nwr lpe update
play

NWR LPE Update WSDOT NWR Local Programs Frequently Asked ROW - PDF document

NWR LPE Update WSDOT NWR Local Programs Frequently Asked ROW Questions Mehrdad Moini, PE (206) 440-4734, moinim@wsdot.wa.gov 7/2019 Does My Project Need ROW ? Can your project be built In its entirety within current ROW? Do you require


  1. NWR LPE Update WSDOT NWR Local Programs Frequently Asked ROW Questions Mehrdad Moini, PE (206) 440-4734, moinim@wsdot.wa.gov 7/2019 Does My Project Need ROW ? • Can your project be built In its entirety within current ROW? • Do you require and temporary construction easements? TCE’s often number one issue for Ad delays. • Do you require a permit? • Is the temporary permit between another governmental agency? • Review Chapter 25 LAG ‐ Section 25.4 (ROW Acquisition) • https://www.wsdot.wa.gov/publications/manuals/fulltext/M3 6‐63/Lag25.pdf • LTAP Training Opportunities – • When in Doubt……….. Call David!!!! Early and Often! 2 What is required to start ROW acquisition w ith Federal Dollars? • Project is on the STIP • Approved NEPA – (current and less than 3 years old) ‐ • PFE – Project Funding Estimate – Project Funding Estimate (PFE) is a detailed parcel‐by‐parcel estimate of total expected right of way acquisition costs and is used to obtain authorization and funding for the project. A PFE is required if any appraisals are planned to be waived, and the Agency intends to prepare waiver valuations for any of the parcels on the project. A PFE is based on market transactions (sales) that reflect the current real estate market. Ideally, it is completed by an appraiser, an appraisal reviewer, and a relocation expert. Other ROW staff with appropriate experience, including qualified consultants, may also prepare a PFE. https://www.wsdot.wa.gov/publications/manuals/fulltext/M36‐63/Lag25.pdf • Approved ROW Plans – A ROW Plan indicating the property required to build and maintain the transportation project is required. A right of way plan is a valuable visual‐aid tool for negotiators, appraisers, and attorneys involved in acquisition transactions. It also helps property owners understand why and how their properties are being acquired. https://www.wsdot.wa.gov/publications/manuals/fulltext/M36‐63/Lag25.pdf • Approved relocation plans ‐ 3 1

  2. NWR LPE Update Do state funded projects need a ROW Certification While there is an expectation that the uniform process will be followed on State Funded projects a certification process by Local Programs is not required. 4 What is ROW Certification? ywvutsrqponmlkjihgfedcaWTSRQPONMLIFDC • A statement that sufficient property rights to construct, operate, and maintain the facility as shown on the PS&E have been obtained • ROW is clear of encroachments • ROW was been acquired with the URA and /or the Federal Land Transfer Process 5 What are the three kinds of ROW certifications ? • Certificate 1 (most preferred) • https://www.wsdot.wa.gov/publications/manuals/fulltext/M3 6‐63/Lag25.pdf • Certificate 2 • https://www.wsdot.wa.gov/publications/manuals/fulltext/M3 6‐63/Lag25.pdf • Certificate 3 (least preferred) • https://www.wsdot.wa.gov/publications/manuals/fulltext/M3 6‐63/Lag25.pdf 6 2

  3. NWR LPE Update What is a Certification 1 ? • All necessary rights have been acquired o Deed or physical possession and use obtained … Legal ownership not mandatory o Trial or appeal cases may be pending but legal possession • All occupants have vacated the ROW • Right to enter on all land • Right to remove salvage or demolish any remaining improvements • WSDOT does not allow CERT 1 on a possession and use agreement 7 What is a Certification 2 ? • Right to occupy all ROW o Trial or appeal of some parcels may be pending o Some parcels have rights to entry only. Possession and use or legal ownership has not been obtained. • All occupants have vacated the ROW • Right to enter on all land • Right to remove salvage or demolish any remaining improvements 8 What is a certification 3 ? • All ROW not acquired • Acquisition of a few parcels not complete • All occupants have had replacement housing made available per 49 CFR 24.204 but may not have moved • Justification is required o Full explanations and reasons o Identify each outstanding parcel o Provide realistic date of physical occupancy and use TWO certification options Excepted Parcel and Time Based 9 3

  4. NWR LPE Update Certification 3 cont. Time based • Agreement that payment and relocation be completed prior to bid opening • Allows use of time between ad and bid opening Excepted Parcel • Must notify bidders of locations where right of occupancy not obtained • Contractors must work around the parcel • Rarely used Certification 3 should be an exception 10 Who do I contact if I have ROW questions? • David Narvaez HQ’s Local Programs for NWR (206) 440-4205, narvaed@wsdot.wa.gov • Mehrdad Moini, PE – Local Programs Engineer (206) 440‐4734, moinim@wsdot.wa.gov • Renae Larson – Snohomish/ N. King Co • Sayma Rahman – S. King Co. • Tareq Al‐Zeer – Skagit, Whatcom, Island & San Juan Co. 11 Questions 12 4

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend