FINAL MARKET READINESS PROPOSAL: INDONESIA
Final Market Readiness Proposal Country: Indonesia FINAL MARKET - - PowerPoint PPT Presentation
Final Market Readiness Proposal Country: Indonesia FINAL MARKET - - PowerPoint PPT Presentation
Final Market Readiness Proposal Country: Indonesia FINAL MARKET READINESS PROPOSAL: INDONESIA Introduction: MRP Focus Core Technical and Institutional Readiness Components in Power and Industry Sectors: Emission profile and baseline
FINAL MARKET READINESS PROPOSAL: INDONESIA 2
Introduction: MRP Focus
- Core Technical and Institutional Readiness
Components in Power and Industry Sectors:
- Emission profile and baseline setting
- MRV system development and piloting in electricity
generation and cement production
- Planning for a Market-based Instrument:
- Technical assessment and policy consultation on
market instrument
- Piloting the selected instrument
FINAL MARKET READINESS PROPOSAL: INDONESIA 3
Introduction: MRP Objective
The Objectives: To understand and determine the type
and scope of appropriate market-based instruments; to prepare supporting draft regulation as needed; to design and establish market infrastructures; to build required capacity of participating institutions and individuals.
The Long Term Goal: The establishment of new market
mechanisms or market based instruments to scale-up mitigation actions in Indonesia based on country- specific conditions and international carbon market situations.
FINAL MARKET READINESS PROPOSAL: INDONESIA 4
Process of Revising MRP
Consultations with other ministries after PA6 Changes in MRP text to update its context, better
formulation of focus and objectives, as well as to address PA6 questions
Incorporate timeline, list of activities and budget Presentation of final MRP to relevant ministries as the
result of MRP preparation works
FINAL MARKET READINESS PROPOSAL: INDONESIA 5
Joint Crediting Mechanism (JCM) between Indonesia
and Japan was established in August 26, 2013.
The new development will not affect PMR
Implementation Phase much. However, JCM experiences may provide knowledge and awareness to support Implementation Phase. Update on Context
FINAL MARKET READINESS PROPOSAL: INDONESIA 6
General feedback from PA6
- 1. Some of the figures in
Indonesia MRP presentation should be incorporated to the final proposal (figures in the slide number 40).
- 2. Need some clarifications on
PMR institutional arrangements.
- 3. Nusantara Carbon Scheme
and other new initiatives should be described clearer.
- 4. Need to consider the time
framing on the proposed schedule.
Feedback
- 1. Done.
- 2. Done.
- 3. Done. We put a text box to
describe the NCS.
- 4. Done. We already consult
with the ministries involved.
Follow Up
FINAL MARKET READINESS PROPOSAL: INDONESIA 7
Specific feedback from PA6
- 1. Elaborate as much as possible
the direction it expects to go in terms of emission trading, crediting, a combination of the two or something entirely new.
- 2. Include discussion on demand
and how it is expected to develop, and more details on bilateral relationship with Japan.
Feedback
- 1. Done. A text box of MBI is
already incorporated to the proposal.
- 2. Done. We put the latest
progress of JCM and its demand.
Follow Up
FINAL MARKET READINESS PROPOSAL: INDONESIA 8
MRV and data issues feedback from PA6
- 1. Express clarity on the work on
MRV for NAMAs by BAPPENAS
- r other ministries.
- 2. On data: explain emission data
from industries already
- btained and explain how
mitigation potential (sectoral) is determined.
- 3. On data collection: it is
important that the reporting entities understand the purpose of the data collection
Feedback
- 1. Responses on MRV are found
- n paragraphs: 114,116, Table
9, Table 10, paragraphs 124.
- 2. There is no further detail data
yet from the Ministry of Industries.
- 3. It’s explained on the
institutional tracks of the MRV development.
Follow Up
FINAL MARKET READINESS PROPOSAL: INDONESIA 9
Sector choices & baselines feedback from PA6
- 1. More discussion on the
selection process of narrowing the choice from 11 to 3.
- 2. Explain how this top down
target is with respect to bottom up activities that are being carried out.
- 3. More information on the
planned cap: what kind of cap is it, will it cover individual emission?
