Pelamis - Wave Energy in Action !! 2 Wave Hub - What is it? - - PowerPoint PPT Presentation

pelamis wave energy in action
SMART_READER_LITE
LIVE PREVIEW

Pelamis - Wave Energy in Action !! 2 Wave Hub - What is it? - - PowerPoint PPT Presentation

WAVE HUB A Future for Wave Energy in Cornwall Dr Mike Patching BEng, PhD, CEng, MEI 1 Pelamis - Wave Energy in Action !! 2 Wave Hub - What is it? Simple idea! An area of sea with an electrical cable and connection point


slide-1
SLIDE 1

1

‘WAVE HUB’

A Future for Wave Energy in Cornwall

Dr Mike Patching

BEng, PhD, CEng, MEI

slide-2
SLIDE 2

2

‘Pelamis’ - Wave Energy in Action !!

slide-3
SLIDE 3

3

Wave Hub - What is it?

Simple idea!

§ An area of sea with an electrical cable and connection point

  • ffshore into which arrays of Wave Energy Converters will

be connected § A connection to the National Grid for initially up to 30 MW

  • f wave power

§ Permits to allow connection and operation of the facility

slide-4
SLIDE 4

4

Why are we doing it?

§ Demonstrate commercial viability of wave energy

slide-5
SLIDE 5

5

R&D Initial prototype Refined prototype Pre- commercial device Market entry with commercial product Market penetration Demonstration

NaREC Wave Hub EMEC

Wave Hub … a route to commercialisation

slide-6
SLIDE 6

6

What do we hope will happen?

§ Demonstrate commercial viability of wave energy § Maintain and strengthen the UK lead in marine renewable energy § Develop a new industry in the South West § Contribute significantly to the South West renewable energy generation

slide-7
SLIDE 7

7

Where did it come from?

§ 2001 SWRDA Regional Renewable Energy Strategy § 2002 Agreement to support biomass, wave and tidal power § 2002 Set up Regen SW § Oct 2003 Seapower South West Report § Jan 2004 METOC Seapower SW Review § April 2004 Wave Hub Feasibility Study Starts

slide-8
SLIDE 8

8

Feasibility Study Organisation

PROJECT MANAGER SCOTT WILSON OCEANS Dr Mike Patching

SWRDA

Mr Dominic Vincent – Environment Manager Advisory Group Regen SW AD LITTLE ' Business Case' HALCROW 'Technical Feasibility Study' BOND PEARCE 'Consents and Permits' D CLARK 'Publicity' CSEP 'Stakeholder Consultation'

slide-9
SLIDE 9

9

Project Requirements (What do we need to do?)

§ A site (offshore and onshore) § A suitable resource (wave energy) § A grid connection § Feasible technology (practical and cost effective) § A business case (market need and financially viable) § Legally allowed to do it (permits and consents including an EIA) § Stakeholder support

slide-10
SLIDE 10

10

slide-11
SLIDE 11

11

Grid Connection Options

Western Power Distribution Network

slide-12
SLIDE 12

12

slide-13
SLIDE 13

13

slide-14
SLIDE 14

14

slide-15
SLIDE 15

15

Inshore shipping route

slide-16
SLIDE 16

16

Wave Energy Converter Arrays

G e n G e n G e n

Cab le Sup port Buo ys

33kV Sub-Sea Cable

Wave Hub Substati

  • n

33kV Cable Joint

Utility Company Substation 33kV Bus-bar Connection Point

Cable Duct Directionally Drilled Through Sand Dunes 33/11kV Power Connectio n Unit 11kV Wave Energy Device Connection Cables

11k V Cab le Spli ces

Terminatio n & Distributio n Unit

11kV Wave Energy Device Cables

WAVE HUB EQUIPMENT Wave Hub System Diagram Figure5.3

33/11kV Power Connectio n Unit 11kV Wave Energy Device Connection Cables 1 x 3-core 33kV Underground Cable 33kV PCU Conne ction Cables

Shore based equip ment

Wet Hub

Communic ations and Control 33kV Circuit Breakers Works hop

G e n

slide-17
SLIDE 17

17

The wet hub

§ Sub-sea transformers § Remotely operable sub-sea switchgear and protection systems

slide-18
SLIDE 18

18

Typical 33kV Cable

slide-19
SLIDE 19

19

slide-20
SLIDE 20

20

slide-21
SLIDE 21

21

slide-22
SLIDE 22

22

Potential Benefits

The potential to create an International industry in SW § Development of wave energy sector and associated supply chains

– including marine technology and advanced engineering resulting in over 450 jobs in the SW by 2010 and 700 by 2020.

§ Inward Investment

– GVA from indirect impacts to the SW of £15million and £27 million respectively with 20-40% expected in Cornwall.

§ 20MW wave power produced and sold by 2008

– supplying 14,000 homes; meet up to 30% of Cornwall’s renewable energy target and up to 5% of the Regional target.

§ Links to Higher Education

– Centres of Excellence in CUC, Plymouth and Exeter leading to the establishment of a high profile wave energy R&D base in west Cornwall.

slide-23
SLIDE 23

23

Wave Hub – a long way to go!

Major issues to be addressed: § Funding § Consents and Licenses § Stakeholder Agreement § The Wave Device Developers § Engineering Studies and Surveys § Detailed Design § Procurement § Construction § Operation

slide-24
SLIDE 24

24

Permits & Consents

§ Electricity Act 1989 Section 36 (DTI) § Food & Environment Protection Act 1985 (DEFRA) § Coast Protection Act 1949 § Town & Country Planning Act 1990 § Electricity Act 2004 § The Marine Bill ? § European Legislation - EIA Directive § Nature Conservation Directives § SEA § Crown Estate § ING

slide-25
SLIDE 25

25

Contracts

§ Power Purchase Agreement (PPA) § Device Developer Agreement(s) § Engineering Procurement and Construction (EPC) § Grid Connection Agreement § Management, Operation and Maintenance Agreement § Metering Agreement § Company Formation

slide-26
SLIDE 26

26

Costs

Wave Hub Development and Construction Estimated Costs Stage 95% probability of being exceeded Mean probability 5% probability of being exceeded Development £1.25 million £1.42 million £1.60 million Construction £11.41 million £12.42 million £13.45 million

slide-27
SLIDE 27

27

SWRDA WAVE HUB PROJECT TIMELINE 2006 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec DEVELOPMENT: SWRDA Funding & Staff Carry out EIA Site Surveys Engineering design for EIA DTI/CE/DEFRA Consultation Planning Route Map Planning Applications Granted Wave Measurement Energy Analysis Engineering Specifications WHMC Business Plan and Funding Contracts (Developer, Grid, EPC) Design & Tender for Construction (OJEC) PROCUREMENT: Wave Energy Devices Wet Hub (transformers) Cables Switchgear CONSTRUCTION: ONSHORE OFFSHORE Grid Conection Commissioning OPERATION: 2005 2006

CAPITAL FUNDING GRANTED FOR PROCUREMENT & CONSTRUCTION PLANNING

WHMC CONTRACTS WITH DEVELOPERS, UTILITY AND EPC CONTRACTOR Appoint WHMC Managing Director MOU with Project Developers Complete Business Plan & Apply for Funding

slide-28
SLIDE 28

28

Conclusions

§ It is Technically Feasible !! § It is wanted and supported by Industry and Government § It is supported by SWRDA § It appears to have positive environmental benefits and negligible negative impacts (to be confirmed by EIA) § It has Local Stakeholder support (so far) § It is legal § It requires a lot more work! § It will cost - but not excessively so! § We are not alone!