community consultation july 18 2018 at waterfront toronto
play

Community Consultation July 18, 2018 At Waterfront Toronto, we work - PowerPoint PPT Presentation

Community Consultation July 18, 2018 At Waterfront Toronto, we work with our partners at the City of Toronto, Province of Ontario and Government of Canada. 2 Chris Glaisek SVP Planning & Design, Waterfront Toronto Julius Gombos VP


  1. Community Consultation July 18, 2018

  2. At Waterfront Toronto, we work with our partners at the City of Toronto, Province of Ontario and Government of Canada. 2

  3. Chris Glaisek SVP Planning & Design, Waterfront Toronto Julius Gombos VP Project Delivery, Waterfront Toronto 3

  4. Insert map from Port Lands 101 context board 4

  5. 5

  6. Keating Channel 6

  7. 7

  8. 8

  9. The Port Lands Flood Protection Project 9

  10. Keating Channel Port Lands Flood Protection 10 Project Boundary

  11. What are we building? 11

  12. Earthworks/Flood Protection 12

  13. Bridges and Structures

  14. Roads and Municipal Services 14

  15. Parks 15

  16. Where are we now? 16

  17. A decade of planning 2017 2006 2011 2015 $1.25 billion funding for Don Mouth Port Lands DMNP EA and Lower Port Lands Flood Naturalization and Port Acceleration Initiative Don Lands EA approved Protection Lands Flood Protection Project Environmental Port Lands Framework Plan and Villiers Island Assessment (DMNP EA) Precinct Plan approved began 2012 2016 2007 Port Lands Due Diligence report Framework Plan and International design for Port Lands Flood Villiers Island competition Protection completed Precinct Plan began

  18. Where are we now? we are here Feb 2018 July 2018 Spring 2019 Port Lands Flood Protection (PLFP) PLFP community Design for parks & river Community consultation #2 is 60% complete consultation #1 Fall 2018 Fall 2019 May 2018 River excavation begins Design for Design river, parks, Design for parks & river is Commissioners Street is roads & bridges is 30% 50% complete complete complete Design complete on Cherry Street & Cherry Street Bridge North

  19. Construction Progress 19

  20. 20

  21. 21

  22. 22

  23. Construction Schedule 23

  24. Construction Schedule: July 2018 – September 2018 24

  25. Construction Schedule: September 2018 – December 2018 25

  26. Construction Schedule: January 2019 – April 2019 26

  27. Construction Schedule: May 2019 – July 2019 27

  28. Construction Schedule: August 2019 – October 2019 28

  29. Construction Schedule: November 2019 – December 2019 29

  30. Matthew Urbanski, Principal, MVVA Herb Sweeney, Associate Principal, MVVA James Roche, Partner, DTAH Michael Meschino, Principal, Entuitive 30

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend