Peninsula Corridor Electrification Project
S MCTA
TA Board of Directors April 5, 2018 Agenda Item # 11b
Peninsula Corridor Electrification Project S MCTA TA Board of - - PowerPoint PPT Presentation
Peninsula Corridor Electrification Project S MCTA TA Board of Directors April 5, 2018 Agenda Item # 11b Caltrain System 77 Miles, 32 Stations 92 Weekday Trains Caltrain owns (S F to S J) Tenants (ACE, CC, Amtrak,
TA Board of Directors April 5, 2018 Agenda Item # 11b
Caltrain owns (S F to S J) Union Pacific owns (S J to Gilroy)
Stations
Trains
CC, Amtrak, Freight)
20,000 25,000 30,000 35,000 40,000 45,000 50,000 55,000 60,000 65,000
Average Daily Ridership
Bi-directional commute with riders standing on trains going southbound and northbound
At Retirement Age: 20/ 29 loco; 73/ 134 cars
Area Project Service 51 miles San Francisco to San Jose (Tamien Station) Electrification:
Facilities
Electric Trains (EMUs)
Up to 79 mph Service Increase
time
service
Mixed-fleet service (interim period) Continue tenant service
Freight
Metric Today PCEP
Example Baby Bullet Train Retain 5-6 stops 60 minutes 45 minutes Retain S F to S J 60 minutes 6 stops 13 stops Example Redwood City S tation Train stops / peak hour 3 5
Note: Prototypical Train and S chedule
Note: Prototypical Train and S chedule
Note: 2013 BAC Report, generates $2.5B economic activity and 9,600 j obs
Over 250 Entities
Caltrain Electrification Groundbreaking July 2017 S alt Lake City Vehicle Plant Groundbreaking October 2017
by 1 & 3
work from 8 p.m.- 6 a.m.
work
acoustical barrier blankets and position lights away from homes
Loading Reinforcing S teel Cages Drilling of Foundations
Loading Reinforcing S teel Cages Lowering Reinforcement Cage Final Alignment of Anchor Bolts
Foundation Concrete Quality Testing Concrete Placement with Pump
Final Finishing of Exposed Concrete Foundations Restoration of Ballast and Area Around Foundation
18
19
Cab End Underframe Exterior Paint Test S amples
idewall Extrusion
20
Machined part Cruciform j oint fillet weld S ide wall
Upper Deck Assembly Middle Underframe in Welding
Upper and Lower Carbody S ubassemblies Coming Together
S MCTA Contribution: $80m
Note: Budget / Expenditures as of December 31, 2017
25
* Includes executed change orders and awarded contracts ** Refer to Contingency Drawdown Table on next slide for details
Budget Current Budget* Q2 Costs Costs to Date Estimate at Completion Electrification $696.6 $696.7 $26.7 $183.9 $696.7 S CADA $0.0 $3.4 $0.0 $0.0 $3.4 EMU $550.9 $551.8 $17.1 $60.7 $551.8 S eparate Contract & S upport Costs $417.2 $417.2 $20.5 $143.9 $417.2 Contingency $315.5 $311.1 $0.0 $0.0 $269.6 Anticipated Changes $0.0 $0.0 $0.0 $0.0 $41.5 PCEP Total $1,980.3 $1,980.3 $64.4 $388.5 $1,980.3
(in millions)
26
$315.5 $289.6 $231.7 $193.1 $154.5 $115.8 $77.2 $38.6
$312.0 $311.1 $269.6
$0 $50 $100 $150 $200 $250 $300 $350
Apr-16 Jun-16 Aug-16 Oct-16 Dec-16 Feb-17 Apr-17 Jun-17 Aug-17 Oct-17 Dec-17 Feb-18 Apr-18 Jun-18 Aug-18 Oct-18 Dec-18 Feb-19 Apr-19 Jun-19 Aug-19 Oct-19 Dec-19 Feb-20 Apr-20 Jun-20 Aug-20 Oct-20 Dec-20 Feb-21 Apr-21 Jun-21 Aug-21 Oct-21 Dec-21 Feb-22 Apr-22 Jun-22 Aug-22
Millions
Minimum Contingency Level Actual Contingency Drawdown Anticipated Contingency Drawdown
CHP05 CHP06 CHP04 CHP03 CHP02 CHP07 CHP08 CHP01 Contingency Hold Points (CHP)
CHP01 - Determination of Baseline Budget Rev 4 CHP02 - Entry into Engineering CHP03 - PG&E Substation Design Acceptance CHP04 - Finish Segment 4A All Disciplines CHP05 - OCS Acceptance Testing Completion - Segment 1 CHP06 - Construction & Testing Completion - All Segments CHP07 - EMU Conditional Acceptance of 14th Trainset CHP08 - Pre-Revenue Testing Complete