looking after our local and the wider environment Ensuring maximum local spend Caring for and developing the local workforce
We want to build on the award winning work on Phase 1 and push for
even more community benefit in phase 2
Phase 2 - Cross Tay Link Road
CHALLENGES FACED:
Environmentally sensitive landscape Consultation with numerous statutory bodies Access to the west bank of the River Tay – Scheduled Monument
Consent
Communication with the public / local stakeholders Largest capital project ever undertaken by the Council – no
precedents
Communicating the message of Perth Transport Futures – more than
just new roads!
Technical complexity of high embankments on poor ground within a
physically constrained location
Phase 2 - Cross Tay Link Road
NEXT STEPS
Finalise the contract documentation and issue ITT in April 2020
(pending planning approval)
Contract Award – One Year ECI period commences September /
October 2020 including:
Final site investigations Detailed design including exploring options for efficiencies / improvements (by contractor) Enabling works (temporary haul routes, site compounds, NRSWA diversions etc.) Site clearance
Land vested by September 2021 (worst case) Main construction commences Autumn 2021 Works completed by Spring 2024