Oversight at NSFs Operating Large Facilities Christopher Weber, - - PowerPoint PPT Presentation

oversight at nsf s operating large facilities
SMART_READER_LITE
LIVE PREVIEW

Oversight at NSFs Operating Large Facilities Christopher Weber, - - PowerPoint PPT Presentation

Oversight at NSFs Operating Large Facilities Christopher Weber, Kristen Koopman, Kristen Kulinowski, Stephanie Shipp April 23, 2013 Chartered by Congress in 1991 to provide rigorous objective advice and analysis to Office of Science and


slide-1
SLIDE 1

Oversight at NSF’s Operating Large Facilities

Christopher Weber, Kristen Koopman, Kristen Kulinowski, Stephanie Shipp April 23, 2013

slide-2
SLIDE 2
  • Chartered by Congress in 1991 to provide rigorous
  • bjective advice and analysis to Office of Science and

Technology Policy (OSTP) and other Executive Branch agencies, offices, and councils

  • Provide analyses of national science and technology

issues of interest to OSTP and

  • ther Executive Branch agencies
  • IDA began operating the Science and

Technology Policy Institute (STPI) in 2003

4/24/2013 1

slide-3
SLIDE 3

Presentation Outline

  • Project Background
  • Study questions
  • Approach/project schedule
  • Findings by Study Question
  • Recommendations
  • Discussion/Questions

2

slide-4
SLIDE 4

Project Background

  • NSF sponsored STPI to examine oversight

issues related to operating large facilities

  • First time such a study had been attempted

– Challenge for NSF and STPI of identifying and gathering data for first time

  • Facilities Working Group (POs) defined study

questions November 2011 (next slide)

  • Study completed June-August 2012

3

slide-5
SLIDE 5

Study Questions

  • Central Question: What steps can be taken to streamline NSF
  • versight review of operating facilities?
  • Sub-questions:

– What are the different assessments (particularly including reviews but also including site visits and audits) that occur during the operational phase across NSF facilities, and by which NSF units? – What are the goals for these assessments (including: what decisions must be made on the basis of each), how do they sequence, and where are there

  • verlaps in goals and timing?

– On a representative case basis, what are the typical resource cost factors, particularly including person-time, associated with preparing for, executing, evaluating and acting on recommendations of reviews? – Are there important differences in review/oversight approaches that depend

  • n the features/attributes of the facilities?

4

slide-6
SLIDE 6

Approach Summary

5

Study Questions Interviews with Program Officers (Case Studies) Interviews with Awardees (Case Studies) Analysis of Cooperative Agreements (all

  • perating facilities)
  • 1. What are the different assessments

(particularly including reviews but also including site visits and audits) that occur during the

  • perational phase across NSF facilities, and by

which NSF units? 

  • 2. Are there important differences in

review/oversight approaches that depend on the features/attributes of the facilities? 

  • 3. What are the goals for these assessments

(including what decisions must be made on the basis of each), how do they sequence, and where are there overlaps in goals and timing?  

  • 4. On a representative case basis, what are the

typical resource cost factors, particularly including person-time, associated with preparing for, executing, evaluating, and acting on recommendations of reviews?   Central Question: What steps can be taken to streamline NSF oversight review of operating facilities?    Note: Questions were reordered from the original list for ease of presentation.

slide-7
SLIDE 7

Scope of Oversight Considered

  • Clear interest in NSF reviews, including BSR
  • PO interviews showed many using reports in
  • versight
  • Guidance led to limiting to programmatic
  • versight (exclude audits) except BSR
  • Internal governance vs. oversight? Oversight if:

– Required by CA – PO participates or receives reports from body – Awardee considers it part of NSF oversight

6

slide-8
SLIDE 8

Facilities Chosen for Case Studies

7

Facility Sites Mobile Yearly Operations Budget (FY12, $M) Directorate Division Partnerships Atacama Large Millimeter Array/National Radio Astronomy Observatory 1/12 N/N $72 R&RA, $3 MREFC MPS AST IN EarthScope 1600 N $26.2 GEO EAR IA Incorporated Research Institutions for Seismology 150 N $11.3 GEO EAR IA Integrated Ocean Drilling Program 1 Y $38.9 GEO OCE IN Laser Interferometer Gravitational-wave Observatory 2 N $30.5 R&RA, $21 MREFC MPS PHY

  • National Optical Astronomy

Observatory 2 N $25.5 MPS AST IA National Solar Observatory 8 N $8 R&RA , $10M MREFC, MPS AST IA Network for Earthquake Engineering Simulation 14 N $20.5 ENG CMMI IAIN

Note: facilities anonymized in results slides

slide-9
SLIDE 9

FINDINGS

8

slide-10
SLIDE 10

Q1: What are the different assessments (particularly including reviews but also including site visits and audits) that occur during the operational phase across NSF facilities, and by which NSF units? Q2: Are there important differences in review/oversight approaches that depend on the features/attributes of the facilities?

slide-11
SLIDE 11

What are the different assessments across facilities?

