Omroro Pipelines Project Public Meeting 15 August 2019 Agenda - - PowerPoint PPT Presentation
Omroro Pipelines Project Public Meeting 15 August 2019 Agenda - - PowerPoint PPT Presentation
Omroro Pipelines Project Public Meeting 15 August 2019 Agenda Introductions Wellington Water, Brian Perry Civil, WCC, GWRC Overview of project Wellington Water Progress report Brian Perry Civil Wallace St bulk main
Agenda
- Introductions
─ Wellington Water, Brian Perry Civil, WCC, GWRC
- Overview of project – Wellington Water
- Progress report – Brian Perry Civil
- Wallace St bulk main works / diversion options – Brian
Perry Civil
- Questions
Overview
- Omāroro Reservoir being built to address growth and
improve resilience
- Pipelines project is building the water network for the
Omāroro Reservoir
- Further renewal work being delivered at the same time –
intent is no more major water network works in the area for many years
Scope of pipelines work
- A new bulk water main
- (Hargreaves, Wallace, Howard)
- Renewal of local water mains
- (Hargreaves, Wallace, Finlay)
- Upgrade of storm water pipe
- (Rolleston, Wallace)
- Renewal of existing sewer
- (Wallace, Finlay)
Progress report
- Local water renewals on Hargreaves St completed
- Bulk water on Hargreaves St underway
- Local water renewals on Wallace St underway
- Valve chamber at Hargreaves/Wright St corner underway
- We’ll keep you informed about impact and progress of work
Construction Plan – estimated dates
bulk water main local water mains storm water sewer
Wallace St traffic volumes
- Wright St peak flow is
~200/hr (~1000/day)
- June/July 2017, June
2018 traffic counts
- Weekday/weekend
peak is ~1600/hr (~20,000/day)
- 10pm – 5am peak is
~400/hr (~1000/nght)
Wallace St traffic reduction
- VMS boards
encourage use of alternative routes
- Advertising campaign
- n radio, social media
and other online channels
- Advising delivery co’s,
taxis, ubers to use alternate routes
- We anticipate
significant reduction in flow along Wallace St
- WCC will continue to
monitor
TM options for Wallace St bulk main work
Options considered included:
- Option 1: Stop Go on Wallace Street
- Option 2: Partial Diversion, NB Wright St, SB Wallace St
- Close Wallace St/ Wright St
- Option 3: Full diversion to Adelaide Rd
- Option 4: Full diversion to Tasman St
- Option 5: Close Wallace St, NB Wright St, SB Tasman St
- Option 6: Close Wallace St, full diversion to Wright St
- This is by far the safest and least disruptive option
Option 1: Stop / Go on Wallace St
- Advantages
─ No diversion required ─ No changes to bus operations
- Ruled out because
─ Stop / Go on Wallace St creates gridlock throughout the network due to tailbacks ─ The modelling confirms intolerable delays even outside of peak hours ─ This option is not feasible
Wallace St bulk water challenge
Option 2: NB Wright St, SB Wallace St
- Partial diversion, northbound traffic only onto Wright St
- Advantages
─ Only northbound traffic on Wright St
- Ruled out because
─ Wallace St road width is insufficient to safely construct bulk water pipes from Hargreaves St to Howard St ─ Due to deep trenches, large diameter pipes leaves insufficient room to allow traffic flow past the work site ─ This option is not feasible
Bus routing options
- Divert via Adelaide Rd
─ Too far from current routes, large number of stops displaced ─ High impact on University and Schools
- Divert via Tory St / Tasman St
─ Diversion leads to convoluted routes ─ Twice carparks affected & overhead services to resolve (cf Wright St) ─ Significant distance from current routes, stops displaced
- Divert via Wright St
─ Short Diversion follows same route (1 stop relocated from Wallace St) ─ Some overhead wires need lifting for double-deckers
Option 3: Full diversion to Adelaide Rd
- Wallace St and Wright St both closed to through traffic
- Advantages
─ No additional traffic on Wright St
- Ruled out because
