Participation Mark Wilson MRTPI Infrastructure Planning Lead - - PowerPoint PPT Presentation

participation
SMART_READER_LITE
LIVE PREVIEW

Participation Mark Wilson MRTPI Infrastructure Planning Lead - - PowerPoint PPT Presentation

DCO Process - Effective Participation Mark Wilson MRTPI Infrastructure Planning Lead Background The DCO Process Local authorities role Legislation / Guidance / Advice Hinkley Point C experience Current Caseload of


slide-1
SLIDE 1

DCO Process - Effective Participation

Mark Wilson MRTPI – Infrastructure Planning Lead

slide-2
SLIDE 2
  • Background
  • The DCO Process
  • Local authorities’ role
  • Legislation / Guidance / Advice
  • Hinkley Point C experience
slide-3
SLIDE 3

Current Caseload of Nuclear Projects

slide-4
SLIDE 4

Planning Act 2008 is based on clear principles

  • Clear and statutory timetable
  • National Policy addresses need

and principles

  • Front loaded
  • Predominantly Written

Representations

  • Development as applied for

(Development Consent Order)

slide-5
SLIDE 5
  • Clear and statutory timetable
  • National Policy addresses need and

principles

  • Front loaded
  • Predominantly Written Representations
  • Development as applied for

(Development Consent Order)

Planning Act 2008 is based on clear principles

slide-6
SLIDE 6

Pre-Application

Led by the Developer A chance to influence what the project looks like A Statutory Requirement

DEVEL DEVELOPE OPER

slide-7
SLIDE 7

Acceptance

28 Day Deadline We will ask Local Authorities for views Consultation must be adequate, and application must be satisfactory for examination

DEVEL DEVELOPE OPER

slide-8
SLIDE 8

Register to participate in the Examination Inspector(s) appointed ASAP and will issue a draft timetable A Preliminary Meeting to discuss the timetable

Pre-Examination

DEVEL DEVELOPE OPER

slide-9
SLIDE 9

Examination

A strict timetable for submissions A bespoke setup of hearings, to suit the case Cannot last more than 6 months

DEVEL DEVELOPE OPER

slide-10
SLIDE 10

Reporting

The Inspector(s) consider and draft their report They will make a recommendation to the Secretary of State Cannot last more than 3 months

DEVEL DEVELOPE OPER The Planning he Planning Inspector Inspectorate te

slide-11
SLIDE 11

Decision

Decision made by Secretary of State – an elected Government Minister Decision is final, but can be challenged in the courts 3 months from receiving the report

DEVEL DEVELOPE OPER The Planning he Planning Inspector Inspectorate te Minis iniste ter

slide-12
SLIDE 12

Statutory Timescales

PRE-APPLICATION EXAMINATION DECISION acceptance pre-examination reporting

DEVEL DEVELOPE OPER The Planning he Planning Inspector Inspectorate te Minis iniste ter

Up to 2+ years 6 Months 3

Months

3

Months

c.3

Months 1 Month

Applications are considered and determined in predictable stages, within predictable timescales

slide-13
SLIDE 13

Statutory Timescales

  • Respond to pre-application consultation to

influence the scheme

  • Register at Pre-Examination to participate in

the examination

  • Participate in the Examination to influence the

decision

Summary

slide-14
SLIDE 14

Perspectives

Local Authorities

Ensure local views are taken account

  • f (political)

Development Plan policies followed Alternatives? Resources and business continuity Land owner? Robust mitigation measures

PINS (ExA)

Fair, transparent process for everyone involved Balance local impacts against national need Consider the application as made Gathering evidence to be able to make a well-reasoned recommendation Complete the examination within statutory time limits

slide-15
SLIDE 15

Local Impact Report Statement of Common Ground Written Representation(s) Pre App / Existing Evidence Base / Dev’t Pan

Key examination documents / submissions

slide-16
SLIDE 16

Resources

Joint

working with

  • ther

Councils

Be proactive – Preliminary Meeting

Concise and Proportionate End of the examination is busy Discharge of requirements / enforcement Understand the examination timetable

PPA

SoCG / s106 / LIR / Requirements

slide-17
SLIDE 17

Legislation / Guidance / Advice

  • Planning Act 2008

and Regulations / Rules

  • DCLG Guidance

(statutory)

  • PINS Advice Notes

(non statutory)

slide-18
SLIDE 18
  • Advice Note 1: Local

Impact Reports

  • NEW! Advice Note 2:

The role of local authorities in the development consent process

slide-19
SLIDE 19

Hinkley Point C Application

Submitted 31 Oct 2011 Circa 46,000 pages 800 Plans Accepted for examination

  • n 24 Nov

2011

slide-20
SLIDE 20

HPC Examination

21 March 2012 to 21 Sept 2012 (6 months)

3 days of accompanied site visits 15 days of hearings 2150 examination documents submitted

Principal Issues Traffic; Socio Economic; Landscape / Visual Impact; Combwich (site specific); Dev’t Consent Order

1600 Interested Parties (1200 registrations)

slide-21
SLIDE 21

“…we drew attention to the fact that our initial assessment of the principal issues did not include matters such as nuclear safety, security, protection of people and the transport of nuclear material. We explained that it was not our intention to duplicate the consideration of matters which are within the remit of the bodies responsible for nuclear regulation.”

Hinkley Point C Panel Report (para 1.5) - 19 Dec 2012

slide-22
SLIDE 22

DCO pre-Consultation DCO Application GDA Initial Assessment GDA Assessment Nuclear Site Licence Environmental Permits

2007 2008 2009 2010 2011 2012 2013 Hinkley Point C Nuclear Power Station - Consents

Steps 1&2 Steps 3 & 4

Application Engage

Stage 1

Stage

2 Stage 2

Update Application Application Application Grant

Licence

Permits Interim

DAC SoDA

DAC

SoDA

slide-23
SLIDE 23

Sizewell B s34(1) Electricity Act 1957

  • Duration of Public Inquiry: 2y 3m

(Jan 1983 to Mar 1985)

  • SoS Decision: Aug 1987
  • Time Taken: 4.5 Years

Hinkley Point C Dev’t Consent Order

  • Duration of Examination: 6 months

(Mar 2012 to Sep 2012)

  • SoS Decision: Mar 2013
  • Time Taken: 1 Year