october 2017
play

October 2017 Dave Lovell Programme Manager @ networkrailwest - PowerPoint PPT Presentation

October 2017 Dave Lovell Programme Manager @ networkrailwest Organisational Update Paul Stanford - RDD Simon Roberts - PCM Peter Corneck - PCM Stuart Hitch Suzanne Renton Head of Engineering Head of Prog Integration Simon Roberts SPM


  1. October 2017 Dave Lovell Programme Manager @ networkrailwest

  2. Organisational Update Paul Stanford - RDD Simon Roberts - PCM Peter Corneck - PCM Stuart Hitch Suzanne Renton Head of Engineering Head of Prog Integration Simon Roberts – SPM Dave Lovell – SPM Anthony Bolton – SPM Scott Pillinger – SPM SP&C Enhancements WRaTH B & C

  3. PDSW Update Suzanne Renton

  4. CP6 Statement of Funds Available …announced last week

  5. CP6 Statement of Funds Available …announced last week, so what? 47.9 billion pounds – 24% more than the CP5 amount Of the 47.9 billion, there is 18 billion for renewals The amounts will be refined during the regulatory process By summer 2018 there will be detailed draft amounts for the 2019 to 2024 period for consultation but Network Rail Board sighted that dialogue with the supply market needs be underway Budgets will be set at route level, as part of devolution of accountability and authority to routes The regulatory process will conclude with a final determination in October 2018 Work has started with Route Asset Managers

  6. Ex2NA The story so far…

  7. The vulnerable coast…

  8. ‘Critical resilience of this iconic railway line’

  9. The vulnerable coastline… Year Severe Event Extreme Event Likelihood Likelihood 2014 1 in 3.5 years 1 in 25 years 2065 1 in 0.75 years 1 in 4 years 2115 1 in 0.38 years 1 in 1.5 years Severe Event: 2-7 day closure of the Extreme Event: Several month closure railway line of the line; similar to events in 2014 “We cannot accurately predict when a failure will occur, it may be tomorrow, next year or in 10 years, what we do know is that the cliffs will fall again and the sea wall will collapse”

  10. Work undertaken since 2014 Following 2014 events NR spent £45-£50m on putting the railway back and an additional £20m of tactical strengthening close to the breach NR commission a £3m study at the end of 2014 which included a detailed engineering study, Drone Surveys, Ground investigations and Roped access surveys

  11. The study area: Exeter to Newton Abbot

  12. Preferred option: Section 3 Section 3: Kennaway Tunnel to Parsons Tunnel

  13. Preferred option: Section 3 Section 3: Kennaway Tunnel to Parsons Tunnel • Action required Immediately and also CP7 & 12. Existing sea defences will become vulnerable as sea levels rise, primary hazard is the geotechnical hazard from rock falls • Options Consist of: New mass concrete sea wall, Rock revetment, and Tunnel portal protection (rock fall protection)

  14. Preferred option: Section 3 Section 3: Kennaway Tunnel to Parsons Tunnel

  15. Preferred options: Section 4 Section 4: Parsons Tunnel to Teignmouth

  16. Preferred options: Section 4 Section 4: Parsons Tunnel to Teignmouth Action required Immediately. Existing sea defences will become vulnerable as sea levels rise, primary hazard is the geotechnical hazard Two plausible solution to achieve resilience in this area….. Preferred option consists of: Realigned railway from geotechnical hazard; new rock revetment to protect reclaimed land; stabilisation of cliffs

  17. Preferred options: Section 4 Section 4: Parsons Tunnel to Teignmouth Short list options – “Advance the Line”

  18. Preferred options: Section 4 Section 4: Parsons Tunnel to Teignmouth Short list options – “Advance the Line”

  19. Discounted option: Section 4 Section 4: Parsons Tunnel to Teignmouth Short list options – Cliff Regrade

  20. Since October 2016: The results of the Geo-Environmental Review are launched at Dawlish Warren on 17 November 2016

  21. October – November 2016: drop-in sessions for the public are held. Events take place in Dawlish Warren, Exeter, Teignmouth, Torquay, Plymouth and Truro. Nearly 1,000 people attend.

  22. 20 October 2016: Secretary of State for Transport Chris Grayling visits Dawlish “There is no option for the future that allows our railway links to Devon and Cornwall to be cut […] That has to be an absolute commitment from the government. We can't leave this railway link in a position where it is not open for the future.”

  23. 17 November 2016: £10,000,000 given to ongoing study works (on top of £5,000,000 already made available .”

  24. Section 2 – Our proposal

  25. Project Delivery The next phase of development is divided into three packages: Marine Parade [new section of sea wall between Kennaways Tunnel and Dawlish Water] Work to be undertaken includes: • Ground investigation / structural assessment of site and wall • Environmental surveys • Outline design for new wall and drainage • Tenders will be issued summer 2017 • Contract awarded early 2018 • Contract duration approx. one year

  26. Project Delivery Package 1 – Marine Parade [new section of sea wall between Kennaways Tunnel and Dawlish Water]

  27. Project Delivery Parson’s Tunnel Portal Protection [new rockfall shelter] & CBU 17. Work to be undertaken includes: • Ground investigation of site • Environmental surveys • Outline design for rockfall Shelter and cliff stabilisation • Tenders to be issued summer 2017, contract award early 2018. • Contract duration approx one year

  28. Scheme Concept Development: Geotechnical Proposed Intervention Works: Section 3 (Cliff Behaviour Unit 17) – Parsons Tunnel portal extension works and a rock anchor / netting system is to be developed.

  29. Project Delivery Parsons Tunnel to Teignmouth [railway on reclaimed land] Offshore ground investigation Environmental Impact Assessment Options for type of defence structure (wall vs revetment vs hybrid) Outline design for new sea defence structure Development of construction methodology & programme, highlighting logistical issues and key risks Tenders to be issued September 2017 Contract award spring 2018. Contract duration approx 16 months

  30. Scheme Concept Development: Geotechnical The recently completed geomorphological studies and ground investigations have identified that 2 sections of the Sea Cliff need to be prioritised in CP6. These 2 Sections encompass a discrete section of rock cutting within Section 3 located at the northern end of Parson’s Tunnel (designated as Cliff Behaviour Unit 17) and all sea cliffs within Section 4.

  31. Scheme Concept Development: Geotechnical Proposed Intervention Works: Section 4 (Parsons Tunnel to Teignmouth) – Land reclamation and stabilisation of the sea cliffs by rock anchoring and netting and the construction of buttresses.

  32. Project Delivery Package 3 – Parsons Tunnel to Teignmouth [railway on reclaimed land]

  33. Scheme Concept Development: Offshore No specific offshore structures will be constructed as part of the proposed resilience works. However, the following surveys / studies will be incorporated into future phases of work: • Hydrodynamic Studies (Tidal Studies) • Wave Studies (HR Wallingford) • Benthic Surveys • Topographical & Bathymetric Surveys

  34. Communicating with Stakeholders

  35. Communication with MPs Annual updates to APPG on South West Rail – more frequently if requested, plus ad hoc meetings when significant events warrant

  36. Communication with MPs Direct one-to-one or email updates to individual MPs, either when significant moments in the programme are passed (funding announcements, strategic plans etc) or more frequently when significant work packages are underway

  37. Communication with Local Authorities and the PRTF PRTF will be our primary point of contact for major announcements, joint statements etc. We will support all Local Authorities & LEPs and work with them for issues which affect specific areas and local concerns (see also Communications with Communities and Individuals).

  38. Ex2NA Team Project Manager Scheme Project Scheme Project Manager Manager Senior Project Consents Environmental Commercial Construction Engineer Civils Manager Specialist Manager Manager (DPE) Coastal Engineer Geo-Technical Engineer A2CO Changes 3 8

  39. Thank you Any questions? @ networkrailwest

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend