Open F Open For orum um November 14, 2018 Disc Disclaimer - - PowerPoint PPT Presentation

open f open for orum um
SMART_READER_LITE
LIVE PREVIEW

Open F Open For orum um November 14, 2018 Disc Disclaimer - - PowerPoint PPT Presentation

Open F Open For orum um November 14, 2018 Disc Disclaimer laimer All information provided today is for information only, is non-binding, does not constitute legal or other advice, and does not amend or form part of any future Request for


slide-1
SLIDE 1

Open F Open For

  • rum

um

November 14, 2018

slide-2
SLIDE 2

Disc Disclaimer laimer

All information provided today is for information

  • nly, is non-binding, does not constitute legal or
  • ther advice, and does not amend or form part of

any future Request for Proposals (RFP).

slide-3
SLIDE 3

Purpose Provide information Get feedback and answer questions

slide-4
SLIDE 4

01

Project Overview 02 Schedule

03

Project Management Approach

04

Project Delivery

Agenda

05

Quality Assurance Program

06

Minority & Small Business Affairs – DBE Program

07

Q&A

slide-5
SLIDE 5

Ov Over erview and view and NEP NEPA Sta A Status tus

slide-6
SLIDE 6

Project Purpose and Needs Primar Primary y Pur Purpose pose Secon Secondar dary N y Needs eeds

Improve freight mobility Improve safety in the corridor Improve system linkages

slide-7
SLIDE 7

19 19 12 12 14 14 166 166

Bridges Interchanges Interstate Roadway

(miles) (lane miles)

134k 134k

AADT

(Between St. Andrews and I-20) Existing Existing Pr Propos

  • posed

ed

45 45

11 11 14 14 188 188 #

slide-8
SLIDE 8

Current and Potential Adjacent Projects

01

I-26 Widening (MM 85 to (MM 85 to MM MM 101) 101)

02

US 1 and SC 302 interchanges with I-26

03

I-126 Bridge Replacement at Elmwood Avenue

04

I-20 Widening (MM MM 49 to 49 to MM MM 60) 60)

05

I-20 at US1 interchange, Lexington County

slide-9
SLIDE 9

I-26 from Harbison Blvd. to Piney Grove Rd.

slide-10
SLIDE 10

I-26/St. Andrews Road and I-20/I-26

slide-11
SLIDE 11

I-26 from I-20 to I-126

slide-12
SLIDE 12

I-20 from Bush River Road to I-26

slide-13
SLIDE 13

Schedule

slide-14
SLIDE 14

Public Support

slide-15
SLIDE 15

Quick Facts

291 291

ROW Tracts

2.0 2.0 Million SY Million SY

Pavement

45 45

Bridge Structures

1.3 Million 1.3 Million SF SF

Bridge Deck Area

4 Million C Million CY

Earthwork All quantities are preliminary pending final design

slide-16
SLIDE 16

Pr Project

  • ject Appr

pproac

  • ach
slide-17
SLIDE 17

Dedicated Project Team

Deputy Secretary for Engineering Leland Colvin, PE Design Manager Chris Lacy, PE Project Manager Brian Klauk, PE Construction Manager David Rister, PE

Construction Inspection Materials Management Project Controls Design Disciplines Design Reviews Right of Way Utilities Railroads Environmental Compliance

Program Director Ladd Gibson, PE

Federal Highway Administration Dedicated SCDOT management Dedicated SCDOT and/or consultant staff

slide-18
SLIDE 18
  • Discipline Level Support Staff
  • Communications Lead/staff
  • NEPA Compliance Lead
  • ROW Acquisition Oversight
  • Utility Agreement Coordinator
  • Risk Management
  • Financial Reporting
  • Multi-modal Coordination
  • Design Management Lead
  • Roadway Design Lead
  • Structures Design Lead
  • Hydrology Design Lead
  • Geotechnical Design Lead
  • Traffic Design Lead
  • Lighting Design
  • Landscaping and Aesthetics

Dedicated Project Team

Construction Inspection Materials Management Project Controls Design Disciplines Design Reviews Right of Way Utilities Railroads Environmental Compliance

slide-19
SLIDE 19
  • Project Engineer
  • Assistant Project Engineer
  • Materials Management Engineer
  • Safety Officer
  • Public Involvement
  • DBE/EEO/OJT Compliance Officer
  • CPM Scheduler
  • Estimator/Claims Review
  • Construction Document Control
  • RCEs by Segment

Dedicated Project Team

  • Inspectors/Technicians
  • AASHTO Accredited Lab
  • Survey Verification
  • Environmental Compliance
  • ITS/Signal Coordination
  • Utility Construction Oversight
  • ROW Compliance
  • HAZMAT Oversight
  • Aerial Photography
  • RR Flagger Coordination

Construction Inspection Materials Management Project Controls Design Disciplines Design Reviews Right of Way Utilities Railroads Environmental Compliance

slide-20
SLIDE 20

Anticipated Schedule

* The FEIS and ROD have moved to Spring 2019. This change does not impact the procurement schedule shown above.

