peninsula corridor electrification project
play

Peninsula Corridor Electrification Project Real Estate Process - PDF document

Peninsula Corridor Electrification Project Real Estate Process LPMG June 25, 2015 Real Estate Need Project Need - Traction Power Facilities - Overhead Contact System Poles - Electric Safety Zone Identified in FEIR Approach -


  1. Peninsula Corridor Electrification Project Real Estate Process LPMG June 25, 2015 Real Estate Need • Project Need - Traction Power Facilities - Overhead Contact System Poles - Electric Safety Zone • Identified in FEIR • Approach - Friendly - Eminent Domain (only if needed) 2 1

  2. Scope • Most project improvements within right of way (ROW) • Limited land needed outside of ROW - Narrow strips for poles and ESZ - 2 TPF outside of rail right of way 3 Scope continued Number of San San Santa Parcels Francisco Mateo Clara Total County County County PCEP ROW Needs (Fee and 5 102 56 163 Easement) Note: Based on FEIR 4 2

  3. Process • Friendly - Contact property owners - Appraisal and negotiate - Written offer - Closing • Eminent Domain (only if needed) - Additional time - Use cooperative agreement with VTA, SamTrans and City and County of San Francisco • Complete acquisition by fall 2017 5 Next Steps • May to Summer - Contact property owners - Begin appraisal process • JPB Items to Come (Summer) - Delegation of Authority - Cooperative Agreements with VTA, SamTrans, and City and County of San Francisco - Secure real estate services contract 6 3

  4. Questions 7 4

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend