SLIDE 1 General Engineering Consultant (GEC) Information Forum
May 15, 2018
VTA’s BART Silicon Valley Phase II
SLIDE 2 GE GEC Inf nformat
ion For
um
SLIDE 3 Opening Remarks Nur uria ia I.
Fer ernandez nandez
General Manager/CEO
Santa Clara Valley Transportation Authority
GE GEC Inf nformat
ion For
um
SLIDE 4
Opening Remarks
SLIDE 5 VTA Program Information Carolyn
Chief Engineering and Program Delivery Officer
Santa Clara Valley Transportation Authority
GE GEC Inf nformat
ion For
um
SLIDE 6 Phase I Extension ($2.4 billion)
- 10-mile extension under construction
- 2 stations: Milpitas and Berryessa/North
San Jose
- Anticipated opening year ridership: 23,000
per average weekday Phase II Extension ($4.7 billion*)
- 6-mile extension (5-mile tunnel)
- 4 stations
- Newhall Yard Maintenance Facility
- Anticipated opening year ridership: 33,000
per average weekday
*Pre-Risk Assessed $, excludes finance costs *Pre-Risk Assessed $, excludes finance costs
VTA’s BART Silicon Valley
SLIDE 7 VTA’s BART Silicon Valley
- Development began in the early 2000s as a single
16-mile extension project from Fremont to Santa Clara.
- In early 2009, VTA Board of Directors committed to
building project in phases, with focus on Phase I
- During the design development, the 6-mile tunnel
section with 4 stations (Phase II) was put on hold
- Phase I is currently under construction, testing and
commissioning
- Renewed planning efforts for Phase II began in 2014
SLIDE 8 VTA and BART Partnership
- Comprehensive Agreement between VTA & BART executed in 2001
- Santa Clara Valley Transportation Authority (VTA) Responsibilities:
- Pay all costs associated with the extension
- Contracting/Procurement
- Construct to applicable BART/industry standards, codes, and regulations
- Retain ownership of infrastructure
- Bay Area Rapid Transit (BART) Responsibilities:
- Technical Assistance
- Operations
- Maintenance
- Service Planning
SLIDE 9 Phase II Status
In April 2018, both the VTA and BART Board of Directors adopted the Recommended Project Description and Approved the Phase II Extension Project that consists of the BART Extension with Transit-Oriented Joint Development (TOJD):
- Tunnel Configuration: Single Bore
- Downtown Station: West Location
- Diridon Station: North Location
SLIDE 10 Downtown San Jose Station Options
West Option East Option
SLIDE 11 Diridon Station Options
North Option South Option
SLIDE 12 Upcoming Phase II Milestones
- Federal approval (NEPA) of environmental documents
- Record of Decision (ROD) from FTA: June 2018
- Apply for Full Funding Grant Agreement (FFGA) with FTA: 4th Quarter 2019
- FFGA Approval: Early 2020
SLIDE 13 BART Program Information Rob
ert t Power ers
Deputy General Manager
Bay Area Rapid Transit
GE GEC Inf nformat
ion For
um
SLIDE 14
BART Update
SLIDE 15 Project Information Den ennis nis O.
Ratc tclif liffe
Deputy Director
Santa Clara Valley Transportation Authority
GE GEC Inf nformat
ion For
um
SLIDE 16 Phase II Overview
- 6 mile alignment with 5 miles of single
bore tunnel
- Ties into existing Phase I tail tracks south
- f Berryessa/North San Jose Station
- East Portal is located at Las Plumas Ave &
North Marburg Way just east of US-101
- Three underground stations:
- Alum Rock/28th Street
- Downtown
- Diridon
- The West Portal is located north of I-880
near Newhall St.