slide-21
SLIDE 21

Pr Project

  • ject Deliv

Deliver ery y

slide-22
SLIDE 22

Single Construction Contract

slide-23
SLIDE 23

ATCs and Stipends

  • Preliminary ATCs
  • Formal ATCs
  • Stipends for unsuccessful short-listed teams
  • Considering: Unlimited preliminary ATCs and limited formal ATCs
slide-24
SLIDE 24

Award Criteria

  • Best Value with Weighted Criteria
slide-25
SLIDE 25

Contract Payments

  • Considering: SCDOT specified or Contractor specified draw schedule
slide-26
SLIDE 26

Surveys

  • 2009-2010 Aerial Surveys and Associated Control Provided
  • 2018 Pavement Resurfacing Project near completion
slide-27
SLIDE 27

Utilities

  • Utility Task Force to mitigate risk
  • Considering: Early ROW acquisition for selected utilities
  • Considering: MOU's with major utilities
slide-28
SLIDE 28

SUE

  • Level B/C SUE 80% complete
  • Tracking new utility installation via encroachment permits
slide-29
SLIDE 29

Geotechnical Investigations

  • Baseline Geotechnical Report complete
  • Over 200 soil borings and associated testing complete
slide-30
SLIDE 30

Pavement

  • Set up as an asphalt job
  • Providing multiple pavement options
  • Considering: ATCs for concrete pavement
  • I-26/I-126 rehab includes replacement of

asphalt in composite sections

  • Expect areas of poor subgrade under

existing shoulders and new location alignments

  • Considering: Performance specification on

temporary pavement

slide-31
SLIDE 31

Maintenance

  • f Traffic
  • Considering: Alternative MOT design criteria for hourly lane closure restrictions
  • Considering: Coordination with DB Teams on long-term lane closure
slide-32
SLIDE 32

IMR – Interchange Design

  • Two IMRs underway for entire project
  • Expected approval prior to RFP release
slide-33
SLIDE 33

Desig Design Sub n Submittal mittal Reviews views

  • Segmentation within the project limits will be allowed
  • Partial submittals will be entertained
slide-34
SLIDE 34

ROW Acquisition

  • Early and Post-ROD Acquisitions
  • Remaining ROW Acquisition will be the responsibility of the Design Build Team
  • Considering: Various options for ROW payment responsibility
slide-35
SLIDE 35

Environmental Mitigation/Permitting

  • Permittee Responsible Mitigation (PRM) Plan will be provided by SCDOT
  • PRM is anticipated to provide sufficient credits for Preferred Alternative
slide-36
SLIDE 36

Envision and INVEST

Environmental Sustainability

  • Currently being tracked and monitored
  • Design-Build contractor may be required to document sustainability management
slide-37
SLIDE 37

Quality Assurance Program

slide-38
SLIDE 38

Quality Assurance Program

Quality Acceptance (QA) Owner Verification (OV) Independent Assurance (IA) Acceptance Program Independent Assurance Program Quality Control (QC) Quality Assurance Program Contractor's IQF SCDOT / CM Firm Contractor SCDOT

slide-39
SLIDE 39

Quality Control

Quality Acceptance (QA) Owner Verification (OV) Independent Assurance (IA) Acceptance Program Independent Assurance Program Contractor's IQF SCDOT / CM Firm SCDOT Quality Control (QC) Contractor Quality Assurance Program

  • Contractor’s Responsibility
  • Not used for Acceptance
slide-40
SLIDE 40

Owner Verification (OV) SCDOT / CM Firm Independent Assurance (IA) SCDOT

Independent Quality Firm

Independent Assurance Program Quality Control (QC) Contractor Quality Assurance Program Acceptance Program Quality Acceptance (QA) Contractor's IQF

  • Independent Quality Manager
  • Engineering Judgment
  • Sampling and Testing
  • Testing Results
slide-41
SLIDE 41

Quality Acceptance (QA) Contractor's IQF Independent Assurance (IA) SCDOT

Owner Verification

Independent Assurance Program Quality Control (QC) Contractor Quality Assurance Program Acceptance Program Owner Verification (OV) SCDOT / CM Firm

  • Owner Verification Plan
  • Sampling and Testing
  • Testing Results
slide-42
SLIDE 42

Independent Assurance

Quality Acceptance (QA) Owner Verification (OV) Acceptance Program Quality Control (QC) Contractor's IQF SCDOT / CM Firm Contractor Quality Assurance Program Independent Assurance Program Independent Assurance (IA) SCDOT

  • Evaluation of Personnel and

Equipment used for Acceptance

slide-43
SLIDE 43

Division of Minority & Small Business Affairs

  • Disadvantaged Business Enterprise (DBE) goal
  • DBE point person
  • Business Development Center (803-737-6426)
slide-44
SLIDE 44

Ques Questions tions