- 4. Explain whether there is lesson
learnt or possible synergy to be contributed to the success of this PMR activities.
Feedback Follow Up
- 1. It’s explained in para. 64, 65,
and 66
- 2. It’s explained in para. 70
- 3. It’s explained in para. 72
- 4. It’s explained in MBI Text Box
FINAL MARKET READINESS PROPOSAL: INDONESIA 10
Provide climate change policy context in Indonesia. Total GHG emission in 2020 is estimated to reach 2.95 GtCO2.
Forestry and peat will remain as major emissions sources until then, however, energy related emissions will have the highest growth rate.
Indonesia is committed to reduce GHG emissions by 26% below
BAU level in 2020 by its own resources. With international support, further emission reduction could achieve 41%.
An indicative list of activities to achieve the target is available
(RAN-GRK).
Market-based instruments can be a promising tool to cost-
effectively abate GHG emissions to support achievement of unilateral GHG emissions reduction target, or even beyond that.
Summary of Building Block 1
FINAL MARKET READINESS PROPOSAL: INDONESIA 11
Provide the process of target areas selection for PMR
Implementation Phase
The process involved considerations such as:
- Existing policies
- Emissions reduction potential
- Replicability
- Technology availability
- Investment effectiveness
- Stakeholder supports
- Issues in MRV
- Market sustainability
The selection process resulted two target areas for priority
sectors in PMR Implementation Phase: electricity generation and energy-intensive industries
Summary of Building Block 2
FINAL MARKET READINESS PROPOSAL: INDONESIA 12
The selection process provides logical framework for the MRP as summarized
below:
Summary of Building Block 2 (ctd.)
Framework; Scope; Mechanism & Governance; Guidelines; Piloting in Jamali & Cement Industry; Etc. MRV System in Power and Industry Sector Law No. 30/2007 of Energy Law No. 32/2009 of Environmental Protection GR No. 70/2009 of Energy Conservation PR No. 61/2011 of National Action Plan for GHG Reduction PR No. 71/2011 of National GHG Inventory MEMR No. 14/2012 of Energy Management MoI No. 14/2012 of GHG Reduction Road Map in Cement Industry PR No. 28/2008 of National Industry Policy Law No. 6/1994 of UNFCCC Ratification Energy Management System GHG Information Information for Policy Making
+
Policy Context Expected Output Expected Outcome Goal
Gap Analysis Cost & Benefit Analysis
Assessment; Selection; Design; Piloting; Etc. Market-based Instrument Design MBI Design + Piloting Best Practice Benchmark for Other Sector
FINAL MARKET READINESS PROPOSAL: INDONESIA 13
Describe the existing works and further works necessary to
develop a robust and reliable database useful for future target setting.
All activities to support this shall be participatory, transparent,
reliable and encourage consensus among stakeholders.
Summary of Building Block 3
Activities Budget Needed (USD) Requested (USD)
- A. Profiling Emissions in Power & Industry Sectors
A comprehensive carbon abatement cost curve in the two target areas. 700,000 300,000 A calculated / reviewed / estimated sectoral baseline emission of the target areas 250,000 100,000 Total 950,000 400,000
FINAL MARKET READINESS PROPOSAL: INDONESIA 14
Describe the activities to be conducted in order to develop a
working MRV system within power and industry sectors.
MRV system development works will be divided into Governance
Track and Piloting Track.
Governance Track will deal with policy support development,
institutional framework development, relevant guidelines development, data management, etc. to ensure the MRV system is workable dan sustainable. The development works will build upon the existing practice to the farthest extent as possible and appropriate.
Piloting Track will focus on fine tuning the MRV system taking into
account the participants circumstances.
All activities shall be participatory, transparent, reliable and
encourage consensus among stakeholders.
Summary of Building Block 3 (ctd.)
FINAL MARKET READINESS PROPOSAL: INDONESIA 15
Summary of Building Block 3 (ctd.)