  • Documents examined:

– Cooperative Agreements and Contracts – Programmatic Terms and Conditions – General Financial and Administrative Terms and Conditions

  • Supplemental FATC for Managers of Large Facilities and

FFRDCs

– Project Solicitations – Governance documents (for international collaborations) – Input from case studies

10

slide-12
SLIDE 12

Facilities use different language to describe oversight

  • Generally three kinds of oversight:

– NSF-organized reviews – Reports submitted to the NSF – Internal governance conducted by the awardee

  • Within these categories, oversight procedures

covering similar content still had different names

– Necessitated creation of a taxonomy

11

slide-13
SLIDE 13

Creation of a Taxonomy for Oversight

  • Example taxonomy for NSF-organized reviews:

12 Review Category Description Terms found in CAs Program A comprehensive review including science, often reviewing project planning documents. Program review panel, review of science and facility programs, site visits Operations A review focused on facility

  • peration or technical operation.

Operations merit review, merit review site visit of facility

  • perations, operations and maintenance review,

maintenance and operations review Management A review focused on the overall management of the facility and the performance of the management

  • rganization.

Management performance review, interim management review, review of management and operations, in-depth review of management, review of management performance Transition A review covering the transition between awardees or stages of the project. Transition Review BSR An NSF Business Systems Review. Business Systems Review Proposal A proposal review in preparation for a renewal. (Not included in CAs) Other Other reviews; largely those without enough detail provided to categorize properly. On-site review, annual review, review

slide-14
SLIDE 14

Some CAs provide flexibility in

  • versight requirements

13

  • Frequency requirements are not always absolute:

10 of 18 facilities use “at least” to specify frequency

  • Five facilities require the BSR “as deemed

necessary”

  • Some facilities have other language for flexibility

(allowing content and scheduling of review to be determined during the award, combining a quarterly report with an annual report, allowing the final report to take the place of the annual report for the final year, etc)

slide-15
SLIDE 15

NSF’s oversight is unique to each facility

  • Different CAs require different types of

reviews at different frequencies

  • All facilities require a retrospective annual

report

  • Most (but not all) CAs require a forward-

looking annual program plan

  • Internal governance very facility-specific

14

slide-16
SLIDE 16

No trends based on size or age

Weak correlation between facility size (as measured by funding request) and annualized number

  • f reviews

Weak correlation between facility age and annualized number of reviews

15

0.5 1 1.5 2 2.5 3 3.5 4 4.5 5 $- $20 $40 $60 $80 $100 Number of NSF Reviews FY2013 Funding Request 0.5 1 1.5 2 2.5 3 3.5 4 4.5 5 1950 1960 1970 1980 1990 2000 2010 2020 Number of NSF Reviews Start Year of Facility

slide-17
SLIDE 17

Directorates/Divisions can have similar requirements

  • Only trends at Division and Directorate level

– Networked facilities in ENG facilities tend to have multiple reviews per year due to structure – AST facilities tend to have common annual program review, 5-year management review, and internal governance similarities

  • Many potential reasons for differences:

– tradition, facility structure, awardee preferences, PO preferences – Determining actual reasons requires further study

16

slide-18
SLIDE 18

Q3: What are the goals for these assessments (including: what decisions must be made on the basis of each), how do they sequence, and where are there

  • verlaps in goals and timing?

1 Scope 2 Timing

slide-19
SLIDE 19

Findings: Goals of Oversight

  • NSF oversight includes different activities to

different parties

– Awardees often considered governance bodies to be oversight – Not consistent across facilities even within Divisions/Directorates – More study needed across more facilities

18

slide-20
SLIDE 20

Are There Overlaps in Scope?

  • Perceptions highly varied between POs and

awardees; roughly half said no overlap

  • BSRs and renewal proposals seen as highly

burdensome (even though less time invested than in other types)

19 Facility PO Awardee 1 Yes, BSR/Mgmt Yes, Internal/Mgmt 2 Yes, BSR/Mgmt, Mgmt/Renew Yes BSR/Mgmt 3 No overlap No overlap 4 No overlap Yes, Ops/Internal 5 Yes, BSR/Mgmt Yes, Program/Internal 6 No overlap Yes, BSR/A133 Audits 7 No overlap No overlap 8 Yes, BSR/Mgmt Yes, Program/Internal

slide-21
SLIDE 21

Other Scope Findings

  • Link between programmatic reviews and

recompetition decision is unclear

  • Review charges show considerable variation in

types of questions and level of detail

– Level of detail probably a function of history, previous review results – Is more detail helpful?