- One at-grade station (Santa Clara)
- Yard and Maintenance Facility
SLIDE 17 Major Stakeholders
- Community and future patrons
- Adjacent businesses and the
Downtown Business Association
- BART
- City of San Jose
- City of Santa Clara
- Private developers along corridor
- Caltrain
- California High Speed Rail
Authority
- Caltrans
- PG&E and Other Utility Owners
- Army Corps of Engineers
- Many Others…
SLIDE 18 Phase II Current and Near Term Activities
- Environmental & Geotechnical
Investigations
- Community Outreach
- 3rd Party Agreements
- Utility Investigations
- Real Estate Plan and
Acquisitions
- Tunnel Boring Machine (TBM)
Power Plan
Development Plan
SLIDE 19 Phase II Reporting Structure
Program Management Engineering Services Consultant (GEC)
SLIDE 20
Phase II Reporting Structure
SLIDE 21 Proposed Contract Strategy & Scope of Work Sha harif rif Abo bou-Sabh Sabh
HNTB+PB - Program Manager
GE GEC Inf nformat
ion For
um
SLIDE 22 Scope of the GEC
- Develop design in accordance with final contracting plan
- Integrate all design scope
- Review and evaluate alternate concepts submitted during
construction procurement
- Review design-build progress and final design submittals
- Manage closeout and turnover milestones
- Support of systems integration testing and commissioning
- Coordinate with project stakeholders and developers
- Ensure timely as-built documentation
- Design support during construction
- Operate within the Project Information Control System
SLIDE 23 Phase II Contracting Strategies
PROPOSED INITIAL CONTRACTS
- Advanced Utility Relocation (Design-Bid-Build)
- Enabling Works (On-Call Design-Bid-Build)
- Demolition of existing structures
- Hazardous Materials Abatement
- Tunnel and Stations Heavy Civil (Design-Build)
- Will produce technical documents for the Contract Solicitations
SLIDE 24 Phase II Contracting Strategies
PROPOSED FOLLOW-ON CONTRACTS
- Track and Systems (Design-Bid-Build)
- Newhall Yard & Santa Clara Station (Design-Bid-Build)
- Station Fit Out (Design-Bid-Build)
SLIDE 25 Phase II Contracting Strategies
PROPOSED FOLLOW-ON CONTRACTS (CONTINUED)
- Parking Garages (Design-Build)
- Transit Oriented Joint Development (TOJD) at stations
- Coordination with TOJD designers/developers
SLIDE 26
East Portal – Overview
SLIDE 27
Alum Rock Station – Site Concept
SLIDE 28
Downtown San Jose Station – Site Concept
SLIDE 29
Station Entrance Concept
SLIDE 30
Typical Tunnel Section
SLIDE 31
Diridon Station – Site Concept
SLIDE 32
West Portal – Overview
SLIDE 33
Newhall Yard – Overview
SLIDE 34
Santa Clara Station (at-grade) – Site Concept
SLIDE 35
Project Information Control System
SLIDE 36
- Navisworks
- HCSS
- Primavera P6
- Acumen
- Amazon Web Services
- SharePoint Online
- ProjectWise
- Bluebeam
- BIM / VDC
Software / Tools
SLIDE 37
SharePoint Online
SLIDE 38
ProjectWise
SLIDE 39
Bluebeam
SLIDE 40 Autodesk Revit will be used to Design & Document all Vertical Components (Stations).
BART WARM SPRINGS - REVIT RENDERING SINGLE BORE – BENTLEY RENDERINGS
BIM/VDC
SLIDE 41
Navisworks
SLIDE 42
HCSS
SLIDE 43
Geographic Information System
SLIDE 44 Scope of the GEC
- Develop design in accordance with final contracting plan
- Integrate all design scope
- Review and evaluate alternate concepts submitted during
construction procurement
- Review design-build progress and final design submittals
- Manage closeout and turnover milestones
- Support of systems integration testing and commissioning
- Coordinate with project stakeholders and developers
- Ensure timely as-built documentation
- Design support during construction
- Operate within the Project Information Control System
SLIDE 45 Procurement Information Th Thor
Chief Procurement Officer
Santa Clara Valley Transportation Authority
GE GEC Inf nformat
ion For
um
SLIDE 46 RFP S18088 FOR GEC SERVICES
- Federal procurement requirements apply
- Selection subject to the Brooks Act
- Proposers need to be registered on VTA.org
- All communication is with authorized Point of Contact
- Rely on requirements in the RFP
SLIDE 47
RFP S18088 SCHEDULE
PUBLISH
MAY
PRE-PROPOSAL CONFERENCE
JUNE
PROPOSALS DUE
JULY
COST PROPOSALS
AUGUST
INTERVIEWS
AUGUST
BOARD APPROVAL
OCTOBER
SLIDE 48
RFP REQUIREMENTS – DBE/SBE
RFP BUSINESS DIVERSITY REQUIREMENTS INCLUDE: ASSIGNED - 15.45% DBE GOAL ASSIGNED - 30% ASPIRATIONAL SBE GOAL THE ACHIEVEMENT OF THE DBE GOAL WILL BE CALCULATED TOWARDS THE SBE ASPIRATION GOAL
SLIDE 49
Questions
SLIDE 50 Closing
- This Forum is an opportunity
for subcontractors to network with primes
information tables in the lobby, members of Risk Management, Office of Business Diversity, Procurement and Community Engagement will be available