1
Pelamis - Wave Energy in Action !! 2 Wave Hub - What is it? - - PowerPoint PPT Presentation
Pelamis - Wave Energy in Action !! 2 Wave Hub - What is it? - - PowerPoint PPT Presentation
WAVE HUB A Future for Wave Energy in Cornwall Dr Mike Patching BEng, PhD, CEng, MEI 1 Pelamis - Wave Energy in Action !! 2 Wave Hub - What is it? Simple idea! An area of sea with an electrical cable and connection point
2
‘Pelamis’ - Wave Energy in Action !!
3
Wave Hub - What is it?
Simple idea!
§ An area of sea with an electrical cable and connection point
- ffshore into which arrays of Wave Energy Converters will
be connected § A connection to the National Grid for initially up to 30 MW
- f wave power
§ Permits to allow connection and operation of the facility
4
Why are we doing it?
§ Demonstrate commercial viability of wave energy
5
R&D Initial prototype Refined prototype Pre- commercial device Market entry with commercial product Market penetration Demonstration
NaREC Wave Hub EMEC
Wave Hub … a route to commercialisation
6
What do we hope will happen?
§ Demonstrate commercial viability of wave energy § Maintain and strengthen the UK lead in marine renewable energy § Develop a new industry in the South West § Contribute significantly to the South West renewable energy generation
7
Where did it come from?
§ 2001 SWRDA Regional Renewable Energy Strategy § 2002 Agreement to support biomass, wave and tidal power § 2002 Set up Regen SW § Oct 2003 Seapower South West Report § Jan 2004 METOC Seapower SW Review § April 2004 Wave Hub Feasibility Study Starts
8
Feasibility Study Organisation
PROJECT MANAGER SCOTT WILSON OCEANS Dr Mike Patching
SWRDA
Mr Dominic Vincent – Environment Manager Advisory Group Regen SW AD LITTLE ' Business Case' HALCROW 'Technical Feasibility Study' BOND PEARCE 'Consents and Permits' D CLARK 'Publicity' CSEP 'Stakeholder Consultation'
9
Project Requirements (What do we need to do?)
§ A site (offshore and onshore) § A suitable resource (wave energy) § A grid connection § Feasible technology (practical and cost effective) § A business case (market need and financially viable) § Legally allowed to do it (permits and consents including an EIA) § Stakeholder support
10
11
Grid Connection Options
Western Power Distribution Network
12
13
14
15
Inshore shipping route
16
Wave Energy Converter Arrays
G e n G e n G e n
Cab le Sup port Buo ys
33kV Sub-Sea Cable
Wave Hub Substati
- n
33kV Cable Joint
Utility Company Substation 33kV Bus-bar Connection Point
Cable Duct Directionally Drilled Through Sand Dunes 33/11kV Power Connectio n Unit 11kV Wave Energy Device Connection Cables
11k V Cab le Spli ces
Terminatio n & Distributio n Unit
11kV Wave Energy Device Cables
WAVE HUB EQUIPMENT Wave Hub System Diagram Figure5.3
33/11kV Power Connectio n Unit 11kV Wave Energy Device Connection Cables 1 x 3-core 33kV Underground Cable 33kV PCU Conne ction Cables
Shore based equip ment
Wet Hub
Communic ations and Control 33kV Circuit Breakers Works hop
G e n
17
The wet hub
§ Sub-sea transformers § Remotely operable sub-sea switchgear and protection systems
18
Typical 33kV Cable
19
20
21
22
Potential Benefits
The potential to create an International industry in SW § Development of wave energy sector and associated supply chains
– including marine technology and advanced engineering resulting in over 450 jobs in the SW by 2010 and 700 by 2020.
§ Inward Investment
– GVA from indirect impacts to the SW of £15million and £27 million respectively with 20-40% expected in Cornwall.
§ 20MW wave power produced and sold by 2008
– supplying 14,000 homes; meet up to 30% of Cornwall’s renewable energy target and up to 5% of the Regional target.
§ Links to Higher Education
– Centres of Excellence in CUC, Plymouth and Exeter leading to the establishment of a high profile wave energy R&D base in west Cornwall.
23
Wave Hub – a long way to go!
Major issues to be addressed: § Funding § Consents and Licenses § Stakeholder Agreement § The Wave Device Developers § Engineering Studies and Surveys § Detailed Design § Procurement § Construction § Operation
24
Permits & Consents
§ Electricity Act 1989 Section 36 (DTI) § Food & Environment Protection Act 1985 (DEFRA) § Coast Protection Act 1949 § Town & Country Planning Act 1990 § Electricity Act 2004 § The Marine Bill ? § European Legislation - EIA Directive § Nature Conservation Directives § SEA § Crown Estate § ING
25
Contracts
§ Power Purchase Agreement (PPA) § Device Developer Agreement(s) § Engineering Procurement and Construction (EPC) § Grid Connection Agreement § Management, Operation and Maintenance Agreement § Metering Agreement § Company Formation
26
Costs
Wave Hub Development and Construction Estimated Costs Stage 95% probability of being exceeded Mean probability 5% probability of being exceeded Development £1.25 million £1.42 million £1.60 million Construction £11.41 million £12.42 million £13.45 million
27
SWRDA WAVE HUB PROJECT TIMELINE 2006 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec DEVELOPMENT: SWRDA Funding & Staff Carry out EIA Site Surveys Engineering design for EIA DTI/CE/DEFRA Consultation Planning Route Map Planning Applications Granted Wave Measurement Energy Analysis Engineering Specifications WHMC Business Plan and Funding Contracts (Developer, Grid, EPC) Design & Tender for Construction (OJEC) PROCUREMENT: Wave Energy Devices Wet Hub (transformers) Cables Switchgear CONSTRUCTION: ONSHORE OFFSHORE Grid Conection Commissioning OPERATION: 2005 2006
CAPITAL FUNDING GRANTED FOR PROCUREMENT & CONSTRUCTION PLANNING
WHMC CONTRACTS WITH DEVELOPERS, UTILITY AND EPC CONTRACTOR Appoint WHMC Managing Director MOU with Project Developers Complete Business Plan & Apply for Funding
28