Options for Energy Buyers Options for Energy Buyers Bloomberg - - PowerPoint PPT Presentation

options for energy buyers options for energy buyers
SMART_READER_LITE
LIVE PREVIEW

Options for Energy Buyers Options for Energy Buyers Bloomberg - - PowerPoint PPT Presentation

Options for Energy Buyers Options for Energy Buyers Bloomberg Offices Bloomberg Offices 8 November 2006 8 November 2006 Centrica Storage Limited Rough Storage use for Winter 06 and beyond 1. Introductions to CSL 2. The role of storage in


slide-1
SLIDE 1

Options for Energy Buyers Options for Energy Buyers Bloomberg Offices Bloomberg Offices

8 November 2006 8 November 2006

Centrica Storage Limited

slide-2
SLIDE 2

2

Rough Storage use for Winter 06 and beyond

1. Introductions to CSL 2. The role of storage in GB 3. Rough Recovery

  • Options for Energy Buyers (1) – Rough Update

4. Storage Outlook for Winter 06 5. Options for Energy Buyers (2) – Use storage information 6. Options for Energy Buyers (3) Valuing Rough Storage 7. Operating with Rough Storage in your portfolio

slide-3
SLIDE 3

3

An introduction to Centrica Storage

  • Centrica Storage Limited is a wholly owned subsidiary of Centrica plc
  • Centrica Storage is a ring-fenced part of Centrica plc, separated from

the supply side legally, physically and financially (Chinese walls). Undertakings agreed with Secretary of State December 2003 governing operation of Rough

slide-4
SLIDE 4

4 47/8A Installed 1977 6 wells 24/7 Operation Easington Terminal Rough gas processing Amethyst gas processing Tie in to National Transmission System 24/7 Operation Hedon, near Hull Administration/engineering Venture House, Staines Headquarters and Commercial

  • ffice

24/7 Operation

AMETHYST

10 20 km

EASINGTON TERMINAL 29 km @ 36" 29 km @ 16"

ROUGH

York

47/3B Installed 1983 24 wells 24/7 Operation

Introduction to CSL - Facilities overview

slide-5
SLIDE 5

5 Rough York

Easington Terminal To National Transmission System

36” Pipeline Riser Shaft

AP BD BP CD AD

16” Pipeline 36” Submarine Pipeline 18 Miles 18”Inter-field Pipeline 1.25 Miles

47/3B 47/8A

  • Represents 74% of UK

storage and supplies 10% of UK peak winter demand

  • Largest offshore gas storage

facility in Western Europe (strategically important).

  • 185 billion cubic feet

(bcf) cushion gas

  • ~118 bcf storage

capacity

  • Deliverability max

44.8mcm/day

  • Average Injection

~15mcm/day

  • Onshore processing

terminal at Easington for Rough, Amethyst, Rose and Helvellyn processing (third party gas).

Introduction to Centrica Storage – Process Overview

slide-6
SLIDE 6

6

Actual GB Load Duration Curve 05/06

50 100 150 200 250 300 350 400 450 1 26 51 76 101 126 151 176 201 226 251 276 301 326 351 m cm Beach Supply Isle of Grain IUK Rough MRS SRS Rough injection Supply 04/05

Storage Year 05/06

Rough Injections Rough Injections

Rough storage is used to provide seasonal swing to the market

Continued indigenous production declines

Storage prices from market spread

slide-7
SLIDE 7

7

200 400 600 800 1000 1200 1400 1 16 31 46 61 76 Time to empty - Days GWh Glenmavis Partington Avonmouth Dynevor Arms Hole House Farm Hornsea Hatfield Moor Humbly Grove Rough

Existing UK Storage Facilities Winter 05/06 Rough

Winter 06/7 Humbly Grove available for the Winter More deliverability from Hole House

slide-8
SLIDE 8

8

Rough’s place in the storage and gas market

Storage Capacity Rough 74% Hafield Moor 3% Hornsea 8% Humbly Grove 7% Hole House 1% National Grid LNG 7%

Deliverability Rough 35% Hafield Moor 2% Hornsea 15% Humbly Grove 6% Hole House 2% National Grid LNG 40% Average Injection - Summer 06 Rough 66% Hafield Moor 4% Hornsea 8% Humbly Grove 6% Hole House 13% National Grid LNG 3%

slide-9
SLIDE 9

9

Recovery Program - Statistics

Phased Recovery completed to plan

  • Phase 1 – remanning: full extent of damage unknown, installations ‘black’
  • Phase 2 – reinstatement of injection operations
  • Phase 3 – reinstatement of production operations
  • Potential for reoccurrence eliminated

Over 400,000 man-hours worked Safety

  • Zero lost time accidents
  • No Safety or Environmental incidents

Quality

  • >500 Flange Joints made
  • No hydrocarbon leaks, minimal rework - start up first time to plan

Time

  • Phase 2 - 112 Days from incident to recommence injection
  • Phase 3 - 217 Days from incident to become production ready

Cost

  • Circa £30 million project

Execution

  • Planned, resourced, managed and implemented by CSL
slide-10
SLIDE 10

10

CSL – Rough Flows

Net Storage Movement

  • 300,000,000
  • 200,000,000
  • 100,000,000

100,000,000 200,000,000 300,000,000 400,000,000 500,000,000 600,000,000 01/01/05 01/02/05 01/03/05 01/04/05 01/05/05 01/06/05 01/07/05 01/08/05 01/09/05 01/10/05 01/11/05 01/12/05 01/01/06 01/02/06 01/03/06 01/04/06 01/05/06 01/06/06 01/07/06 01/08/06 01/09/06 01/10/06 01/11/06

  • Near 100% reliability for 2005
  • High summer load factor on injection 2005
  • Highest withdrawal rate 492 GWh
  • Sand monitoring & 8 Alpha
  • Highest volume injected in a season
  • Release of peak production rates Nov-Jan
  • Cycling from November to late January

£ £50> million spent on Rough by CSL to date! 50> million spent on Rough by CSL to date!

