Summary of Proposed Eminent Domain November 24, 2015 Real Estate Site Control Timeline Planned Notice to Proceed: June 1, 2016* S ubmit Filing of Time Prior to Notification Possession Complaint Notice to Available for to City Awarded


slide-1
SLIDE 1

Summary of Proposed Eminent Domain November 24, 2015

slide-2
SLIDE 2

Real Estate Site Control Timeline

Submit

Notification to City Council

  • 45 Days

Filing of Complaint in Court

  • +/- 60 Days

Possession Awarded

  • +/- 60 Days

Time Prior to Notice to Proceed

  • +/- 8 Days

Planned Notice to Proceed: June 1, 2016*

Dillingham Utility & Road Widening Package: April 5, 2016 ( -42 Days) ** HART Board Authorization to File Action Available for Construction Hart Board Approval to Proceed

slide-3
SLIDE 3

Resolution No. 2015-95 Heirs and/or Assigns of Charles S. Desky, Trustee Tax Map Key: 2-3-003-000

slide-4
SLIDE 4

Resolution No. 2015-95 Tax Map Key: 2-3-003-000 Heirs and/or Assigns of Charles S. Desky, Trustee

slide-5
SLIDE 5

Resolution No. 2015-95 Tax Map Key: 2-3-003-000 Heirs and/or Assigns of Charles S. Desky, Trustee

 Partial Fee Acquisition  Total Acquisition: 9,908 square feet  July 9, 2015: Notice of Offer to Purchase  July 17, 2015: Received from Corporation Counsel - Publically post Notice of Offer to Purchase and Referral for Eminent Domain Action  September 7-13, 2015: Publically Posted Notice of Offer  September 9, 2015: Response from Interested Party requesting a Title Report and Survey of Condemned Area  To clear clouded Title, maintain Project construction, Land Court, mapping and escrow may cause delays