Oak Chan Elementary School Modernization Project
SCHOOL PRESENTATION MARCH 30, 2017
Oak Chan Elementary School Modernization Project SCHOOL - - PowerPoint PPT Presentation
Oak Chan Elementary School Modernization Project SCHOOL PRESENTATION MARCH 30, 2017 OVERALL SITE PLAN PROJECT OVERVIEW Phase 1 Milestone #1 (April 17 July 31, 2017): Grading, Placement of all temporary portable classroom, restroom,
SCHOOL PRESENTATION MARCH 30, 2017
Phase 1 – Milestone #1 (April 17 – July 31, 2017):
Grading, Placement of all temporary portable classroom, restroom, administration and student care buildings, including all utilities
Multipurpose (Building B) modernization Phase 1 – Milestone #2 (June – December 2017):
Administration (Building A) modernization Phase 1 – Milestone #3 (June 2017 – July 2018):
Construction of Buildings C-10-plex Classroom, D – Learning/Media Center, E – 8-plex Classroom and F - Kindergarten Phase 2 – Milestone #1 (June 2018 – July 2018):
Hardcourt, apparatus yard, parking lot Phase 2 – Milestone #2 (July 2018 – September 2018)
Removal of temporary trailers, playfield restoration