Operational readiness in transition Sven Ternov, LFV/Swedavia Barry - - PowerPoint PPT Presentation

EUROCONTROL Safety R&D Seminar Operational readiness in transition Sven Ternov, LFV/Swedavia Barry Kirwan, EEC Paul Humphreys, EEC Safety R&D Seminar Page 1 / Total_number 25-27 Otober 2006 EUROCONTROL Barcelona - SPAIN


slide-1
SLIDE 1

Safety R&D Seminar EUROCONTROL 25-27 Otober 2006 Barcelona - SPAIN Page 1 / Total_number

EUROCONTROL Safety R&D Seminar

Operational readiness in transition

Sven Ternov, LFV/Swedavia Barry Kirwan, EEC Paul Humphreys, EEC

slide-2
SLIDE 2

Safety R&D Seminar EUROCONTROL 25-27 Otober 2006 Barcelona - SPAIN Page 2 / Total_number

EUROCONTROL Safety R&D Seminar

Introduction Many ANSP’s gone through transition to new ATS systems, quite a few are planning to do so. Shall everybody make their own mistakes? Or might there be lessons learned?

slide-3
SLIDE 3

Safety R&D Seminar EUROCONTROL 25-27 Otober 2006 Barcelona - SPAIN Page 3 / Total_number

EUROCONTROL Safety R&D Seminar

Methods and material I ■ 4 ANSP’s having gone through transition ■ 2 non ATS organisations having gone through transition ■ 2 ANSP’s to validate the results

slide-4
SLIDE 4

Safety R&D Seminar EUROCONTROL 25-27 Otober 2006 Barcelona - SPAIN Page 4 / Total_number

EUROCONTROL Safety R&D Seminar

Method ■ Semistructured interviews

  • Controllers not involved in project
  • Controllers involved in project
  • Line (middle) management
  • Senior management (Hq)

■ Questions prior to visit

slide-5
SLIDE 5

Safety R&D Seminar EUROCONTROL 25-27 Otober 2006 Barcelona - SPAIN Page 5 / Total_number

EUROCONTROL Safety R&D Seminar

7 9 7 8 Total 1 2 4 Senior management 2 2 2 Middle management 2 3 4 1 Controllers involved in project 2 4 1 1 Controllers not involved in project ANSP 3 Site D ANSP 2 Site C ANSP 2 Site B ANSP 1 Site A Interviewed staff

slide-6
SLIDE 6

Safety R&D Seminar EUROCONTROL 25-27 Otober 2006 Barcelona - SPAIN Page 6 / Total_number

EUROCONTROL Safety R&D Seminar

Site description

Site A Site B Site C Site D

Transition to the new system in 2001, which already had been implemented at the countries airports, i.e. a system that was already working. Transition to new system in 2003. The site is an en- route and approach centre, interfacing with

  • ceanic airspace

Transition to new system in 2003, at the same time as site B. Site C is mainly TMA and approach Transition to new system, contract signed 1997, went

  • perational

March 2005. Stripless system. Site D site is mainly en route and TMA,

slide-7
SLIDE 7

Safety R&D Seminar EUROCONTROL 25-27 Otober 2006 Barcelona - SPAIN Page 7 / Total_number

EUROCONTROL Safety R&D Seminar

SAS

Transition to Airbus fleet

■ Project managers picked from the line ■ Some waste of time due to lack of project managerial skills ■ No learning from earlier transition projects ■ Pool of trained project managers desirable

slide-8
SLIDE 8

Safety R&D Seminar EUROCONTROL 25-27 Otober 2006 Barcelona - SPAIN Page 8 / Total_number

EUROCONTROL Safety R&D Seminar

Barsebäck

Shutting down of the remaining reactor ■ Transition went very well ■ Transition management on site ■ High in house competency for managing transitions

slide-9
SLIDE 9

Safety R&D Seminar EUROCONTROL 25-27 Otober 2006 Barcelona - SPAIN Page 9 / Total_number

EUROCONTROL Safety R&D Seminar

ANSP’s ■ Two good transitions, two bad transitions ■ Results in accordance with each other ■ Very difficult to make ANSP’s participate in study

slide-10
SLIDE 10

Safety R&D Seminar EUROCONTROL 25-27 Otober 2006 Barcelona - SPAIN Page 10 / Total_number

EUROCONTROL Safety R&D Seminar

Success factors I

■ Professional project management ■ Project location physically located at the site for the transition ■ Recruit interested controllers from the site early (specifications phase) ■ Use these controllers as trainers later on ■ Inform other controllers as soon as possible concerning the project status

slide-11
SLIDE 11

Safety R&D Seminar EUROCONTROL 25-27 Otober 2006 Barcelona - SPAIN Page 11 / Total_number

EUROCONTROL Safety R&D Seminar

Success factors II

■ Keep on with informing controllers on a regular (monthly) basis ■ Engage other controllers on hands-on exercises as soon as possible, but not before the system is sufficiently mature ■ Do whatever else you can to obtain controller confidence in the new system, and thus avoiding rumours.

slide-12
SLIDE 12

Safety R&D Seminar EUROCONTROL 25-27 Otober 2006 Barcelona - SPAIN Page 12 / Total_number

EUROCONTROL Safety R&D Seminar

Validation of results

Validation site A (transition 2003) ■ All key issues covered Validation site B (transition 2007) ■ Very valuable for us, will use the report as checklist

slide-13
SLIDE 13

Safety R&D Seminar EUROCONTROL 25-27 Otober 2006 Barcelona - SPAIN Page 13 / Total_number

EUROCONTROL Safety R&D Seminar

Safety in transition

■ A badly handled transition can constitute a hazard ■ Non-confident controllers can constitute a hazard ■ Controllers are good at identifying hazards

slide-14
SLIDE 14

Safety R&D Seminar EUROCONTROL 25-27 Otober 2006 Barcelona - SPAIN Page 14 / Total_number

EUROCONTROL Safety R&D Seminar

Generic process model

The EEC report ”A SAFE APPROACH TO TRANSITION: KEY ELEMENTS FOR TRANSITION SUCCESS”, EEC, 2006 ■ More than 50 critical items for transition success ■ A generic process model for transition ■ A time line for transition, beginning 4 years before O-day, ending 2 months after transition.

slide-15
SLIDE 15

Safety R&D Seminar EUROCONTROL 25-27 Otober 2006 Barcelona - SPAIN Page 15 / Total_number

EUROCONTROL Safety R&D Seminar

Safety in transition II

■ Before O-day: robust procedures for catching controller concerns, swift feed-back ■ After O-day: Effective incident reporting system implemented