Community Consultation July 18, 2018 At Waterfront Toronto, we work - - PowerPoint PPT Presentation

community consultation july 18 2018 at waterfront toronto
SMART_READER_LITE
LIVE PREVIEW

Community Consultation July 18, 2018 At Waterfront Toronto, we work - - PowerPoint PPT Presentation

Community Consultation July 18, 2018 At Waterfront Toronto, we work with our partners at the City of Toronto, Province of Ontario and Government of Canada. 2 Chris Glaisek SVP Planning & Design, Waterfront Toronto Julius Gombos VP


slide-1
SLIDE 1

Community Consultation July 18, 2018

slide-2
SLIDE 2

2

At Waterfront Toronto, we work with our partners at the City of Toronto, Province of Ontario and Government of Canada.

slide-3
SLIDE 3

Chris Glaisek SVP Planning & Design, Waterfront Toronto Julius Gombos VP Project Delivery, Waterfront Toronto

3

slide-4
SLIDE 4

4

Insert map from Port Lands 101 context board

slide-5
SLIDE 5

5

slide-6
SLIDE 6

6

Keating Channel

slide-7
SLIDE 7

7

slide-8
SLIDE 8

8

slide-9
SLIDE 9

The Port Lands Flood Protection Project

9

slide-10
SLIDE 10

10

Keating Channel

Port Lands Flood Protection Project Boundary

slide-11
SLIDE 11

11

What are we building?

slide-12
SLIDE 12

12

Earthworks/Flood Protection

slide-13
SLIDE 13

Bridges and Structures

slide-14
SLIDE 14

14

Roads and Municipal Services

slide-15
SLIDE 15

15

Parks

slide-16
SLIDE 16

Where are we now?

16

slide-17
SLIDE 17

A decade of planning

2006

Don Mouth Naturalization and Port Lands Flood Protection Project Environmental Assessment (DMNP EA) began

2007

International design competition

2011

Port Lands Acceleration Initiative

2015

DMNP EA and Lower Don Lands EA approved

2016

Due Diligence report for Port Lands Flood Protection completed

2017

$1.25 billion funding for Port Lands Flood Protection Port Lands Framework Plan and Villiers Island Precinct Plan approved

2012

Port Lands Framework Plan and Villiers Island Precinct Plan began

slide-18
SLIDE 18

Where are we now?

Feb 2018

Port Lands Flood Protection (PLFP) Community consultation #1

May 2018

Design river, parks, roads & bridges is 30% complete

July 2018

PLFP community consultation #2

Fall 2018

River excavation begins Design for parks & river is 50% complete Design complete on Cherry Street & Cherry Street Bridge North

Spring 2019

Design for parks & river is 60% complete

we are here Fall 2019

Design for Commissioners Street is complete

slide-19
SLIDE 19

19

Construction Progress

slide-20
SLIDE 20

20

slide-21
SLIDE 21

21

slide-22
SLIDE 22

22

slide-23
SLIDE 23

23

Construction Schedule

slide-24
SLIDE 24

24

Construction Schedule: July 2018 – September 2018

slide-25
SLIDE 25

25

Construction Schedule: September 2018 – December 2018

slide-26
SLIDE 26

26

Construction Schedule: January 2019 – April 2019

slide-27
SLIDE 27

27

Construction Schedule: May 2019 – July 2019

slide-28
SLIDE 28

28

Construction Schedule: August 2019 – October 2019

slide-29
SLIDE 29

29

Construction Schedule: November 2019 – December 2019

slide-30
SLIDE 30

Matthew Urbanski, Principal, MVVA Herb Sweeney, Associate Principal, MVVA James Roche, Partner, DTAH Michael Meschino, Principal, Entuitive

30