pelamis wave energy in action
play

Pelamis - Wave Energy in Action !! 2 Wave Hub - What is it? - PowerPoint PPT Presentation

WAVE HUB A Future for Wave Energy in Cornwall Dr Mike Patching BEng, PhD, CEng, MEI 1 Pelamis - Wave Energy in Action !! 2 Wave Hub - What is it? Simple idea! An area of sea with an electrical cable and connection point


  1. ‘ WAVE HUB ’ A Future for Wave Energy in Cornwall Dr Mike Patching BEng, PhD, CEng, MEI 1

  2. ‘ Pelamis ’ - Wave Energy in Action !! 2

  3. Wave Hub - What is it? Simple idea! § An area of sea with an electrical cable and connection point offshore into which arrays of Wave Energy Converters will be connected § A connection to the National Grid for initially up to 30 MW of wave power § Permits to allow connection and operation of the facility 3

  4. Why are we doing it? § Demonstrate commercial viability of wave energy 4

  5. Wave Hub … a route to commercialisation R&D NaREC Demonstration Initial prototype Refined prototype EMEC Pre- commercial device Wave Hub Market entry with commercial product Market penetration 5

  6. What do we hope will happen? § Demonstrate commercial viability of wave energy § Maintain and strengthen the UK lead in marine renewable energy § Develop a new industry in the South West § Contribute significantly to the South West renewable energy generation 6

  7. Where did it come from? § 2001 SWRDA Regional Renewable Energy Strategy § 2002 Agreement to support biomass, wave and tidal power § 2002 Set up Regen SW § Oct 2003 Seapower South West Report § Jan 2004 METOC Seapower SW Review § April 2004 Wave Hub Feasibility Study Starts 7

  8. Feasibility Study Organisation Advisory Group SWRDA Regen SW Mr Dominic Vincent – Environment Manager PROJECT MANAGER SCOTT WILSON OCEANS Dr Mike Patching BOND PEARCE CSEP D CLARK AD LITTLE HALCROW 'Technical Feasibility 'Consents and 'Stakeholder ' Business Case' 'Publicity' Study' Permits' Consultation' 8

  9. Project Requirements (What do we need to do?) § A site (offshore and onshore) § A suitable resource (wave energy) § A grid connection § Feasible technology (practical and cost effective) § A business case (market need and financially viable) § Legally allowed to do it (permits and consents including an EIA) § Stakeholder support 9

  10. 10

  11. Grid Connection Options Western Power Distribution Network 11

  12. 12

  13. 13

  14. 14

  15. Inshore shipping route 15

  16. Wave Energy Converter Arrays Utility Company Substation G G G G e e e 33kV Bus-bar e n n n n Connection Point Cab le 11kV Sup Wave port Energy Buo Device ys Cables 11k V Cab le Spli ces Shore Wet based Hub Wave equip 11kV Wave Hub Energy ment Substati Device Connection on Communic Works 33kV Circuit Cables ations and hop Breakers Control 11kV Wave Energy 33/11kV Device Power Connection Connectio Cables n Unit 33/11kV 1 x 3-core 33kV Power Underground Connectio Cable n Unit 33kV Sub-Sea Cable Cable Duct Directionally Drilled 33kV Through Sand Cable 33kV Dunes Joint PCU Conne WAVE HUB ction Terminatio EQUIPMENT Cables n & Distributio n Unit Wave Hub System Diagram 16 Figure5.3

  17. The wet hub § Sub-sea transformers Remotely operable § sub-sea switchgear and protection systems 17

  18. Typical 33kV Cable 18

  19. 19

  20. 20

  21. 21

  22. Potential Benefits The potential to create an International industry in SW § Development of wave energy sector and associated supply chains – including marine technology and advanced engineering resulting in over 450 jobs in the SW by 2010 and 700 by 2020. § Inward Investment – GVA from indirect impacts to the SW of £15million and £27 million respectively with 20-40% expected in Cornwall. § 20MW wave power produced and sold by 2008 – supplying 14,000 homes; meet up to 30% of Cornwall ’ s renewable energy target and up to 5% of the Regional target. § Links to Higher Education – Centres of Excellence in CUC, Plymouth and Exeter leading to the establishment of a high profile wave energy R&D base in west Cornwall. 22

  23. Wave Hub – a long way to go! Major issues to be addressed: § Funding § Consents and Licenses § Stakeholder Agreement § The Wave Device Developers § Engineering Studies and Surveys § Detailed Design § Procurement § Construction § Operation 23

  24. Permits & Consents § Electricity Act 1989 Section 36 (DTI) § Food & Environment Protection Act 1985 (DEFRA) § Coast Protection Act 1949 § Town & Country Planning Act 1990 § Electricity Act 2004 § The Marine Bill ? § European Legislation - EIA Directive § Nature Conservation Directives § SEA § Crown Estate § ING 24

  25. Contracts § Power Purchase Agreement (PPA) § Device Developer Agreement(s) § Engineering Procurement and Construction (EPC) § Grid Connection Agreement § Management, Operation and Maintenance Agreement § Metering Agreement § Company Formation 25

  26. Costs Wave Hub Development and Construction Estimated Costs Stage 95% probability of Mean probability 5% probability of being being exceeded exceeded £1.42 million Development £1.25 million £1.60 million £12.42 million Construction £11.41 million £13.45 million 26

  27. SWRDA WAVE HUB 2005 2006 PROJECT TIMELINE 2006 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec DEVELOPMENT: SWRDA Funding & Staff PLANNING Carry out EIA Site Surveys Engineering design for EIA CAPITAL FUNDING GRANTED FOR DTI/CE/DEFRA Consultation Planning Route Map PROCUREMENT & Planning Applications Granted CONSTRUCTION Wave Measurement Energy Analysis Engineering Specifications WHMC CONTRACTS WITH DEVELOPERS, UTILITY AND WHMC EPC CONTRACTOR Business Plan and Funding Contracts (Developer, Grid, EPC) Design & Tender for Construction (OJEC) Appoint PROCUREMENT: WHMC Wave Energy Devices Managing Wet Hub (transformers) Director Cables Switchgear MOU with Project CONSTRUCTION: ONSHORE OFFSHORE Developers Grid Conection Commissioning Complete Business Plan & Apply for Funding OPERATION: 27

  28. Conclusions § It is Technically Feasible !! § It is wanted and supported by Industry and Government § It is supported by SWRDA § It appears to have positive environmental benefits and negligible negative impacts (to be confirmed by EIA) § It has Local Stakeholder support (so far) § It is legal § It requires a lot more work! § It will cost - but not excessively so! § We are not alone! 28

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend