Summary of Proposed Eminent Domain November 24, 2015 Real Estate - - PowerPoint PPT Presentation
Summary of Proposed Eminent Domain November 24, 2015 Real Estate - - PowerPoint PPT Presentation
Summary of Proposed Eminent Domain November 24, 2015 Real Estate Site Control Timeline Planned Notice to Proceed: June 1, 2016* S ubmit Filing of Time Prior to Notification Possession Complaint Notice to Available for to City Awarded
Real Estate Site Control Timeline
Submit
Notification to City Council
- 45 Days
Filing of Complaint in Court
- +/- 60 Days
Possession Awarded
- +/- 60 Days
Time Prior to Notice to Proceed
- +/- 8 Days
Planned Notice to Proceed: June 1, 2016*
Dillingham Utility & Road Widening Package: April 5, 2016 ( -42 Days) ** HART Board Authorization to File Action Available for Construction Hart Board Approval to Proceed
Resolution No. 2015-95 Heirs and/or Assigns of Charles S. Desky, Trustee Tax Map Key: 2-3-003-000
Resolution No. 2015-95 Tax Map Key: 2-3-003-000 Heirs and/or Assigns of Charles S. Desky, Trustee
Resolution No. 2015-95 Tax Map Key: 2-3-003-000 Heirs and/or Assigns of Charles S. Desky, Trustee
Partial Fee Acquisition Total Acquisition: 9,908 square feet July 9, 2015: Notice of Offer to Purchase July 17, 2015: Received from Corporation Counsel - Publically post Notice of Offer to Purchase and Referral for Eminent Domain Action September 7-13, 2015: Publically Posted Notice of Offer September 9, 2015: Response from Interested Party requesting a Title Report and Survey of Condemned Area To clear clouded Title, maintain Project construction, Land Court, mapping and escrow may cause delays