  • Most POs would welcome guidance from LFO to

reduce overlap

– Particularly related to overlap with BSR – Guidance needed on point of management reviews

20

slide-22
SLIDE 22

Timing: Findings

  • Considerable temporal overlap between multiple

reviews and between reviews, reports, and internal oversight

– All case studies showed some overlap – Most often with BSR and renewal process – Burden different at different times of process

  • POs try to avoid such timing issues but not always

possible

– Combining reviews/reports – Postponing reviews

21

slide-23
SLIDE 23

Timing: Examples

22

CY FY Type

10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9

Board

IN IN IN IN IN IN IN IN IN IN IN IN IN IN IN IN IN

IntAdv

IC IC IC IC IC IC IC IC IC IC IC IC IC IC IC IC IC IC IC IC IC IC IC IC IC IC IC IC IC IC IC IC IC IC IC IC IC IC IC IC IC IC IC IC IC IC IC IC IC IC IC IC IC IC IC IC IC IC IC IC

Mgmt SV

NM NM NM NM NM NM NM NM

Mgmt Ext

NM NM NM NM NM NM

Renew

NM NM NM NM NM NM NM NM

BSR

NB NB NB NB NB NB NB NB NB NB NB NB NB NB NB NB NB

Ann Rept

AR AR AR AR AR AR AR AR AR AR

Qsci

QR QR QR QR QR QR QR QR QR QR QR QR QR QR QR QR QR QR QR QR QR QR QR QR QR QR QR QR QR QR QR QR QR QR QR QR QR QR QR QR 2013 2008 2009 2010 2011 2012 2009 2010 2011 2012 2013

CY FY Type

10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3

Int Prog IC IC IC IC IC IC IC IC IC IC Int Mgmt IC IC Program NS NS NS NS NS NS NS NS NS Mgmt NM NM Portfolio NX NX Renew NM NM NM NM NM NM NM NM NM NM NM NM BSR NB NB NB NB NB NB NB NB Ann Rept AR AR AR AR AR Ann Plan AR AR AR AR AR AR AR AR AR AR LR Plan AR AR AR AR AR AR AR AR Qsci QR QR QR QR QR QR QR QR QR Qfin QR QR QR QR QR QR QR QR QR QR QR QR QR QR QR QR QR QR 2010 2011 2012 2013 2014 2014 2009 2010 2011 2012 2013

slide-24
SLIDE 24

Q4: On a representative case basis, what are the typical resource cost factors, particularly including person-time, associated with preparing for, executing, evaluating, and acting on recommendations of reviews?

slide-25
SLIDE 25

Substantial awardee time involved with NSF oversight, 1 to 10 FTEs

24

0.0 1.0 2.0 3.0 4.0 5.0 6.0 7.0 8.0 9.0 10.0 1 2 3 4 5 6 7 8 FTE employees Subannual Reports Annual Reports Internal NSF BSR NSF Reviews 0.00 0.05 0.10 0.15 0.20 0.25 1 2 3 4 5 6 7 8 FTE employees/$M

slide-26
SLIDE 26

Person-time Between Facilities

  • Some variability based on facility age

– Could account for trends within Directorates – Number of required reviews not correlated to age, but older facilities tended to have lower estimated burden

  • Caveat: small sample size and mostly

estimates

25

slide-27
SLIDE 27

Awardee Person-time Between Categories

  • Reporting largest time sink (51%

average)

– Compare 14% NSF reviews, 11% internal – Some facilities consider subannual reports essential for management

  • Large variation between facilities

– Reporting 20%-95% – Reviews <5%-50% – Internal 0%-60%

  • Most awardee comments on

BSR/renewal

– Different staff involved (director less involved in subannual reporting) – More pressure (renewal/recompetition)

26 0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% 1 2 3 4 5 6 7 8 Subannual Reports Annual Reports Internal NSF BSR NSF Reviews

slide-28
SLIDE 28

RECOMMENDATIONS

27

slide-29
SLIDE 29

Study Recommendations (1)

  • Standardize oversight terminology and scopes

– LFO working with Directorates and Divisions – Will help share best practices

  • Clearly communicate oversight requirements

to facilities during the development of CAs

– Insert language for flexibility where appropriate

  • To the extent possible, schedule oversight

upfront (during CA development) to avoid

  • verlap

28

slide-30
SLIDE 30

Study Recommendations (2)

  • Consider internal oversight in total oversight burden

– POs, Directorates, and LFO should include these activities in scheduling and designing oversight

  • Conduct further study to understand how internal

governance activities could contribute to NSF oversight goals

  • Clarify the role of management reviews in the context
  • f recompetition decisions

– Discuss need and purpose of management reviews if recompetition decision made prior to or apart from review

29

slide-31
SLIDE 31

Acknowledgements

  • Funding provided by NSF Large Facilities Office
  • Thanks to:

– Bill Miller, LFO for direction – Other LFO staff for feedback and information – POs and Awardees for speaking with us!

  • Co-authors: Stephanie Shipp, Kristen

Kulinowski

30

slide-32
SLIDE 32

Questions

  • ?

31