open f open for orum um
play

Open F Open For orum um November 14, 2018 Disc Disclaimer - PowerPoint PPT Presentation

Open F Open For orum um November 14, 2018 Disc Disclaimer laimer All information provided today is for information only, is non-binding, does not constitute legal or other advice, and does not amend or form part of any future Request for


  1. Open F Open For orum um November 14, 2018

  2. Disc Disclaimer laimer All information provided today is for information only, is non-binding, does not constitute legal or other advice, and does not amend or form part of any future Request for Proposals (RFP).

  3. Purpose Get feedback Provide and answer information questions

  4. Agenda Project Overview 02 01 03 04 Schedule Project Project Delivery Management Approach 05 06 07 Quality Assurance Minority & Small Q&A Business Affairs – Program DBE Program

  5. Ov Over erview and view and NEP NEPA Sta A Status tus

  6. Project Purpose and Needs Primar Primary y Pur Purpose pose Secon Secondar dary N y Needs eeds Improve freight mobility Improve safety in the corridor Improve system linkages

  7. Existing Existing Pr Propos oposed ed 19 19 45 45 Bridges 12 12 11 11 Interchanges 14 14 14 14 Interstate (miles) 166 166 188 188 Roadway (lane miles) 134k 134k AADT # (Between St. Andrews and I-20)

  8. Current and Potential Adjacent Projects 01 02 03 04 05 I-126 Bridge I-20 US 1 and I-26 I-20 at US1 Replacement Widening Widening SC 302 interchange, at Elmwood (MM MM 49 to 49 to interchanges (MM 85 to (MM 85 to Lexington Avenue MM MM 60) 60) MM MM 101) 101) with I-26 County

  9. I-26 from Harbison Blvd. to Piney Grove Rd.

  10. I-26/St. Andrews Road and I-20/I-26

  11. I-26 from I-20 to I-126

  12. I-20 from Bush River Road to I-26

  13. Schedule

  14. Public Support

  15. Quick Facts 291 291 1.3 Million 1.3 Million SF SF Bridge Deck Area ROW Tracts 2.0 2.0 Million SY Million SY 4 Million C Million CY Pavement Earthwork 45 45 All quantities are preliminary pending final design Bridge Structures

  16. Pr Project oject Appr pproac oach

  17. Dedicated Project Team Deputy Secretary for Federal Highway Engineering Administration Leland Colvin, PE Program Director Ladd Gibson, PE Dedicated SCDOT Design Manager Project Manager Construction Manager Chris Lacy, PE Brian Klauk, PE David Rister, PE management Dedicated SCDOT Design Construction Right of Way and/or consultant Disciplines Environmental Project Inspection Utilities Compliance Controls staff Railroads Design Reviews Materials Management

  18. Dedicated Project Team Design Construction Right of Way Disciplines Environmental Project Inspection Utilities Compliance Controls Railroads Materials Management Design Reviews • Design Management Lead • Discipline Level Support Staff • Roadway Design Lead • Communications Lead/staff • Structures Design Lead • NEPA Compliance Lead • ROW Acquisition Oversight • Hydrology Design Lead • Utility Agreement Coordinator • Geotechnical Design Lead • Risk Management • Traffic Design Lead • Financial Reporting • Lighting Design • Multi-modal Coordination • Landscaping and Aesthetics

  19. Dedicated Project Team Construction Design Right of Way Inspection Disciplines Environmental Project Utilities Compliance Controls Railroads Design Reviews Materials Management • Project Engineer • Inspectors/Technicians • Assistant Project Engineer • AASHTO Accredited Lab • Materials Management Engineer • Survey Verification • Safety Officer • Environmental Compliance • Public Involvement • ITS/Signal Coordination • DBE/EEO/OJT Compliance Officer • Utility Construction Oversight • CPM Scheduler • ROW Compliance • Estimator/Claims Review • HAZMAT Oversight • Construction Document Control • Aerial Photography • RCEs by Segment • RR Flagger Coordination

  20. Anticipated Schedule * The FEIS and ROD have moved to Spring 2019. This change does not impact the procurement schedule shown above.

  21. Pr Project oject Deliv Deliver ery y

  22. Single Construction Contract

  23. ATCs and Stipends • Preliminary ATCs • Formal ATCs • Stipends for unsuccessful short-listed teams • Considering: Unlimited preliminary ATCs and limited formal ATCs

  24. Award Criteria • Best Value with Weighted Criteria

  25. Contract Payments • Considering: SCDOT specified or Contractor specified draw schedule

  26. Surveys • 2009-2010 Aerial Surveys and Associated Control Provided • 2018 Pavement Resurfacing Project near completion

  27. Utilities • Utility Task Force to mitigate risk • Considering: Early ROW acquisition for selected utilities • Considering: MOU's with major utilities

  28. SUE • Level B/C SUE 80% complete • Tracking new utility installation via encroachment permits

  29. Geotechnical Investigations • Baseline Geotechnical Report complete • Over 200 soil borings and associated testing complete

  30. Pavement • • Set up as an asphalt job Expect areas of poor subgrade under • Providing multiple pavement options existing shoulders and new location • Considering: ATCs for concrete pavement alignments • • I-26/I-126 rehab includes replacement of Considering: Performance specification on asphalt in composite sections temporary pavement

  31. Maintenance of Traffic • Considering: Alternative MOT design criteria for hourly lane closure restrictions • Considering: Coordination with DB Teams on long-term lane closure

  32. IMR – Interchange Design • Two IMRs underway for entire project • Expected approval prior to RFP release

  33. Desig Design Sub n Submittal mittal Reviews views • Segmentation within the project limits will be allowed • Partial submittals will be entertained

  34. ROW Acquisition • Early and Post-ROD Acquisitions • Remaining ROW Acquisition will be the responsibility of the Design Build Team • Considering: Various options for ROW payment responsibility

  35. Environmental Mitigation/Permitting • Permittee Responsible Mitigation (PRM) Plan will be provided by SCDOT • PRM is anticipated to provide sufficient credits for Preferred Alternative

  36. Envision and INVEST Environmental Sustainability • Currently being tracked and monitored • Design-Build contractor may be required to document sustainability management

  37. Quality Assurance Program

  38. Quality Assurance Program Quality Assurance Program Independent Assurance Acceptance Program Program Quality Owner Quality Control Independent Acceptance Verification (QC) Assurance (IA) (QA) (OV) Contractor Contractor's IQF SCDOT / CM Firm SCDOT

  39. Quality Control • Contractor’s Responsibility Quality Assurance • Not used for Acceptance Program Independent Assurance Acceptance Program Program Quality Owner Quality Control Independent Acceptance Verification (QC) Assurance (IA) (QA) (OV) Contractor Contractor's IQF SCDOT / CM Firm SCDOT

  40. Independent Quality Firm • Independent Quality Manager Quality Assurance • Engineering Judgment Program • Sampling and Testing • Testing Results Independent Assurance Acceptance Program Program Quality Owner Quality Control Independent Acceptance Verification (QC) Assurance (IA) (QA) (OV) Contractor Contractor's IQF SCDOT / CM Firm SCDOT

  41. Owner Verification • Owner Verification Plan Quality Assurance • Sampling and Testing Program • Testing Results Independent Assurance Acceptance Program Program Quality Owner Quality Control Independent Acceptance Verification (QC) Assurance (IA) (QA) (OV) Contractor Contractor's IQF SCDOT / CM Firm SCDOT

  42. Independent Assurance • Evaluation of Personnel and Quality Assurance Equipment used for Program Acceptance Independent Assurance Acceptance Program Program Quality Owner Quality Control Independent Acceptance Verification (QC) Assurance (IA) (QA) (OV) Contractor Contractor's IQF SCDOT / CM Firm SCDOT

  43. Division of Minority & Small Business Affairs • Disadvantaged Business Enterprise (DBE) goal • DBE point person • Business Development Center (803-737-6426)

  44. Ques Questions tions

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend