SLIDE 1
1
Peninsula Corridor Electrification Project Draft Environmental Impact Report
LPMG March 27, 2014
Context
2
Peninsula Corridor Electrification Project Draft Environmental - - PDF document
Peninsula Corridor Electrification Project Draft Environmental Impact Report LPMG March 27, 2014 Context 2 1 Caltrain Modernization Program ~$1.5 Billion Early Investment Program CBOSS PTC (2015) Peninsula Corridor
2
3
4
5
Stakeholder Outreach Establish Owner’s Team Environmental Clearance Procure/Select Contractor Team Design/Manufacture/Build *Schedule subject to change
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
*Note: CBOSS, which minimizes gate down time, is assumed to be in place
22
23
24
25
26
27
28
29
30
31
32