Activities Budget Needed (USD) Requested (USD)
- B. MRV System Development (Governance Track)
Rules and regulations on MRV 450,000 250,000 Institutional set up for MRV 600,000 300,000 Capacity building and awareness raising activities 1,000,000 250,000 Total 2,050,000 800,000
- C. MRV System Development (Piloting Track)
Map of MRV activities at the installation level in Indonesia 200,000 100,000 Monitoring protocols 500,000 200,000 Data management system at the installation level 600,000 250,000 GHG emission data and review on MRV system at installation level and at aggregated data management level 400,000 100,000 Total 1,700,000 650,000
FINAL MARKET READINESS PROPOSAL: INDONESIA 16
Describe the activities to comprehensively assess, prioritize,
select, design and test market-based instrument in appropriate sector
All activities shall be participatory, transparent, reliable and
encourage consensus among stakeholders.
Summary of Building Block 4
Activities Budget Needed (USD) Requested (USD)
- D. Framework for Market-Based Instrument
A comprehensive assessment report on MBI options for Indonesia 450,000 250,000 A design of selected market-based instrument for selected sector 300,000 200,000 Draft policy(ies) required for the establishment and implementation of MBI 450,000 250,000 Piloting the market-based instrument in the selected sector 650,000 300,000 Total 1,850,000 1,000,000
FINAL MARKET READINESS PROPOSAL: INDONESIA 17
Define the organization structure of Implementation Phase,
which consists Steering Committee, Project Implementation Unit(s), and Expert Group(s).
Describe the activities to integrate all works in Implementation
Phase and appropriately communicate the progress and results to relevant stakeholders.
DNPI will be the PIU for organization, communication and
stakeholder engagement.
Summary of Building Block 5
Activities Budget Needed (USD) Requested (USD)
- E. Organization, Communication, Consultation and
Engagement PMR implementation reports 100,000 50,000 Stakeholder consultations and capacity building reports 300,000 100,000 Total 400,000 150,000
FINAL MARKET READINESS PROPOSAL: INDONESIA 18
Implementation Phase Schedule
Profiling Emissions A comprehensive carbon abatement cost curve in the two target areas. A calculated / reviewed / estimated sectoral baseline emission of the target areas MRV System Development (Gov't Track) Rules and regulations on MRV Institutional set up for MRV Capacity building and awareness raising activities MRV System Development (Piloting Track) Map of MRV activities at the installation level in Indonesia Monitoring protocols Data management system at the installation level GHG emission data and review on MRV system at installation level and at aggregated data management level Framework for MBI A comprehensive assessment report on MBI options for Indonesia A design of selected market-based instrument for selected sector Draft policy(ies) required for the establishment and implementation of MBI Piloting the market-based instrument in the selected sector Year-1 Year-2 Year-3 Year-4 PMR Activities
FINAL MARKET READINESS PROPOSAL: INDONESIA 19
Process of developing Indonesia PMR budget
Interministrial meetings was conducted to discuss
the proposal budget.
Three ministries, the Ministry of Finance, the
Ministry of Industry, and the Ministry of Energy and Mineral Resources , calculated their budget needs based on activities proposed in the draft MRP and actual conditions.
The MRP preparation consultant combine all of the
budget needs and discuss it among ministries.
We comes up with the “minimal amount” needs of
the previous budget proposed.
FINAL MARKET READINESS PROPOSAL: INDONESIA 20
Activities Budget Needed (USD) Requested (USD) Profiling Emissions in Power & Industry Sectors 950,000 400,000 MRV System Development (Governance Track) 2,050,000 800,000 MRV System Development (Piloting Track) 1,700,000 650,000 Framework for Market-Based Instrument 1,850,000 1,000,000 Organization, Communication, Consultation and Engagement 400,000 150,000 Total 6,950,000 3,000,000
Recapitulation of Proposed Budget
FINAL MARKET READINESS PROPOSAL: INDONESIA 21
Conclusion
- Indonesia MRP proposes works on (a) core technical
and institutional readiness components in power and industry sectors and (b) planning for a market-based instrument (MBI). It will be completed in 4 years after project start.
- These works will enhance understanding of market-
based instruments, support the implementation of existing climate-related policies, and contribute to the decision making process of MBI implementation.
- Out of total estimated cost of USD 6,950,000,
Indonesia request the PA for USD 3,000,000 funding.
FINAL MARKET READINESS PROPOSAL: INDONESIA 22