─ Very long diversion ─ Limited capacity on Adelaide Road for the additional traffic ─ Public transport impact too great – route changes and delays ─ Network resilience compromised if Wallace St + Wright St closed ─ This option is not feasible
Option 4: Full diversion to Tory St/Tasman St
- Wallace St and Wright St both closed to through traffic
- Advantages
─ No additional traffic on Wright St
- Ruled out because
─ Poor connection to road network, particularly north end ─ Very long diversion ─ Tory St / Tasman St ill-suited to anticipated traffic flows ─ More affected residents, more parking displaced ─ Public transport impact significant – long route change
Option 5: NB Wright St, SB Tasman St
- Wallace St closed between Hargreaves St and John St
- Advantages
─ Only northbound traffic on Wright St
- Ruled out because
─ Same reasons as Option 4 ─ Complex diversion due to diverse routes NB/SB ─ Max number of affected residents
Option 6: Full Diversion Wright St
- Wallace St closed between Hargreaves St and John St
- Disadvantages
─ Significantly increased traffic on Wright St
- Advantages
─ Shortest diversion length – least impact on residents/parking ─ Least impact on bus operations and bus users ─ Minimal infrastructure change required ─ This is by far the safest and least disruptive option
Wright St diversion
- Traffic diverted to Wright St at
Hargreaves St and John St
- Car parking removed on one side
- f Wright St
- Buses will use the route
- Travel times reliable
- Work can proceed safely
- Overall disruption shortened with
this diversion
- Wright St diversion route
- Wallace St work area
Wright St bus route
- Testing/Investigations
─ Have modelled longest buses using vehicle tracking software ─ Have physically trialled the longest buses by driving the route ─ Wires lifted for double deckers ─ To do: Adjust road camber at corners in Hargreaves St ─ To do: Test drive double deckers ─ Buses will pass each other on Wright St ~16 times a day
- Controls
─ Bus stop will be near the laneway to Wallace St ─ Signalised crossing for pedestrians as per Wallace St ─ Additional lighting if required
Wright St diversion bus tracking
Hargreaves St / Wright St intersection John St / Wright St intersection
Impacts of diversion on Wright St residents
- The additional traffic will be significantly greater than existing
flows - expect reduction on current Wallace St traffic
- Pedestrian crossing installed near alley through to Wallace
St for safe passage across Wright St
- Bus stop moved from outside Wallace St dairy to beside
new pedestrian crossing in Wright St
- Car parks removed on one side (uneven numbers) to
provide space for two way traffic
- Rubbish collection will be on a different schedule
What can be done to reduce the impact?
- Traffic calming measures such as reduced speed limits,
traffic lights and minimum lane widths
- VMS boards on feeder routes encouraging people to use
Adelaide Road as an alternative
- Advertising campaign on radio, social media and other
- nline channels telling people to avoid the area
- Asking delivery companies, taxis, ubers to use alternate
routes
- Coupon parking will be changed to residents’ parking in
adjacent streets – surveys indicate unused parks exceed ‘lost’ parks
Impacts of work on Wallace St residents
- Access to properties from each end of the work site (no
through traffic)
- Work site moving along the street, different residents
impacted as work progresses
- No parking on street adjacent to work sites
- Full communication with affected residents and businesses
- 1-1 engagement to address individual issues for access that
arise (as we have been doing in Hargreaves St)
- Pedestrians will need to use the formal crossing points, this
will add distance to some people’s walks
Time considerations in diversion options
Alternative 1 – 43 week diversion onto Wright St
11 week full diversion (bulk main works) Nov 2019 – Feb 2020 + 32 week NB diversion (sewer/local water) Feb 2020 – Sep 2020
- r
Alternative 2 – 23 week diversion onto Wright St
23 week full diversion (bulk main/sewer/local water) Nov 2019 – May 2020