Building Johnson County Governments Largest Project Tomahawk Creek - - PowerPoint PPT Presentation

building johnson county government s largest project
SMART_READER_LITE
LIVE PREVIEW

Building Johnson County Governments Largest Project Tomahawk Creek - - PowerPoint PPT Presentation

Building Johnson County Governments Largest Project Tomahawk Creek Wastewater Treatment Facility Why Wastewater Treatment 2 About JCW Located in northeast Kansas Established in 1945 Enterprise funded 220 employees 6


slide-1
SLIDE 1

Building Johnson County Government’s Largest Project – Tomahawk Creek Wastewater Treatment Facility

slide-2
SLIDE 2

Why Wastewater Treatment

2

slide-3
SLIDE 3

About JCW

  • Located in northeast Kansas
  • Established in 1945
  • Enterprise funded
  • 220 employees
  • 6 WWTFs
  • 32 pump stations
  • 2,200 miles of sewer
  • 500,000+ residents served
  • 60 million gallons treated

each day

slide-4
SLIDE 4
slide-5
SLIDE 5

About Tomahawk Creek WWTF

  • Leawood. Mission Rd and Lee Blvd
  • Established in 1955
  • Trickling Filter Facility
  • 1980s Linking Interceptor
  • 7 mgd onsite/10 mgd to KCMO
  • 150,000 – 190,000 residents
slide-6
SLIDE 6

Blue River Basin

Kansas Missouri

slide-7
SLIDE 7

Drivers for Upgrade

  • Age of equipment
  • New regulations for

water quality

  • Increasing operational costs
slide-8
SLIDE 8

Planning Process

  • Previous Studies 2006 and 2013

– Evaluated 8 Alternatives – Evaluated 0 MGD, 10 MGD, and 19 MGD – Recommend 19 MGD Option

  • Project Definition Phase 2014-2015
  • Design and GMP Development 2017 – 2018
  • Construction 2018 - current
slide-9
SLIDE 9

Missouri River Load Reductions Relative to Existing Condition Baseline

9

slide-10
SLIDE 10

All flow Some Flow No Flow

Financial Evaluation of Options

slide-11
SLIDE 11

Operating Cost Comparison

Reduced Costs: $453 Million

slide-12
SLIDE 12

Goals for Long-Term Investment

  • Preserve high quality of life
  • Improve water quality
  • Provide the most cost-

effective long-term solutions for customers

slide-13
SLIDE 13

Existing Tomahawk Creek WWTF

slide-14
SLIDE 14

Preliminary Design Concept

  • Reuse Influent Pumping

Station and Digester Complex

  • IFAS BNR Basins & Blower

Building

  • Separate Sludge

Processing

  • Dual Purpose

Compressible Media Filters

  • Disinfection and

Reaeration Facilities

  • Concrete Lined Excess

Flow Holding Lagoon

slide-15
SLIDE 15

Dual Purpose Compressible Media Filters

slide-16
SLIDE 16

Tomahawk Creek Proposed Delivery Methods

slide-17
SLIDE 17

Why CMAR for this Project

  • Collaboration between All

parties

  • Signiant Pre-design already

completed

  • High risk, complicated project
  • Earlier cost certainty
  • Optimize design
slide-18
SLIDE 18

Tomahawk Creek Proposed CMAR Schedule

slide-19
SLIDE 19

Value Engineering led to Design Evolution

slide-20
SLIDE 20

Evolution of the Site

April 2017 July 2017

slide-21
SLIDE 21

Facility Protection Without Flood Rise

slide-22
SLIDE 22

Bedrock is at Different Elevations at Site

Rock Fill Only Piers Only Piers with Rock Fill

slide-23
SLIDE 23

Power Limitations were Addressed

slide-24
SLIDE 24

BIM / VR Tools were Utilized for Project

slide-25
SLIDE 25
slide-26
SLIDE 26

Bluebeam was Used to Review Documents

slide-27
SLIDE 27

VE Analysis Continues during Construction

slide-28
SLIDE 28

Construction Statistics

  • 250,000 CY of Earth to Move
  • 53,000 CY of Structural Concrete
  • 3 Miles of Electrical Ductbank
  • 110,000 LF of Pipe (Above & Below

Grade)

slide-29
SLIDE 29

Plant Flow Diagram

slide-30
SLIDE 30

Startup Process Overview

slide-31
SLIDE 31

BNR Basin & Basin Blower Building

slide-32
SLIDE 32

Filter Disinfection Complex

slide-33
SLIDE 33

Solids Processing Building

slide-34
SLIDE 34

Administration Building

slide-35
SLIDE 35

Construction Challenges

  • 2018 & 2019 - Wettest Water

Calendar Year in Kansas (57.88 inches)

  • Adjusting to COVID-19

Procedures

  • Tight Construction Footprint
  • Unforeseen Rubbish During

Excavations

slide-36
SLIDE 36

Project Successes

MOPO: Collection System Diversion Evergy Substation Energized

slide-37
SLIDE 37

Facility Startup

  • Coordination Meetings w/ Key

Personnel

  • Energization & LOTO Plan
  • System Startup Plans
  • Key Construction Milestones
slide-38
SLIDE 38
slide-39
SLIDE 39

Lessons Learned

  • Know your site and existing facilities
  • Exploratory digging
  • SCADA Screen Development

– Big project – a lot to take on at once

  • Engage CMAR early
  • Communication, Trust, Teamwork
slide-40
SLIDE 40

For Updates: www.jcwtomahawk.com

slide-41
SLIDE 41

Exp xpec ectation ions