  • Near 100% load factor on injection
  • High level of availability
  • Inj Rates higher than forecast
  • Original space targets met
  • Production tested – 5th October
  • Production starts – 2nd November

Facility closed for repairs

slide-11
SLIDE 11

11

B D B P C D

  • Heli-deck
  • Accommodation
  • 12 wells
  • All gas processing facilities
  • Gas compression (injection)
  • Main power generation
  • 12 wells

Centrica Storage Limited – New Production Process

slide-12
SLIDE 12

12

Process Changes Bypassing dehydration and running sealine wet

  • Modifications based upon running the Rough 36” sea line ‘wet’
  • Bypass the Rough 3B Glycol Dehydration Trains
  • Installation of large header and return pipework
  • Glycol Contactors, Production Separators and Glycol Regeneration

Packages become redundant

  • ESD System extensively modified to reflect changes
  • Install new Hydrate / Corrosion Inhibitor Chemical Injection Skid on both

Rough 8A and Rough 3B

  • Two Injection aftercoolers modified to eliminate failure mode and return to

four injection cooler operation

  • Outcome:
  • Offshore production process simplified
  • Injection aftercooler duty improved
  • Pipeline corrosion management regime enhanced
slide-13
SLIDE 13

13

1st NOVEMBER – ROUGH STORAGE FULL 116.5 bcf! (78 day service)

  • FM on Injection lifted from Gas Day 18th July 2006
  • Rough returned to injection early June – 112 days after the FM
  • Since the return to physical injection operations in June CSL has

filled in excess of 58 bcf of space before the end of winter

  • Full production rates available following the return from annual

maintenance in September

  • All production trains were tested in turn 5th October 2006
  • Commercial withdrawals began 2nd November 2006!
slide-14
SLIDE 14

14

Options for Energy Buyers (2) - Storage Information

  • http://www.nationalgrid.com/uk/Gas/Data/misc/
  • http://storit.centrica-sl.co.uk (aggregate site nominations within day)
  • CSL supportive of attempts to drive forward transparency in the UK and Europe

where appropriate

slide-15
SLIDE 15

15

Purchases Sales

Initial Hedge Shape to give 2.27 x (Q1-Summer) p/SBU Optimal hedge Shape to give 2.4 x (Q1-Summer) p/SBU D J F M A M J J A S

The Q1-Summer spread fits the shape of the SBU and provides a good hedge in forward markets. Summer Contract Q1 Contract Once market monthly contracts trade one can optimise position to fit optimal profile

Options for Energy Buyers (3) – Book storage Rough – SBU pricing and intrinsic value

Standard Bundled Unit (SBU) Withdrawal 1 kWh/day Space 67 kWh Injection 0.35 kWh/day 455m SBU’s sold 1 SBU provides space equivalent to 2.27 therms

slide-16
SLIDE 16

16

Note: Each SBU contains 2.27 therms, therefore to convert from pence/SBU into pence/Therm divide by 2.27

Unlocking the extrinsic value

Extrinsic Intrinsic

2.27 2.4 2.8 to 3.2

Sales activity range

Poor Rough Reliability Injection Cancellation Long Injection Period Force Majeure Good Rough Reliability from high availability

  • f the asset to CSL and customers

Customers able to reshape the CSL product or sell/buy unused capacity as firm or interruptible Customers able to buy/sell gas in store Ability to re-nominate withdrawal/injection with short lead times Customers nominated quantities equal their allocated quantities – irrespective of asset availability Market volatility provides cycling ability to leverage greater value from a Rough SBU Extrinsic value from use of Rough on 100+ days beyond intrinsic valuation Potential upside to 2.4 intrinsic as Dec – Mar spread increases on Fundamental change to winter contract Re-optimise hedge in more liquid market – further intrinsic value Initial Intrinsic Hedge in product-limited market fits shape of Rough

slide-17
SLIDE 17

17

Site Map

Nominations Capacity Management Inventory and Allocation Billing Overview Enter Nomination View Nomination View Profile Activity report Enter Transfer View Transfer Accept Transfer Capacity Transfer Capacity Availability Enter Transfer View Transfer Accept Transfer View Inventory View Charges Centrica Storage Bulletins Public Bulletins Private Bulletins Bulletin Board View Bulletin Enter Bulletin Edit Bulletin Administration (AR functions) Change Password New Account Edit Account

slide-18
SLIDE 18

18

Nomination

STORI T

Allocation

Within the Gas Day Before the gas day After the gas day

slide-19
SLIDE 19

19

Summary

  • Storage has a key role to play in efficient gas market and

balancing

  • Market responding to need for more storage - duration

still an issue but far better placed for demand/supply shocks in future

  • Subject to planning consents!
  • Increased interconnection may increase the potential for

storage cycling

  • CSL has spent £50m> investing in Rough and plans to

spend more

  • Rough was full before the onset of Winter
  • Rough back producing/storing our customers gas
slide-20
SLIDE 20

20

Centrica Storage Limited

WHY SHOULDN’T LARGE GAS USERS BUY STORAGE CAPACITY..?

QUESTIONS…? www.centrica-sl.co.uk Sales and Marketing Information/Queries:

James Lawson +44 (0) 1784 415 304

Analysis Queries:

Andrew Prangley +44 (0) 1784 415 324 Jitendra Patel +44 (0) 1784 415 339 Stuart Waudby +44 (0) 1784 415 305 Email: firstname.lastname@centrica-sl.co.uk