nts flexibility capacity product current enduring
play

NTS Flexibility Capacity Product current enduring proposals and - PowerPoint PPT Presentation

NTS Flexibility Capacity Product current enduring proposals and some alternatives Enduring Offtake Working Group 18 th January 2006 (nks/draft v0p2 18/01/06) Background and presentation objective the current NTS Exit Flexibility


  1. NTS Flexibility Capacity Product – current enduring proposals and some alternatives Enduring Offtake Working Group 18 th January 2006 (nks/draft v0p2 18/01/06)

  2. Background and presentation objective … the current NTS Exit Flexibility Capacity product was developed as part of the DN sales process … implementation of the enduring regime deferred to permit more time to consider the proposed framework …many industry participants have advocated consideration of alternative approaches … this presentation describes the current NTS Exit Flat and Flexibility proposal and some refinements and alternatives

  3. The NTS Exit Capacity Products & Alternatives � “Current” Flat and Flexibility Capacity products � Refinements � Flat and “Increased Flexibility tolerance” product � Expanding flexibility model � Single product model � User high/low flexibility model � Alternatives � “Old NTS Exit Capacity Product” (“NERA” Model) …the above is not intended to be an exhaustive list of possibilities

  4. Current NTS Flat and Flexibility Capacity products … the definitions of the above products have already been implemented in the UNC … DNs secure NTS Exit Capacity products via the Offtake Capacity Statement (OCS) application and allocation processes If implemented in the enduring regime we assume overrun arrangements will be in place to encourage connectees at offtake points to offtake in a manner consistent with their NTS Exit Capacity holdings

  5. Understanding the “flexibility utilisation” assessment principle …. Flexibility utilisation = cumulative offtake to 22:00 – (2/3) of daily flow Offtake profile Average flow rate Throughput = 24*Av flow rate = Flexibility 36 utilisation = 3 06:00 22:00 06:00 Product designed to reflect linepack impact at 22:00; time of maximum system stress

  6. User booking requirements … expectation Users will book NTS “Flat” and “Flexibility” capacity levels required to satisfy all their requirements … may require users to consider both their highest throughput and highest flexibility utilisation requirements Flexibility utilisation NTS Exit Flexibility Capacity booking X (36,3) Feasible range 0 Demand – end of day flow NTS of Flat Capacity “flat” and “flex” offtakes booking (avoiding overruns)

  7. Addressing metering offtake uncertainty Flexibility utilisation = cumulative offtake to 22:00 ( cumulative offtake to 22:00 ) – (2/3) of daily flow * (1 – tolerance) Tolerance set at 1.5% Offtake profile (as implied by meter data) 06:00 22:00 06:00

  8. Flat and “increased tolerance” flexibility … even users with low levels of offtake flow rate variation may have some “flexibility utilisation” … the “tolerance” could be expanded such that users, who might only have a moderately higher average offtake flow rate first 16 hours than over the full day, might not be required to book “flexibility”

  9. Eliminating “flex holding requirement” for low variation users Flexibility utilisation = cumulative offtake to 22:00 ( cumulative offtake to 22:00 ) – (2/3) of daily flow * (1 – tolerance) Tolerance set at [6]% Offtake profile (as implied by meter data) 06:00 22:00 06:00

  10. Expanding flexibility product … many users are unlikely to have coincident peak flexibility and daily offtake requirements … this may force users to “over book” a combination of “flat” and “flexibility” capacity … so there might be scope for contemplating a “Flexibility” entitlement that expands when a user is not fully utilising his “Flat” holding

  11. User booking requirements … expectation Users will book NTS “Flat” and “Flexibility” capacity levels required to satisfy their requirements on “peak throughput” day … unused transmission capacity “automatically converted” into extra Flexibility availability based on a transmission:flexibility substitution ratio Extension of feasible range derived from Flexibility transmission:flexibility substitution utilisation NTS Exit Flexibility Capacity “peak” booking 0 Feasible range Demand – end of day flow NTS Flat of Capacity booking “flat” and “flex” offtakes (avoiding overruns)

  12. .. the “expanding flexibility product” may facilitate efficient User booking? Retains the concept of separate products but Users book a “requirement under peak transmission conditions” ie a flat and flex combination but have increased flex availability off-peak arising from transmission/flexibility substitutability Flexibility entitlement Line derived by assuming a [4.5 : 1] transmission : flexibility substitution ratio Flexibility booking Peak Transmission throughput throughput booking User flex entitlement = flex booking + [2/9] (peak throughput booking – throughput)

  13. “Single product model” … the preceding model still requires users to book 2 separate products … a further simplification might be to contemplate a single “transmission capability” parameter to determine a single “product” booking … assessment of product utilisation made in respect of two dimensions: throughput against single “transmission capability” booking flex usage against a derived flex “entitlement”

  14. .. Developing the simple single parameter booking regime? Single Flexibility parameter entitlement Utilisation assessed in two dimensions: -transmission - Throughput capability - Flexibility booking Feasible range of throughput and flexibility utilisation throughput User flex entitlement = [2/9] (transmission capability booking – throughput)

  15. High/low flexibility user choice model … some users may have a requirement for fairly significant high offtake flow rate variations whilst others might have very low requirements … Users might therefore be offered the opportunity to determine their highest day throughput requirement but to choose whether they would like to purchase a high flexibility or low flexibility dimension to their booking

  16. High/low flexibility choice model Flexibility utilisation Implied NTS High flex option Flexibility holding Feasible range Flex entitlement = of flex and throughput 0 Demand – end of day flow combinations [ 20 ]% of NTS Transmission Transmission Capacity Booking Capacity Booking Flexibility utilisation Low flex option Implied NTS Flexibility holding Flex entitlement = Feasible range 0 Demand – end of day flow [ 5 ]% of of flex and throughput NTS Transmission Transmission combinations Capacity Booking Capacity Booking

  17. … all of the models presented so far have been derivatives based upon the proposed flexibility product … there are alternatives that do not involve the assessment of a “flexibility overrun”

  18. “Old NTS Exit Capacity product” (“NERA” model) … the NTS Exit Capacity product (as currently applies in respect of Direct Connects) requires a single dimension of the transportation service to be booked; an End of Day quantity corresponding to 24 times the Max Hourly Quantity No explicit cap on “flexibility” utilisation Flexibility utilisation Feasible range of throughput and “flexibility” 0 Demand – end of day flow utilisations NTS Transmission Capacity Booking

  19. “Old NTS Exit Capacity product” (“NERA” model) … the NTS Exit Capacity product (as currently applies in respect of Direct Connects) permits effectively unfettered access to offtake flow rate variations … the system has not been designed to accommodate all possible offtake flow rate variations … traditionally this has been managed via restrictions to DN offtake flow rate variations … unfettered offtake flow rate variation would require a bigger system, and/or alternative arrangements to limit offtake flow variations, or certainty that offtake flow rate variations would not exceed capability

  20. Next steps There may be some refinements/variants or alternatives to the current “flat and flexibility” that are worthy of consideration Are there any particular options that EOWG wish to focus upon? .. or is it best to seek to explore more detail in respect of the current flat/flexibility proposal to ascertain its effectiveness against stated objectives?

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend