Oak Chan Elementary School Modernization Project SCHOOL - - PowerPoint PPT Presentation

oak chan elementary school modernization project
SMART_READER_LITE
LIVE PREVIEW

Oak Chan Elementary School Modernization Project SCHOOL - - PowerPoint PPT Presentation

Oak Chan Elementary School Modernization Project SCHOOL PRESENTATION MARCH 30, 2017 OVERALL SITE PLAN PROJECT OVERVIEW Phase 1 Milestone #1 (April 17 July 31, 2017): Grading, Placement of all temporary portable classroom, restroom,


slide-1
SLIDE 1

Oak Chan Elementary School Modernization Project

SCHOOL PRESENTATION MARCH 30, 2017

slide-2
SLIDE 2

OVERALL SITE PLAN

slide-3
SLIDE 3

PROJECT OVERVIEW

Phase 1 – Milestone #1 (April 17 – July 31, 2017):

Grading, Placement of all temporary portable classroom, restroom, administration and student care buildings, including all utilities

Multipurpose (Building B) modernization Phase 1 – Milestone #2 (June – December 2017):

Administration (Building A) modernization Phase 1 – Milestone #3 (June 2017 – July 2018):

Construction of Buildings C-10-plex Classroom, D – Learning/Media Center, E – 8-plex Classroom and F - Kindergarten Phase 2 – Milestone #1 (June 2018 – July 2018):

Hardcourt, apparatus yard, parking lot Phase 2 – Milestone #2 (July 2018 – September 2018)

Removal of temporary trailers, playfield restoration

slide-4
SLIDE 4

Phase and Milestone Schedule

slide-5
SLIDE 5

SITE PLAN – April and May, 2017 & July – September 2018 – The entire playfield

slide-6
SLIDE 6

SITE PLAN – Summer 2017

slide-7
SLIDE 7

SITE PLAN – School Year 2017 - 2018

slide-8
SLIDE 8

SITE PLAN – Summer 2018

slide-9
SLIDE 9

Temporary Classroom & Restroom Buildings

slide-10
SLIDE 10

Administration Building

slide-11
SLIDE 11

Kindergarten

slide-12
SLIDE 12

Unit D - Learning/Media Center Building

slide-13
SLIDE 13

Exterior

slide-14
SLIDE 14

QUESTIONS & ANSWERS